MBA Knowledge Base

Business • Management • Technology

Home » Management Case Studies » Case Study: Wal-Mart’s Distribution and Logistics System

Case Study: Wal-Mart’s Distribution and Logistics System

As the world’s largest retailer with net sales of almost $419 billion for the fiscal year 2011, Wal-Mart is considered a “best-in-class” company for its supply chain management practices . These practices are a key competitive advantage that have enabled Wal-Mart to achieve leadership in the retail industry through a focus on increasing operational efficiency and on customer needs. Wal-Mart’s corporate website calls “logistics” and “distribution” the heart of its operation, one that keeps millions of products moving to customers every day of the year.

Wal-Mart’s highly-automated distribution centers, which operate 24 hours a day and are served by Wal-Mart’s truck fleet, are the foundation of its growth strategy and supply network. In the United States alone, the company has more than 40 regional distribution centers for import flow and more than 140 distribution centers for domestic flow. When entering a new geographic arena, the company first determines if the area will be able to contain enough stores to support a distribution center. Each distribution center supports between 75 to 100 retail stores within a 250-mile area. Once a center is built, stores are gradually built around it to saturate the area and the distribution network is realigned to maximize efficiencies through a process termed “reoptimization”. The result is a “trickle-down” effect: trucks do not have to travel as far to retail stores to make deliveries, shorter distances reduce transportation costs and lead time, and shorter lead time means holding less safety inventory. If shortages do occur, replenishment can be made more quickly because stores receive daily deliveries from distribution centers.

Wal-Mart's Distribution and Logistics System

An important feature of Wal-Mart’s logistics infrastructure was its fast and responsive transportation system. The distribution centers were serviced by more than 3,500 company owned trucks. These dedicated truck fleets allowed the company to ship goods from the distribution centers to the stores within two days and replenish the store shelves twice a week. The truck fleet was the visible link between the stores and distribution centers. Wal-Mart believed that it needed drivers who were committed and dedicated to customer service. The company hired only experienced drivers who had driven more than 300,000 accident-free miles, with no major traffic violation.

Wal-Mart truck drivers generally moved the merchandise-loaded trailers from Wal-Mart distribution centers to the retail stores serviced by each distribution center. These retail stores were considered as customers by the distribution centers. The drivers had to report their hours of service to a coordinator daily. The coordinator scheduled all dispatches depending on the available driving time and the estimated time for travel between the distribution centers and the retail stores. The coordinator informed the driver of his dispatches, either on the driver’s arrival at the distribution center or on his return to the distribution center from the retail store. The driver was usually expected to take a loaded truck trailer from the distribution center to the retail store and return back with an empty trailer. He had to dispatch a loaded truck trailer at the retail store and spend the night there. A driver had to bring the trailer at the dock of a store only at its scheduled unloading time, no matter when he arrived at the store. The drivers delivered the trailers in the afternoon and evening hours and they would be unloaded at the store at nights. There was a gap of two hours between unloading of each trailer. For instance, if a store received three trailers, the first one would be unloaded at midnight (12 AM), the second one would be unloaded at 2 AM and the third one at 4 AM. Although, the trailers were left unattended, they were secured by the drivers, until the store personnel took charge of them at night. Wal-Mart received more trailers than they had docks, due to their large volume of business.

Because Wal-Mart’s fast, responsive transportation operations are such a major part of the company’s successful logistics system, great care is taken in the hiring, training, supervising, and assigning of drivers’ schedules and job responsibilities. From the onset of his retailing career, Wal-Mart founder Sam Walton recognized the importance of hiring experienced people and of building loyalty not only in his customers but also in his employees. The company hires only experienced drivers who have driven more than 300,000 accident-free miles and whom it believes will be committed to customer service. Its retail stores are considered important “customers” of the distribution centers. As stated in the “Private Fleet Driver Handbook” that each driver is given a copy of, drivers are expected to be “polite” and “kind” when dealing with store personnel and others. In addition to containing a driver’s code of conduct, the Private Fleet Driver Handbook gives instructions and rules for following pre-planned travel routes and schedules, the responsible unloading of a truck trailer at a retail store, and the safe-guarding of Wal-Mart’s property. For example, although drivers deliver loaded trailers in the afternoon and evening hours, a trailer can be brought to the store’s docks only at its scheduled unloading time. Because unloading is done at two-hour intervals during the night, a driver is expected to spend the night, returning to the distribution center at a pre-scheduled time with an empty trailer. Coordinators closely monitor the detailed records of each driver’s activities for adherence to rules. Violations are dealt with according to handbook procedures, which include employee education to prevent future occurrences of incorrect actions. By effectively managing every aspect of its transportation operations and treating its drivers fairly, Wal-Mart gets results that are unrivaled in the logistics arena. This philosophy parallels the successful coaching style of New York Giant’s football coach Tom Coughlin who believes that rules are more than just discipline. Rules are a key to consistency, which leads to preparedness, which then leads to proper execution.

To make its distribution process more efficient, Wal-Mart also made use of a logistics technique known as ‘cross-docking.’ In this system, the finished goods were directly picked up from the manufacturing plant of a supplier, sorted out and then directly supplied to the customers. The system reduced the handling and storage of finished goods, virtually eliminating the role of the distribution centers and stores. There were five types of cross-docking.

  • Opportunistic Cross docking – In this method of cross docking, the exact information about where the necessary good should be shipped and from where it should be procured and exact quantity which will be sent was necessary. This method of cross docking has allowed the company to ship directly the goods, necessary retail clients, not storing them in warehouse bins or shelves. Opportunistic cross docking could also be used when the warehouse software of management installed by the retailer, has set ready it, that the specific product was ready to moving and could be moved immediately.
  • Flow-through Cross docking – In this type of cross docking, there was a constant inflow and outflow of the goods from the distribution center. This type of cross docking was mostly suitable for the perishable goods which had very short interval of time, or the goods which were difficult to be kept in warehouses. This cross docking system was mainly accompanied by supermarkets and other retail discount stores, especially for perishable items.
  • Distributor Cross docking – In this type of cross docking, the manufacturer has delivered the goods to directly to retailer. No intermediaries have been involved in this process. It has allowed the retailer to save a major portion of the expenses in the form of storage. As the retailer should not support the distribution center for storage various kinds of the goods, he has helped it to save warehouse costs. The lead time for the delivery of goods from the manufacturer to the consumer was also drastically reduced. However, this method had some disadvantages too. Expenses of transportation both for the manufacturer and for the retailer tended to increase during time when the goods have been required to be transported to different locations several times. Besides, the transportation system should be very fast. Otherwise, the purpose of cross docking has been lost. The transportation system should be also highly responsive and to take the responsibility for delays in delivery of the goods. The retailer was at a greater risk. He has lost that advantage to sharing risks with the manufacturer. This type of cross docking was suitable only for those retailers who had the big distributive network and could be used in situations when goods had to be delivered in a short span of time.
  • Manufacturing Cross docking – In Manufacturing cross docking, these cross docking facilities served the factories and acted as temporary and “mini warehouses.” Whenever a manufacturing company required some parts or materials for manufacturing a particular product, it was delivered by the supplier in small lots within a very short span of time, just when it was needed. This helped reduce the transportation and warehouse costs substantially.
  • Pre-Allocated Cross Docking – Pre-allocated cross docking is very much like the usual cross-docking, except that in this type of cross docking, the goods are already packed and labeled by the manufacturer and it is ready for shipment to the distribution center from where it is sent to the store. The goods can be delivered by the distribution center directly to the store without opening the pack of the manufacturer and re-packing the goods. The store can then deliver the goods directly to the consumer without any further repacking. Goods received by the distribution center or the store are directly sent into the outbound shipping truck, to be delivered to the consumer, without altering the package of the good. Cross docking requires very close co-ordination and co-operation of the manufacturers, warehouse personnel and the stores personnel. Goods can be easily and quickly delivered only when accurate information is available readily. The information can be managed with the help of Electronic Data Interchange (EDI) and other general sales information.

In cross docking, requisitions received for different goods from a store were converted into purchase or procurement orders. These purchase orders were then forwarded to the manufacturers who conveyed their ability or inability to supply the goods within a particular period of time. In cases where the manufacturer agreed to supply the required goods within the specified time, the goods were directly forwarded to a place called the staging area. The goods were packed here according to the orders received from different stores and then directly sent to the respective customers. To gain maximum out of cross-docking, Wal-Mart had to make fundamental changes in its approach to managerial control . Traditionally, decisions about merchandising, pricing and promotions had been highly centralized and were generally taken at the corporate level. The crossdocking system, however, changed this practice. The system shifted the focus from “supply chain” to the “demand chain,” which meant that instead of the retailer ‘pushing’ products into the system; customers could ‘pull’ products, when and where they needed. This approach placed a premium on frequent, informal cooperation among stores, distribution centers and suppliers with far less centralized control than earlier.

Besides, if the supplier knows also, that for the company it will be incredibly difficult to make proper adjustments to guarantee smooth transition to the different supplier, then they will be less inclined to lower their price as much. It is not, how existing suppliers deal with Wal-Mart; when they see that Wal-Mart has found the supplier who will give them lower price, current suppliers lower their prices accordingly. They know that logistical system of the Wal-Mart can address with transition easily, and consequently they do not receive additional leverage, as it will not be difficult or expensive for Wal-Mart to choose other supplier.

Another reason that Wal-Mart’s prices are so competitive is because they buy in such large quantities that transportation from one end of the supply chain to another is not as expensive for additional units. This aspect of the logistical system does not come from skill or expertise it simply comes from the sheer size of the company, but this is still a factor. On the other hand, the Wal-Mart buys so many supplies from different places throughout the world, that they have the luxury of using bigger trucks and using less fuel to go back and forth. Also if by chance they have to use shipping services to transport material from one location to another, Wal-Mart will give them so much business that they will get huge discounts.

On the whole, the logistical system that Wal-Mart uses is so effective because it is so flexible. This is why Wal-Mart is able to offer things much cheaper than other companies can.

About Wal-mart Stores

Wal-Mart Stores, Inc. is the largest retailer in the world, the world’s second-largest company and the nation’s largest nongovernmental employer. Wal-Mart Stores, Inc. operates retail stores in various retailing formats in all 50 states in the United States. The Company’s mass merchandising operations serve its customers primarily through the operation of three segments. The Wal-Mart Stores segment includes its discount stores, Supercenters, and Neighborhood Markets in the United States. The Sam’s club segment includes the warehouse membership clubs in the United States. The Company’s subsidiary, McLane Company, Inc. provides products and distribution services to retail industry and institutional foodservice customers. Wal-Mart serves customers and members more than 200 million times per week at more than 8,416 retail units under 53 different banners in 15 countries. With fiscal year 2010 sales of $405 billion, Wal-Mart employs more than 2.1 million associates worldwide. Nearly 75% of its stores are in the United States (“Wal-Mart International Operations”, 2004), but Wal-Mart is expanding internationally. The Group is engaged in the operations of retail stores located in all 50 states of the United States, Argentina, Brazil, Canada, Japan, Puerto Rico and the United Kingdom, Central America, Chile, Mexico,India and China.

Related posts:

  • Case Study: Wal-Marts Competitive Advantage
  • Case Study: Wal-Mart’s Failure in Germany
  • Case Study: Business Strategy Analysis of Wal-Mart
  • Case Study: An Assessment of Wal-Mart’s Global Expansion Strategy
  • Case Study of Walmart: Procurement and Distribution
  • Use of Logistics Channel and Public and Private Distribution Facilities – For Material Sources
  • Case Study of FedEx: Pioneer of Internet Business in the Global Transportation and Logistics Industry
  • Distribution Center Decisions
  • Case Study: Strategy of Ryanair
  • Case Study: How Netflix Took Down Blockbuster

One thought on “ Case Study: Wal-Mart’s Distribution and Logistics System ”

Leave a reply cancel reply.

Your email address will not be published. Required fields are marked *

This site uses cookies to improve your experience. By viewing our content, you are accepting the use of cookies. To help us insure we adhere to various privacy regulations, please select your country/region of residence. If you do not select a country we will assume you are from the United States. View our privacy policy and terms of use.

  • Materials Handling
  • Tracking and Tracing

Remove

Negotiating With A Chatbot: A Walmart Procurement Case Study

Talking Logistics

MAY 1, 2023

This past February we asked members of our Indago supply chain research community — who are all supply chain and logistics executives from manufacturing, retail, and distribution companies — “Is your company using Artificial Intelligence in its supply chain or logistics operations?”

case study in distribution management

Distribution Network Cost- A Mini Case Study

Logistics Bureau

SEPTEMBER 7, 2022

You can access a recorded webinar about Distribution Network Costs on this link: [link]. ?. Related articles on this topic have appeared throughout our website, check them out: The 7 Principles of Warehouse and Distribution Centre Design. The Long and Short of Designing a Distribution Network.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Trending Sources

The Logistics of Logistics

  • The Lean Thinker

article thumbnail

CASE STUDY: Amware Helps Image Skincare Scale Fulfillment to Support Growth

Amware Logistics and Fulfillment

SEPTEMBER 21, 2021

Image Skincare had just one company-run distribution center in South Florida and sought to open another DC in the center of the country to distribute faster with lower shipping costs. After a competitive bid process, Image turned to Amware to fulfill national orders (except for FL and GA) from its Dallas distribution center.

article thumbnail

Fulfillment That Makes You Smile: Smile America Partners Case Study

3PL Insights

FEBRUARY 2, 2023

After meeting with many fulfillment providers, Smile America Partners decided to work with Evans Distribution Systems. Download the case study here. The post Fulfillment That Makes You Smile: Smile America Partners Case Study appeared first on Evans Distribution Systems.

article thumbnail

A ‘Case Study’ on Distribution Channels

SEPTEMBER 7, 2021

Distribution channels are frequently overlooked as a source of performance enhancement in the Supply Chain. Remember that one of the most important factors to consider when evaluating Distribution Channels would be the cost to serve. It can lead to some excellent alternative Distribution Strategies.

article thumbnail

Recent Case Studies Highlight Weber’s Retail Logistics Expertise

West Coast and California Logistics

MAY 30, 2024

Weber Logistics continues to demonstrate excellence in retail logistics through its partnerships with leading brands. Weber’s work with Cuisinart Outdoors and Reduce Everyday illustrate how 3PL services are tailored to meet their diverse needs of clients, ensuring efficiency, scalability, and superior customer satisfaction.

article thumbnail

CASE STUDY: Handling a 500% order Spike During Pandemic

JUNE 30, 2020

Most sales are online at publicgoods.com, but in early 2020 the company began national distribution to a major retail chain. As if opening up a new sales channel wasn’t enough of a distribution challenge, something else happened in this timeframe – the Coronavirus pandemic shutdown hit hard.

article thumbnail

Watch: Innocent Armor and Jillamy: A Distribution Case Study

Supply Chain Brain

SEPTEMBER 23, 2022

Mike Wang, chief executive officer and founder of Innocent Armor, and Dwayne Shakespeare, director of e-commerce and parcel with Jillamy Inc., explain why Innocent Armor turned to Jillamy for a fulfillment center that could scale in line with the client’s projected growth.

article thumbnail

Principles of Distribution Network Design

APRIL 12, 2022

Here is a simple case study on Distribution Networks that illustrates some key principles in Distribution Network Design. ?. Related articles on this topic have appeared throughout our website, check them out: Do You Know the Signs of Poor Distribution Network Design?

article thumbnail

A ‘Case Study’ on Distribution Channels and Thinking Outside the Box to Save 18% on Costs

article thumbnail

Watch: Cintas & LogistiVIEW: A Case Study

APRIL 17, 2023

Seth Patin, CEO and founder of LogistiVIEW, and David Meyn, senior director of distribution at Cintas, discuss optimizing labor visibility and productivity at the uniform company.

article thumbnail

Case Study: Mitigating disruption when COVID-19 closes your distribution center

Logistics Management

JUNE 24, 2020

Learn how an up-to-date optimization model provided one U.S. distributor with a 55% cost avoidance when one of their facilities had to temporarily close because of a worker who contracted COVID-19.

article thumbnail

Case Study: InterChange Group

Camelot 3PL Software

NOVEMBER 13, 2020

Background: InterChange Group in Harrisonburg, VA performs cold-storage warehousing and distribution for major U.S. The post Case Study : InterChange Group appeared first on Camelot 3PL Software. food producers and other suppliers around the world.

article thumbnail

Case Study: How did GEODIS improve put-away operator productivity by 30%?

SEPTEMBER 18, 2020

The company was proactively looking for ways to enhance their material handling processes in distribution centers when in the fall of 2019, they began researching solutions to make jobs safer while increasing efficiency and throughput. As a 3PL company, GEODIS handles many different operations within its distribution centers.

article thumbnail

Warehouse & Distribution Centre Benchmarking Case Study with John Monck

AUGUST 4, 2020

BENCHMARKING IS A FANTASTIC BUSINESS IMPROVEMENT TOOL. John Monck, Manager Consulting at Logistics Bureau will demonstrate its use and explain more… and more about it. Kindly watch the video below: Best Regards, Rob O’Byrne. Email: [email protected]. Phone: +61 417 417 307.

article thumbnail

247 Customs Broker

Kindly… The post Warehouse & Distribution Centre Benchmarking Case Study with John Monck appeared first on 24/7 Customs Broker News. BENCHMARKING IS A FANTASTIC BUSINESS IMPROVEMENT TOOL. John Monck, Manager Consulting at Logistics Bureau will demonstrate its use and explain more….and and more about it.

article thumbnail

Case Study: Paper Made Easy

FEBRUARY 23, 2021

The post Case Study : Paper Made Easy appeared first on Evans Distribution Systems. We have been able to flex by thousands of tons of inbound and outbound shipments over the years with Evans. They are one of our most trusted and reliable 3PL partners.”.

article thumbnail

Flexible Warehousing with Flexe CEO Karl Siebrecht

MARCH 24, 2023

Founded in 2013 and headquartered in Seattle, Flexe brings deep logistics expertise and enterprise-grade technology to deliver innovative eCommerce fulfillment, retail distribution and network capacity programs to the Fortune 500.

article thumbnail

Case Study: Container Legs in LNG Innovation

Logistics Business Magazine

NOVEMBER 27, 2019

The post Case Study : Container Legs in LNG Innovation appeared first on Logistics Business® Magazine. The new ConFoot CF model with a capacity of 34 tons was introduced in the summer of 2019, offering extended range of use for tank container operators in particular.

article thumbnail

Case Study: The Order Fulfillment Group

AUGUST 12, 2021

Known for its efficiency and quick turnarounds, the third-party logistics provider (3PL) offers comprehensive fulfillment and distribution services that include order entry, accounting, warehousing, and returns receiving to organizations nationwide. Postal Service. The Order Fulfillment Group.

article thumbnail

How a Compost Collection Start-Up Went From 15 Customers to Thousands – A Case Study

APRIL 19, 2019

Read our case study on The Compost Crew and learn how better planning has enabled them to manage up to 600 stops per day! The Compost Crew Case Study Download the case study to learn how WorkWave Route Manager played an important role in The Compost Crew’s sustainable success!

article thumbnail

Case Study: Reusable Box for Magazines and Newspapers

APRIL 20, 2020

AMP, Belgium’s largest media distributor, was looking for an efficient and reusable packaging solution for the distribution of magazines and newspapers. The distribution of magazines and newspapers to supermarkets, petrol stations and press & bookshops takes place at the crack of dawn, before all outlets are open. The Challenge.

article thumbnail

IoT in Logistics “The Maersk Case Study”

Logistics at MPEPS at UPV

MARCH 15, 2021

According to the article “ How IoT can improve the logistic pro ces s ” the internet of things (IoT) provides data, which describes objects “physical assets” for example a good to be transported and distributed worldwide. Photo by Pixabay on Pexels.com.

article thumbnail

PepsiCo: Experts in products but struggling in their distribution

MARCH 9, 2021

The distribution system they operated was through exportation of their products to Ukrainian bottling companies, which then sold the products to independent distributors. Sources: Marketing Channels And Logistics: a Case Study Of Pepsi International.

article thumbnail

Case Study: How to Keep Your Warehouse Pristine

DECEMBER 9, 2019

Beaches Logistics is a busy warehouse and distribution site in Carlisle, a brand new 40,000 square feet facility that only closes for 5 hours every night. In addition to distributing goods for clients we also provide storage for customers who access the warehouse themselves. This is his story: The Cleaning Issue.

article thumbnail

Case Study: From Pick to Shout to Pick to Light

NOVEMBER 26, 2019

The Chilean company has installed Pick to Light for order picking of packaged, long-life products and Put to Light for the distribution of daily fresh pastry products and other food products. “ The post Case Study : From Pick to Shout to Pick to Light appeared first on Logistics Business® Magazine.

article thumbnail

Distribution Center Robots: How Robots Continue to Power the Distribution Center

GlobalTranz

APRIL 6, 2018

Spurred by the record-breaking growth of e-commerce and rising labor costs, robots can have a very positive impact in distribution centers when implemented correctly. Why Do Companies Fear Distribution Center Robots and Their Implementation? Anyone who has worked in a distribution center knows that exceptions arise constantly.

article thumbnail

Case Study: Loading Bay Technology at High-Spec Business Park

DECEMBER 13, 2018

The park has 500,000 sq ft left to be developed, and the latest project to complete was a campus of five high specification industrial / distribution units. Understanding the requirements of large warehouses and distribution centres, Hörmann was able to provide the site with products from their award-winning range of loading bay technology.

article thumbnail

Case Study: Doubling Productivity with SSI Schaefer Automation

Pet supplier Fressnapf opted for a sustainable system concept and SSI Schaefer’s intralogistics competence when extending its European distribution centre. ” The post Case Study : Doubling Productivity with SSI Schaefer Automation appeared first on Logistics Business® Magazine.

article thumbnail

Last Mile Delivery Platform: MercuryGate Use Cases and Success Stories

MercuryGate

OCTOBER 17, 2023

Read these case studies to see how MercuryGate’s last-mile delivery platform helps businesses overcome delivery challenges, optimize routes, and enhance customer communication. The post Last Mile Delivery Platform: MercuryGate Use Cases and Success Stories appeared first on MercuryGate International.

article thumbnail

Case Study: CKF Systems Robots Pick Fragile Snack Product at High Speed

MARCH 30, 2020

The system is helping them to produce, pack and distribute a steady supply of their product to the UK’s supermarkets. The post Case Study : CKF Systems Robots Pick Fragile Snack Product at High Speed appeared first on Logistics Business® Magazine.

article thumbnail

Case Study: Good Day at the Office for System Store Solutions

DECEMBER 11, 2019

This growth has meant change within the business and in July it relocated its warehousing and distribution operation to a brand-new facility in Kempston, Bedfordshire. The post Case Study : Good Day at the Office for System Store Solutions appeared first on Logistics Business® Magazine.

article thumbnail

Case Study: Smelling the Coffee with JCB’s Teletruk

JUNE 7, 2019

The company produces and distributes some 6 million litres of milk per week from its processing facility in Acton, West London and operates additional retail distribution sites in Leeds, Manchester, Derby, Coventry, Cardiff, Birmingham and Plympton in Devon. The company’s Acton site operates around-the-clock, seven-days-a-week.

article thumbnail

Case Study: STILL RX70 Truck Handles Agri Business

MARCH 19, 2019

Steve Holt (IAE Distribution Manager) commented: “We trialled 10 different suppliers and STILL’s product came out on top in terms of fuel-saving and efficiency. In addition, IAE decided to extend their operation (in the distribution side of the business) to a 2-shift pattern and the truck hours have been increased to reflect this.

article thumbnail

Case Study: Marangoni Blackline Performs for Danish Truck Fleet

JULY 31, 2019

It is Marangoni’s recommendation that the RDG101 is utilised on vehicles typically used for regional distribution , like those of Bach & Pedersen, a Danish company with a fleet of 52 trucks and 90 trailers that have been making use of the product in the sizes of 315/60R22,5 and 315/70R22,5.

article thumbnail

Case Study: Helly Hansen opts for UniCarriers once more

OCTOBER 1, 2019

Norwegian clothing manufacturer Helly Hansen operates most of its company fleet at its European distribution centre in the Dutch town of Born. Workwear stocks were warehoused at a separate distribution centre in Sweden until 2011, but they are now stored together with sports clothing at the Born EDC. The centre holds a total of 2.5

article thumbnail

Sortation Case Study: Prepared for Peak Times

JULY 11, 2018

Austrian postal service Österreichische Post AG has built its new distribution centre in Wernberg, in the southernmost Austrian state of Carinthia. The Austrian postal service has responded to this tough task and opened a new distribution centre in Wernberg, in the state of Carinthia. Up to 30,000 packages are handled on a daily basis.

Case Study: Wanzl Roll Cages Supplied to University Hospital Zurich

MARCH 6, 2019

The construction of the new UHZ Logistics and Service Centre in Schlieren, which supplies the UHZ centre in Zurich as well as the external wards, made it necessary to put in place specially coordinated roll containers for distribution . The organisation found Wanzl Logistics + Industry to be the ideal partner for this task.

Case Study: Customer-Centric Live Logistics Optimization for Large Online Retailer

DECEMBER 31, 2018

The client was one of the largest online home goods retailer in North America with more than 60 million active online users, 10 million hosted products, and 20,000 suppliers. LogiNext optimized their entire logistics movement with optimized carrier handling and high customer (delivery) experience.

article thumbnail

Case Study: Roll Out the Barrel for Tailored Materials Handling

NOVEMBER 12, 2019

Following the acquisition of both the Charles Wells Brewing and Beer business and various supply contracts in 2017, Marston’s elected to bring the distribution operation in-house at a new site in West Thurrock. The post Case Study : Roll Out the Barrel for Tailored Materials Handling appeared first on Logistics Business® Magazine.

article thumbnail

How Exceptional Companies Grow with Sarah Ahern & Jonathon McKay

SEPTEMBER 15, 2023

Focused on logistics, manufacturing, and distribution channel strategies, Jonathon helps organizations make confident decisions for bold growth. About Jonathon McKay Jonathon McKay is a highly experienced partner at PATH specializing in exceptional growth strategies for the supply chain industry.

article thumbnail

MAY 13, 2024

Plus hard-hitting interviews, site visits and case studies with Ocado, Bobcat, the UK Department for Transport, Blue Yonder, Koerber, Kinaxis, Sennder, Bowe, Fortna, Dematic, Beumer, TGW, Clark, RightHand Robotics, Distrisort, Transdek, Fronius, Bonfiglioli, Gather AI and Efaflex.

Case Study: Tooling Up with Storage and Picking System

JULY 4, 2018

Based in Yeovil, Somerset, the organisation operates from a purpose-built distribution centre and its philosophy of providing more than 6,000 tools ex-stock at low prices has earned the company an unrivalled industry reputation. The post Case Study : Tooling Up with Storage and Picking System appeared first on Logistics Business® Magazine.

article thumbnail

Case Study: Yale and Forkway Enable Stelrad to Radiate Success

JUNE 18, 2018

As the materials handling equipment supplier to Stelrad for over 15 years, Yale sub-dealer, Forkway, is best placed to advise and guide the company on the most efficient operation in their warehouse and distribution centre. Thanks to the steady growth of the company, there was a need to extend the distribution centre to meet growing demand.

Stay Connected

Join 84,000+ Insiders by signing up for our newsletter

  • Participate in Logistics Brief
  • Add a Source
  • Add a Resource
  • 2019 Logistics Brief MVP Awards
  • 2020 Logistics Brief MVP Awards
  • 2021 Logistics Brief MVP Awards
  • 2022 Logistics Brief MVP Awards
  • Thu. Jul 11
  • Wed. Jul 10
  • Tue. Jul 09
  • Mon. Jul 08
  • Jun 29 - Jul 05
  • Supply Chains
  • Distribution
  • Transportation
  • More Topics 

LinkedIn

Input your email to sign up, or if you already have an account, log in here!

Enter your email address to reset your password. a temporary password will be e‑mailed to you., be in the know on, logistics brief.

Expert insights. Personalized for you.

We organize all of the trending information in your field so you don't have to. Join 84,000+ users and stay up to date on the latest articles your peers are reading.

case study in distribution management

Get the good stuff

Subscribe to the following Logistics Brief newsletters:

You must accept the Privacy Policy and Terms & Conditions to proceed.

More

You know about us, now we want to get to know you!

Check your mail, we've sent an email to . please verify that you have received the email..

We have resent the email to

Let's personalize your content

Use social media to find articles.

We can use your profile and the content you share to understand your interests and provide content that is just for you.

Turn this off at any time. Your social media activity always remains private.

Let's get even more personalized

Choose topics that interest you., so, what do you do.

Are you sure you want to cancel your subscriptions?

Cancel my subscriptions

Don't cancel my subscriptions

Changing Country?

Accept terms & conditions.

It looks like you are changing your country/region of residence. In order to receive our emails, you must expressly agree. You can unsubscribe at any time by clicking the unsubscribe link at the bottom of our emails.

You appear to have previously removed your acceptance of the Terms & Conditions.

More

We noticed that you changed your country/region of residence; congratulations! In order to make this change, you must accept the Aggregage Terms and Conditions and Privacy Policy. Once you've accepted, then you will be able to choose which emails to receive from each site .

You must choose one option

Please choose which emails to receive from each site .

  • Update All Sites
  • Update Each Site

Please verify your previous choices for all sites

Sites have been updated - click Submit All Changes below to save your changes.

We recognize your account from another site in our network , please click 'Send Email' below to continue with verifying your account and setting a password.

You must accept the Privacy Policy and Terms & Conditions to proceed.

This is not me

  • Browse All Articles
  • Newsletter Sign-Up

Distribution →

case study in distribution management

  • 25 Jun 2024
  • Research & Ideas

How Transparency Sped Innovation in a $13 Billion Wireless Sector

Many companies are wary of sharing proprietary information with suppliers and partners. However, Shane Greenstein and colleagues show in a study of wireless routers that being more open about technology can lead to new opportunities.

case study in distribution management

  • 22 Mar 2024

Open Source Software: The $9 Trillion Resource Companies Take for Granted

Many companies build their businesses on open source software, code that would cost firms $8.8 trillion to create from scratch if it weren't freely available. Research by Frank Nagle and colleagues puts a value on an economic necessity that will require investment to meet demand.

case study in distribution management

  • 12 Dec 2023

COVID Tested Global Supply Chains. Here’s How They’ve Adapted

A global supply chain reshuffling is underway as companies seek to diversify their distribution networks in response to pandemic-related shocks, says research by Laura Alfaro. What do these shifts mean for American businesses and buyers?

case study in distribution management

  • 25 Apr 2023

How SHEIN and Temu Conquered Fast Fashion—and Forged a New Business Model

The platforms SHEIN and Temu match consumer demand and factory output, bringing Chinese production to the rest of the world. The companies have remade fast fashion, but their pioneering approach has the potential to go far beyond retail, says John Deighton.

case study in distribution management

  • 29 Nov 2022

How Much More Would Holiday Shoppers Pay to Wear Something Rare?

Economic worries will make pricing strategy even more critical this holiday season. Research by Chiara Farronato reveals the value that hip consumers see in hard-to-find products. Are companies simply making too many goods?

case study in distribution management

  • 18 Oct 2022
  • Cold Call Podcast

Chewy.com’s Make-or-Break Logistics Dilemma

In late 2013, Ryan Cohen, cofounder and then-CEO of online pet products retailer Chewy.com, was facing a decision that could determine his company’s future. Should he stay with a third-party logistics provider (3PL) for all of Chewy.com’s e-commerce fulfillment or take that function in house? Cohen was convinced that achieving scale would be essential to making the business work and he worried that the company’s current 3PL may not be able to scale with Chewy.com’s projected growth or maintain the company’s performance standards for service quality and fulfillment. But neither he nor his cofounders had any experience managing logistics, and the company’s board members were pressuring him to leave order fulfillment to the 3PL. They worried that any changes could destabilize the existing 3PL relationship and endanger the viability of the fast-growing business. What should Cohen do? Senior Lecturer Jeffrey Rayport discusses the options in his case, “Chewy.com (A).”

case study in distribution management

  • 10 Jan 2022

How to Get Companies to Make Investments That Benefit Everyone

Want more organizations to give back to their communities? Frank Nagle says the success of open source software offers an innovative—and unexpected—roadmap for social good. Open for comment; 0 Comments.

case study in distribution management

  • 19 Jul 2020
  • Working Paper Summaries

Open Source Software and Global Entrepreneurship

Does more activity in open source software development lead to increased entrepreneurial activity and, if so, how much, and in what direction? This study measures how participation on the GitHub open source platform affects the founding of new ventures globally.

  • 01 Jun 2020
  • What Do You Think?

Will Challenged Amazon Tweak Its Retail Model Post-Pandemic?

James Heskett's readers have little sympathy for Amazon's loss of market share during the pandemic. Has the organization lost its ability to learn? Open for comment; 0 Comments.

  • 05 Mar 2019

The Impacts of Increasing Search Frictions on Online Shopping Behavior: Evidence from a Field Experiment

This paper challenges the logic that making it easier for consumers to search across a wide assortment of products is the best strategy for online retailers. Experiments show that adding extra search costs to find discounted items can improve gross margins and sales by increasing the number of items inspected and serving as a self-selecting price discrimination mechanism among customers.

case study in distribution management

  • 18 Oct 2018

How to Use Free Shipping as a Competitive Weapon

Free shipping is an increasingly important tool in the online retailer's marketing arsenal, but profit is lost when not done right, says Donald Ngwe. Open for comment; 0 Comments.

case study in distribution management

  • 05 Sep 2018

The Hidden Benefit of Giving Back to Open Source Software

Firms that allow their software programmers to "give back" to the open source community on company time gain benefits—even though competitors might benefit too, says Frank Nagle. Open for comment; 0 Comments.

case study in distribution management

  • 17 Jun 2017

Amazon, Whole Foods Deal a Big Win for Consumers

What does Amazon's $13.4 billion deal for Whole Foods say about the future of retail? Harvard Business School professors Jose Alvarez and Len Schlesinger see good times ahead for consumers as well as both companies. Open for comment; 0 Comments.

  • 06 Jul 2015

Money and Quotas Motivate the Sales Force Best

Bonus programs are effective for motivating sales people, but also costly for companies to maintain. Doug Chung and Das Narayandas study several compensation schemes to see which work best. Open for comment; 0 Comments.

  • 21 May 2015

Incentives versus Reciprocity: Insights from a Field Experiment

Sales force compensation is a key instrument available to firms for motivating and enhancing sales performance. What are the most effective forms of compensation? In a field experiment involving four regional sales forces of a prominent firm in India, the authors examined the impact of conditional and unconditional bonus schemes. Findings from this study provide guidance to firms on how to use conditional and unconditional compensation to enhance sales rep productivity and better manage the achievement of sales forecasts. Closed for comment; 0 Comments.

  • 02 Apr 2015

Digital Initiative Summit: The Business of Crowdsourcing

Gaining the community's trust is vital to building a successful business with crowdsourcing. Open for comment; 0 Comments.

  • 17 Mar 2015

Where Did My Shopping Mall Go?

The growing popularity of online shopping is remaking the world of offline shopping—stores are getting smaller, malls are getting scarcer. Rajiv Lal and José Alvarez look ahead five years at our radically transforming shopping experience. Plus: Book excerpt. Open for comment; 0 Comments.

  • 02 Mar 2015

Retail Reaches a Tipping Point—Which Stores Will Survive?

Part 1: The new book Retail Revolution: Will Your Brick and Mortar Store Survive? argues that ecommerce is about to deal severe blows to many familiar store-based brands—even including Walmart. Here's how retailers can fight back, according to Rajiv Lal, José Alvarez, and Dan Greenberg. Open for comment; 0 Comments.

  • 29 Sep 2014

Why Do Outlet Stores Exist?

Created in the 1930s, outlet stores allowed retailers to dispose of unpopular items at fire-sale prices. Today, outlets seem outmoded and unnecessary—stores have bargain racks, after all. Donald K. Ngwe explains why outlets still exist. Open for comment; 0 Comments.

  • 08 Sep 2014

The Strategic Way To Hire a Sales Team

The equivalent of an entire sales force is replaced at many firms every four years, so it's critical that go-to-market initiatives remain tied to strategic goals. Frank Cespedes explains how in his book, Aligning Strategy and Sales. Closed for comment; 0 Comments.

Helping Distributors Make More Money

Value-added resale partners.

Build relationships with your customers by providing tools for taking on distribution’s greatest challenges.

Integration Partners

Connect the best application options the ERP world has to offer. Integrate with the best and brightest organizations in distribution to cover all of your needs, and more.

CASE STUDIES

See how these distributors harnessed process control and data visibility to take their business operations to new heights. Each story packs industry best practices, relevant for businesses of all sizes and across industries.

Steiner Tractor Parts

Steiner Tractor Parts

Steiner Tractor Supply was ready to modernize and streamline its order management system. Manual input and slow reporting were limiting the company’s potential. Learn how they moved from tracking every order on paper to automating processes and growing their business with SalesPad by Cavallo.

geckobrands

Geckobrands

To encourage their customers to carry additional products, geckobrands needed to prove that unexpected products or styles were top sellers for many customers. Learn how Cavallo helped them leverage their existing data to drive sales.

lightbulbs.com

Lightbulbs.com

LightBulbs.com needed a credit card gateway that was reliable and could scale with their growing business. Learn how they've supercharged their online business with the SalesPad and Square integration.

expresspoint-image3

ExpressPoint

After an acquisition, ExpressPoint needed a single distribution management system that could handle its legacy repair business as well as its new sales business. Learn why it chose SalesPad by Cavallo.

miller-welding-image3

Miller Welding Supply

Maintaining Miller Welding Supply’s legacy distribution management system took three employees five to six hours per day. Learn how SalesPad by Cavallo cut that overhead to improve the company’s speed and flexibility.

Krowne

By working with teams from Admiral Consulting and Cavallo, Krowne overcame these obstacles and recognized transformative results.

bon-chef-catering-equipment-on-buffet-table

By choosing a solution that combined flexibility, ease of use, and reliability, Bon Chef established new processes that led to scalable growth.

chadwell-supply-flooring-samples

Chadwell Supply

As the top supplier of maintenance and flooring products in the United States, Chadwell Supply needed an Operational ERP platform that could handle its growing business.

BlenderBottle Cavallo Distribution Solutions

BlenderBottle

To keep up with skyrocketing sales, BlenderBottle needed a software upgrade. Flexibility in a new solution was a must, one that could grow with the company for years to come.

Picnic Time warehouse management tools

Picnic Time Family of Brands

Frustrated by its previous software’s lack of flexibility, Picnic Time was in the market for a solution that could keep its order processing moving as the company continued to grow.

hoy-shoe-company-saltwater-sandals

Hoy Shoe Co

Find out why SalesPad was the answer to Hoy Shoe Co’s® pursuit of perfect customer service.

regal fabrics distribution software case study

Regal Fabrics

Before Regal Fabrics implemented SalesPad, it struggled with an order processing system that required clicking among multiple different screens, with little to no visibility over its inventory. Now, order processing is free from worries about inventory status.

Handi-Craft Company warehousing software case study

The Handi-Craft Company

Toy manufacturer-turned-baby product distributor, the Handi-Craft Company moved to Cavallo for its user-friendly interface — but stayed for major efficiency improvements.

Ohio Power Tool inventory management solutions

Ohio Power Tool

Ohio Power Tool turned to SalesPad by Cavallo for streamlining its order management processes, improving inventory management, and creating workflows for every business process.

National Band Saw Company distribution software

National Band Saw Company

The National Band Saw Company turned to SalesPad by Cavallo when it needed a software solution that was easy to work with, could handle complex shipping demands, and didn’t compromise on power or scope.

Key Surgical distribution software case study

Key Surgical

Key Surgical is a Minneapolis, Minnesota-based manufacturer and distributor of sterile processing and operating room supplies. With SalesPad added to their on-premises order-to-cash cycle strategy, the company was able to extend the life of its Dynamics GP investment significantly.

Dental City warehousing inventory software

Dental City

While searching for an improvement on the company’s old system, Dental City was introduced to both Microsoft Dynamics GP and SalesPad by Cavallo®, which provided additional power and more user-friendly options for managing the company's order-to-cash cycle.

SEE THE FUTURE OF DISTRIBUTION

  • Cavallo for BC
  • SalesPad for GP
  • Professional Services
  • Cavallo Support
  • Become a Strategic Partner
  • Partner Lead Registration
  • Case Studies
  • Fact Sheets
  • White Papers
  • Events Calendar
  • Agreements / Legal

3351 Claystone Street SE, Suite 100, Grand Rapids, MI 49546

616.245.1221 800.935.5660

  • Skip to content.
  • Jump to Page Footer.

Strategic expansion: Canadian companies' roadmap to US capital success

Our latest guide will give you direct-application tools to help tap into the US funding market.

case study in distribution management

Case study: Dell—Distribution and supply chain innovation

Clock

Read the highlights

  • Cutting out the middleman can work very well.
  • Forgoing the retail route can increase customer value.
  • Re-examine & improve efficiency for process/operations.
  • Use sales data and customer feedback to get ahead of the curve.

In 1983, 18-year-old Michael Dell left college to work full-time for the company he founded as a freshman, providing hard-drive upgrades to corporate customers. In a year’s time, Dell’s venture had $6 million in annual sales. In 1985, Dell changed his strategy to begin offering built-to-order computers. That year, the company generated $70 million in sales. Five years later, revenues had climbed to $500 million, and by the end of 2000, Dell’s revenues had topped an astounding $25 billion. The meteoric rise of Dell Computers was largely due to innovations in supply chain and manufacturing, but also due to the implementation of a novel distribution strategy. By carefully analyzing and making strategic changes in the personal computer value chain, and by seizing on emerging market trends, Dell Inc. grew to dominate the PC market in less time than it takes many companies to launch their first product.

No more middleman: Dell started out as a direct seller, first using a mail-order system, and then taking advantage of the Internet to develop an online sales platform. Well before use of the Internet went mainstream, Dell had begun integrating online order status updates and technical support into their customer-facing operations. By 1997, Dell’s Internet sales had reached an average of $4 million per day . While most other PCs were sold preconfigured and pre-assembled in retail stores, Dell offered superior customer choice in system configuration at a deeply discounted price, due to the cost-savings associated with cutting out the retail middleman. This move away from the traditional distribution model for PC sales played a large role in Dell’s formidable early growth. Additionally, an important side-benefit of the Internet-based direct sales model was that it generated a wealth of market data the company used to efficiently forecast demand trends and carry out effective segmentation strategies. This data drove the company’s product development efforts and allowed Dell to profit from information on the value drivers in each of its key customer segments.

Virtual integration: On the manufacturing side, the company pursued an aggressive strategy of “virtual integration.” Dell required a highly reliable supply of top-quality PC components, but management did not want to integrate backward to become its own parts manufacturer. Instead, the company sought to develop long-term relationships with select, name-brand PC component manufacturers. Dell also required its key suppliers to establish inventory hubs near its own assembly plants. This allowed the company to communicate with supplier inventory hubs in real time for the delivery of a precise number of required components on short notice. This “just-in-time,” low-inventory strategy reduced the time it took for Dell to bring new PC models to market and resulted in significant cost advantages over the traditional stored-inventory method. This was particularly powerful in a market where old inventory quickly fell into obsolescence. Dell openly shared its production schedules, sales forecasts and plans for new products with its suppliers. This strategic closeness with supplier partners allowed Dell to reap the benefits of vertical integration, without requiring the company to invest billions setting up its own manufacturing operations in-house.

Innovation on the assembly floor: In 1997, Dell reorganized its assembly processes. Rather than having long assembly lines with each worker repeatedly performing a single task, Dell instituted “manufacturing cells.” These “cells” grouped workers together around a workstation where they assembled entire PCs according to customer specifications. Cell manufacturing doubled the company’s manufacturing productivity per square foot of assembly space, and reduced assembly times by 75%. Dell combined operational and process innovation with a revolutionary distribution model to generate tremendous cost-savings and unprecedented customer value in the PC market. The following are some key lessons from the story of Dell’s incredible rise:

1. Disintermediation (cutting out the middleman): Deleting a player in the distribution chain is a risky move, but can result in a substantial reduction in operating costs and dramatically improved margins. Some companies that have surged ahead after they eliminated an element in the traditional industry distribution chain include:

  • Expedia (the online travel site that can beat the rates of almost any travel agency, while giving customers more choice and more detailed information on their vacation destination)
  • ModCloth (a trendy virtual boutique with no bricks-and-mortar retail outlets to drive up costs)
  • PropertyGuys.com (offers a DIY kit for homeowners who want to sell their houses themselves)
  • iTunes (an online music purchasing platform that won’t have you sifting through a jumble of jewel cases at your local HMV)
  • Amazon.com (an online sales platform that allows small-scale buyers and sellers to access a broad audience without the need for an expensive storefront or a custom website)
  • Netflix (the no-late-fees online video rental company that will ship your chosen video rentals right to your door)

2. Enhancing customer value: Forgoing the retail route allowed Dell to simultaneously improve margins while offering consumers a better price on their PCs. This move also gave customers a chance to configure PCs according to their specific computing needs. The dramatic improvement in customer value that resulted from Dell’s unique distribution strategy propelled the company to a leading market position.

3. Process and operations innovation: Michael Dell recognized that “the way things had always been done” wasn’t the best or most efficient way to run things at his company. There are countless examples where someone took a new look at a company process and realized that there was a much better way to get things done. It is always worth re-examining process-based work to see if a change could improve efficiency. This is equally true whether you’re a company of five or 500.

4. Let data do the driving: Harnessing the easily accessible sales and customer feedback data that resulted from online sales allowed Dell to stay ahead of the demand curve in the rapidly evolving PC market. Similarly, sales and feedback data were helpful in discovering new ways to enhance customer value in each of Dell’s key customer segments. Whether your company is large or small, it is essential to keep tabs on metrics that could reveal emerging trends, changing attitudes, and other important opportunities for your company.

See additional learning materials for distribution .

Summary: Dell combined operational and process innovation with a revolutionary distribution model to generate tremendous cost-savings and unprecedented customer value in the PC market.

Read next: customer discovery: identifying effective distribution channels for your startup.

Strickland, T. (1999). Strategic Management, Concepts and Cases . McGraw Hill College Division: New York.

Should startups build distribution channels or sell products directly?

Customer discovery: identifying effective distribution channels for your startup, sign up for our monthly startup resources newsletter about building high-growth companies..

  • Enter your email *

You may unsubscribe at any time. To find out more, please visit our Privacy Policy .

This site uses cookies to improve your experience. By viewing our content, you are accepting the use of cookies. To help us insure we adhere to various privacy regulations, please select your country/region of residence. If you do not select a country we will assume you are from the United States. View our privacy policy and terms of use.

  • Inventory Management Software
  • Forecasting
  • Sustainability
  • Supply Chain Visibility

Remove

Negotiating With A Chatbot: A Walmart Procurement Case Study

Talking Logistics

MAY 1, 2023

This past February we asked members of our Indago supply chain research community — who are all supply chain and logistics executives from manufacturing, retail, and distribution companies — “Is your company using Artificial Intelligence in its supply chain or logistics operations?”

case study in distribution management

Distribution Network Cost- A Mini Case Study

Logistics Bureau

SEPTEMBER 7, 2022

You can access a recorded webinar about Distribution Network Costs on this link: [link]. ?. Related articles on this topic have appeared throughout our website, check them out: The 7 Principles of Warehouse and Distribution Centre Design. The Long and Short of Designing a Distribution Network.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Trending Sources

Logistics Viewpoints

The Logistics of Logistics

  • Enchange Supply Chain Consultancy
  • Enterra Insights

article thumbnail

A ‘Case Study’ on Distribution Channels

SEPTEMBER 7, 2021

Distribution channels are frequently overlooked as a source of performance enhancement in the Supply Chain. Remember that one of the most important factors to consider when evaluating Distribution Channels would be the cost to serve. It can lead to some excellent alternative Distribution Strategies.

article thumbnail

Supply Chain Case Study: the Executive's Guide

Supply Chain Opz

JUNE 1, 2014

Analysis of case study is certainly one of the most popular methods for people from business management background. In order to accelerate the learning, this article has gathered 20+ most sought-after supply chain case studies , analyzed/categorized them by industry and the findings are presented.

article thumbnail

Case Study: DSV Implements a Single-Instance Control Tower with a Global Footprint

Advertisement

DSV is one of the biggest names in transport and logistics , operating in over 90 countries with a global network of over 75,000 employees. Supporting inbound freight management, outbound flows, domestic distribution , and storage and value-added services would require all three of DSV’s multi-national business units to participate.

article thumbnail

AI in the Retail Industry: Benefits, Case Studies & Examples

MARCH 27, 2024

The Evolution of Retail Supply Chain & Logistics : A Pre-AI Overview In the pre-AI era, the retail sector was markedly different, especially since the traditional supply chain and logistics models were largely driven by manual labor. This has made deliveries faster. Another way of ensuring greater customer satisfaction!

article thumbnail

AI in the Food Industry: Case Studies, Challenges & Future Trends

MARCH 28, 2024

Integrating Artificial Intelligence (AI) within different segments of the Food Industry, including transportation and logistics , production planning, quality control, and others has kicked off revolutionary transformations. Energy-efficient processing and distribution have minimal environmental impact.

article thumbnail

A Case Study in Closed-Loop Operational Management

NOVEMBER 19, 2014

As I’ve said before, the biggest challenge facing supply chain and logistics executives today is not managing change, because that’s always been the norm in supply chain management, but managing the rapid pace of change. In a recent webcast hosted by Logistics Management and sponsored by Solvoyo , I had the opportunity to interview Orhan Da?l?o?lugil,

article thumbnail

Principles of Distribution Network Design

APRIL 12, 2022

Here is a simple case study on Distribution Networks that illustrates some key principles in Distribution Network Design. ?. Related articles on this topic have appeared throughout our website, check them out: Do You Know the Signs of Poor Distribution Network Design?

article thumbnail

CEVA Logistics Drives Agile, Multi-Leg Inbound Flows for Tech Company

CEVA Logistics , a global leader in third-party logistics , was contracted to help a technology company manage its complex supply chain, supporting B2B, B2C, and reverse flows across multi-leg transport.

article thumbnail

Cross Docking 101: What, Why and How? [with case studies]

SEPTEMBER 23, 2021

Cross docking is an option to consider if you’re thinking about ways to streamline your supply chain – it’s a popular distribution system for fast-moving consumer goods, but can be used in a variety of other industries. This removes the ‘storage’ element of warehousing logistics , and saves on costs, warehousing space, time and labour.

article thumbnail

A ‘Case Study’ on Distribution Channels and Thinking Outside the Box to Save 18% on Costs

article thumbnail

Distribution Center Robots: How Robots Continue to Power the Distribution Center

GlobalTranz

APRIL 6, 2018

Spurred by the record-breaking growth of e-commerce and rising labor costs, robots can have a very positive impact in distribution centers when implemented correctly. As explained by Clint Raiser of Logistics Viewpoints , e-commerce retail sales have grown at 15% annually, doubling in size since 2012. Measure performance.

article thumbnail

TMS for SMB: A Case Study with Carhartt

OCTOBER 19, 2016

Rapid growth, coupled with new market segments and channels (including ecommerce), prompted Carhartt to embark on a multi-million dollar upgrade of its distribution center, which included investments in warehouse management and transportation management solutions. Is SMB defined by a company’s annual revenues?

article thumbnail

Judging Supply Chain Improvement: Campbell Soup Case Study

Supply Chain Shaman

AUGUST 11, 2014

Our approach simply breaks accountabilities and goals across the areas of Manufacturing, Logistics /Network Optimization and Ingredients/Packaging. We now have the ability to focus more on materials management and suppliers upstream, and distribution and customer solutions downstream, to drive optimization. What have you learned?

article thumbnail

Fast Track Your Logistics Career: Expert Training with SCMDOJO

JUNE 11, 2024

Are you ready to excel in logistics management? The SCMDOJO Logistics Management Track is your ultimate logistics training pathway. It’s designed to equip you with the skills and knowledge needed to thrive in the logistics industry. Visit Website to Read Full Program Why SCMDOJO Logistics Track is Unique?

article thumbnail

Delivering Green: Three Case Studies in Low-Carbon Logistics

MIT Supply Chain

APRIL 29, 2013

Caterpillar is the subject of one of three case studies that show how supply chain management can support both environmental and financial goals. Here are three case studies that offer clear, irrefutable evidence that sustainability and profitability can be compatible in the supply chain domain.

article thumbnail

A Case Study in Reverse Logistics Optimization!

Supply Chain Game Changer

NOVEMBER 23, 2018

Check out What Exactly Is Reverse Logistics ? The OEM turned over management of one of the most critical, high-volume segments of its reverse logistics program—the processor business—saving the manufacturer millions of dollars each year; reducing excess inventory; increasing same-day, on-time ship rates; and improving customer satisfaction.

article thumbnail

Recent Case Studies Highlight Weber’s Retail Logistics Expertise

West Coast and California Logistics

MAY 30, 2024

Weber Logistics continues to demonstrate excellence in retail logistics through its partnerships with leading brands. Weber’s work with Cuisinart Outdoors and Reduce Everyday illustrate how 3PL services are tailored to meet their diverse needs of clients, ensuring efficiency, scalability, and superior customer satisfaction.

article thumbnail

The Critical Path: Navigating Supply Chain Efficiency in the Oil Industry

JUNE 27, 2024

Distribution : Transporting oil products to various markets. How Does Automation Enhance Production and Distribution ? What Are the Logistical Challenges in the Oil Industry? How Do Seasonal Weather Patterns Affect Transportation and Distribution ? Extraction : Drilling and pumping oil from underground.

article thumbnail

Importance of Digitalisation to Improve Supply Chains: Helping Businesses Navigate Through Supply Chain Disruptions

The Logistics & Supply Chain Management Society

AUGUST 19, 2022

IoT is making a mark on more and more industries, including logistics . Logistics companies are also leveraging IoT and automation to create more efficient processes. In logistics , this differs significantly from the use of IoT in other industries. In logistics , this differs significantly from the use of IoT in other industries.

article thumbnail

How Exceptional Companies Grow with Sarah Ahern & Jonathon McKay

SEPTEMBER 15, 2023

Focused on logistics , manufacturing, and distribution channel strategies, Jonathon helps organizations make confident decisions for bold growth. The Logistics of Logistics Podcast If you enjoy the podcast, please leave a positive review, subscribe, and share it with your friends and colleagues. The Greenscreens.ai

article thumbnail

Adexa is Recipient of 2024 Top Supply Chain Projects Award

JUNE 17, 2024

The past 12 months has seen companies within the supply chain and logistics space upgrade, enhance, adopt and adapt in order to achieve greater efficiency along the chain. Supply & Demand Chain Executive and sister publication Food Logistics also operate SCN Summit and Women in Supply Chain Forum.

article thumbnail

Free Trade Zone – Is Your 3PL Giving You All the Warehouse and Distribution Cost Savings You Deserve?

ModusLink Corporation

FEBRUARY 8, 2023

Fulfillment Free trade zones, or FTZs, are controlled places in a country that offer warehouse and distribution services for goods from foreign markets, excluding them from paying taxes on those goods. Managing a free trade zone can impact warehouse and distribution operations. The answer, unfortunately, is only sometimes yes.

article thumbnail

Supply Chain Risk Management: Revisiting Ericsson

SCM Research

JUNE 29, 2020

Norrman & Jansson’s (2004) case study on Ericsson’s supply chain risk management (SCRM) practices is definitely part of the canon of SCM literature. International Journal of Physical Distribution & Logistics Management. After 15 years, it was time for an update. Norrman, A. & & Wieland, A.

Next Generation Supply Chain Risk Management: A Case Study

DECEMBER 16, 2015

A case in point is offered by AGCO. AGCO is a global leader in the design, manufacture and distribution of a wide range of agricultural equipment. We are entering an era where it is becoming possible to detect supply chain risks much more quickly.

article thumbnail

Retail Delivery Trends with Matt Schultz

OCTOBER 21, 2022

Matt is Vice President of Logistics Partnerships at OneRail , an Orlando-based last mile transportation visibility solution providing shippers with Amazon-level dependability and speed. Matt Schultz is Vice President of Logistic Partnerships at OneRail. Premier Pet Case Study . The Logistics of Logistics Podcast.

article thumbnail

5 Logistics Best Practices

DECEMBER 2, 2021

These logistics best practices will help businesses of all sizes turn their supply chain into a revenue driver for their business. Prioritizing logistics and supply chain has become a top prior ity for many businesses recovering from recent supply chain disruptions and volatile consumer demand. Logistics Best Practice #4: Plan Ahead.

article thumbnail

Top Talking Logistics Posts & Episodes (Q3 2017)

NOVEMBER 7, 2017

Before You Hire a Logistics Data Scientist. The Mind-Boggling Complexities of Food Distribution (Why Optimization is Critical). 3 Steps to Achieving Predictive Logistics . Using Intelligence Over Scale: The Power of AI and Machine Learning in Supply Chain and Logistics . A Case Study in Project Logistics .

article thumbnail

A New Model for Grocery Delivery with Sean Coakley

NOVEMBER 19, 2021

Sean is the Chief Commercial Officer of Capstone Logistics , a leading provider of technology-enabled warehouse services, freight management, and last mile distribution solutions. He is responsible for helping the company continue its rapid growth across its end-to-end logistics services offering. About Capstone Logistics .

article thumbnail

Best Logistics Management Software: Everything You Need to Know Before Making a Purchase Decision

MAY 3, 2024

As we step into 2024, the world of logistics isn’t what it used to be. Everything is connected – what happens in one part of the supply chain can shake things up in logistics , and the other way around. That is why logistics management software (LMS) is so much more today than what it used to be. We’ve all been witness to this!

article thumbnail

Restructuring Global Value Chains & Tariff Reduction – A Continuous Evolution for Supply Chains

Feature Article by Dr. Raymon Krishnan – President at the Logistics and Supply Chain Management Society. Owning sound data is crucial to planning optimal shipping routes, locating distribution centers and warehouses, and forecasting revenue volumes and other trends. MORE FROM THIS EDITION.

article thumbnail

Best AI Tools for Supply Chain and Logistics: The Ultimate Guide for 2024

APRIL 30, 2024

Exploring the world of AI tools for supply chain and logistics can be quite overwhelming. That’s why we put together this guide – to help you get a glimpse of the best AI tools for supply chain and logistics , how to implement these tools, what to take care of and more. Best AI Tools for Supply Chain and Logistics 1.

article thumbnail

Leveraging Cold Chain Logistics Visibility for COVID-19 Vaccine

FEBRUARY 4, 2021

Let's explore the logistics case study of one of the world’s largest pharma companies, the story of how this US-headquartered, globally present pharma giant improved teamwork in their logistics and is now confidently shipping COVID-19 vaccines using cold chain logistics visibility.

article thumbnail

11th annual Cold Chain Distribution Conference and Exhibition

Supply Chain Movement

JUNE 20, 2016

11 th annual Cold Chain Distribution Conference and Exhibition. Following the fruitful discussions in 2015, SMi’s annual Cold Chain Distribution conference will bring back lively debates and industry updates to London, offering the best platform for delegates to stay ahead of this lucrative market! Date: 12-13 December 2016.

article thumbnail

Lull Case Study: Order Fulfillment that Doesn’t Keep You Up at Night

OCTOBER 11, 2018

Get the PDF of Lull’s case study >> Challenges to Order Fulfillment. Limited Options: It didn’t make sense to continue with only dropshipping, but signing a long-term contract with a third-party logistics provider (3PL) wasn’t the right fit. They make it possible to solve traditional logistics challenges.”.

article thumbnail

Basic Introduction on Supply Chain and Logistics Benchmarking

OCTOBER 13, 2020

Robobyrne: Warehouse & Distribution Centre Benchmarking Case Study . Also, we have a recorded webinar on this topic. You can access it here: [link]. Related articles on this topic have appeared throughout our websites, why not check them out? Supply Chain Secrets: One Of The Best KPI Ever.

article thumbnail

Strong Supply Chains Required For an Economic Rebound: Six Steps To Take

APRIL 15, 2020

No doubt about it, we are characters in a supply chain case study searching to define a new normal. Today, we find ourselves in the middle of a risk management case study . News coverage showcases the differences between logistics and supply chain management. Expect border friction and logistics to be an issue.

article thumbnail

Temperature Controlled Logistics leadership forum – DACH – 2016

JULY 20, 2016

Temperature Controlled Logistics leadership forum – DACH – 2016. Bringing together industry leaders from across logistics , quality, supply chain and distribution the brand new Temperature Controlled Logistics Leaders Forum takes a hard look at core challenges and best practices to take your TCL strategy to the next level!

Rockwell Automation: A Case Study in Supply Chain Excellence

DECEMBER 4, 2018

In his role, Ernest owns strategic sourcing, materials planning, customer care, and logistics operations globally. This methodology was especially crucial for Rockwell Automation global customers, whose impact was notable since it didn’t have the benefit of their distribution network. He is a humble and quiet leader.

article thumbnail

ROI in Supply Chain: Achieving Rapid Value with ThroughPut AI in Just 90 Days

MAY 22, 2024

Download this case study to learn how ThroughPut enabled the manufacturer to: Enhance product mix and segmentation while reducing excess inventory Identify optimal stock levels and reduce working capital Drive 17.8% Global Cement Manufacturer Achieves $1.5M improvement in yield margins 2.

article thumbnail

Book Review: Logistics Clusters-Delivering Value and Driving Growth

OCTOBER 24, 2012

Case Studies . Book Review: Logistics Clusters-Delivering Value and Driving Growth. Recently, Ive found the new book called " Logistics Clusters: Delivering Value and Driving Growth ". Recently, Ive found the new book called " Logistics Clusters: Delivering Value and Driving Growth ". Author of the Book.

Blockchain in Supply Chain: 2 Ethereum-Based Projects That Demonstrate How Blockchain Can Improve Supply Chains

FEBRUARY 6, 2018

Otherwise known as a distributed ledger, the automatic recording of data into the blockchain allows for cryptocurrencies such as Ethereum or Bitcoin to serve as way more than just a store of value. It’s still early days, but there are already two Ethereum-based projects that address some of the major problems that hamper logistics .

article thumbnail

Supply Chain Spotlight on Mexico: Takeaways from Logistic Summit & Expo 2015

APRIL 6, 2015

A clear sign that Mexico is currently in the supply chain spotlight was last month’s Logistic Summit & Expo 2015 in Mexico City, which attracted over 10,000 attendees and almost 200 exhibitors, including leading 3PLs, software vendors, and other supply chain and logistics companies from both the United States and Mexico.

Stay Connected

Join 136,000+ Insiders by signing up for our newsletter

  • Participate in Supply Chain Brief
  • How to achieve six-figure benefits from digitizing paper-based supply chain operation
  • 2019 Supply Chain Brief Summer Reading List
  • Stay At Home Reading List
  • Add a Source
  • Add a Resource
  • 2018 Supply Chain Brief MVP Awards
  • 2019 Supply Chain Brief MVP Awards
  • 2020 Supply Chain Brief MVP Awards
  • 2021 Supply Chain Brief MVP Awards
  • 2022 Supply Chain Brief MVP Awards
  • Thu. Jul 11
  • Wed. Jul 10
  • Tue. Jul 09
  • Mon. Jul 08
  • Jun 29 - Jul 05
  • Warehousing
  • Procurement
  • Transportation
  • Supply Chain
  • More Topics 

LinkedIn

Input your email to sign up, or if you already have an account, log in here!

Enter your email address to reset your password. a temporary password will be e‑mailed to you., be in the know on.

case study in distribution management

Supply Chain Brief

Expert insights. Personalized for you.

We organize all of the trending information in your field so you don't have to. Join 136,000+ users and stay up to date on the latest articles your peers are reading.

case study in distribution management

Get the good stuff

Subscribe to the following Supply Chain Brief newsletters:

You must accept the Privacy Policy and Terms & Conditions to proceed.

More

You know about us, now we want to get to know you!

Check your mail, we've sent an email to . please verify that you have received the email..

We have resent the email to

Let's personalize your content

Use social media to find articles.

We can use your profile and the content you share to understand your interests and provide content that is just for you.

Turn this off at any time. Your social media activity always remains private.

Let's get even more personalized

Choose topics that interest you., so, what do you do.

Are you sure you want to cancel your subscriptions?

Cancel my subscriptions

Don't cancel my subscriptions

Changing Country?

Accept terms & conditions.

It looks like you are changing your country/region of residence. In order to receive our emails, you must expressly agree. You can unsubscribe at any time by clicking the unsubscribe link at the bottom of our emails.

You appear to have previously removed your acceptance of the Terms & Conditions.

More

We noticed that you changed your country/region of residence; congratulations! In order to make this change, you must accept the Aggregage Terms and Conditions and Privacy Policy. Once you've accepted, then you will be able to choose which emails to receive from each site .

You must choose one option

Please choose which emails to receive from each site .

  • Update All Sites
  • Update Each Site

Please verify your previous choices for all sites

Sites have been updated - click Submit All Changes below to save your changes.

We recognize your account from another site in our network , please click 'Send Email' below to continue with verifying your account and setting a password.

You must accept the Privacy Policy and Terms & Conditions to proceed.

This is not me

Supply Chain Secrets

A ‘Case Study’ on Distribution Channels

Sep 21, 2021 | Case Studies , Chain of Responsibility , Distribution Channels , Logistics , Supply Chain , Videos , Vlogs | 2 comments

Distribution channels are frequently overlooked as a source of performance enhancement in the Supply Chain. But if you think outside the box, your company could save 18% annually.

Remember that one of the most important factors to consider when evaluating Distribution Channels would be the cost to serve. It can lead to some excellent alternative Distribution Strategies.

Editor’s Note: This post was originally published on September 08, 2021, under the title “A ‘Case Study’ on Distribution Channels and Thinking Outside the Box to Save 18% on Costs”  on Logistics Bureau’s website.

Contact Rob O'Byrne

Nice dickie

Rob

Thanks, Demetrius!

Submit a Comment Cancel reply

Your email address will not be published. Required fields are marked *

Save my name, email, and website in this browser for the next time I comment.

Recent Posts

  • Boost Your Logistics Performance With These Top 10 Tips! (Plus Extra Help)
  • Supply Chain & Logistics Coaching Coming Soon Online – Pick Your Topics
  • Why Choose Supply Chain As Your First Job?
  • Books and Guides

Distribution Center Optimization in Mexico

Global manufacturer depends on visibility and accuracy.

A Global Manufacturer

For this global industrial manufacturer of vehicles and engines, production depends on exceptional and reliable service throughout the supply chain. When the manufacturer was looking for a partner to manage its distribution centers, it sought a company familiar with the challenges of automobile supply chain management and decided on Penske Logistics. Penske has managed inventory in two of the manufacturer's facilities in Mexico since 2002.

As part of its work, Penske manages one 150,000-square-foot internal distribution center and one 400,000-square-foot external distribution center. It provides receiving, storage, sequencing, kitting and repacking. Penske handles large parts and modules as well as shipping racks and the trailer yard. Penske also designs and produces the material sequencing racks in-house, saving production space and reducing downtime.

Improved Supply Chain Visibility

The actions inside a distribution center are the catalyst for speeding deliveries, managing inventories and cutting costs. Penske's proprietary technologies track the flow of inventory through and around the distribution center, monitor product velocity, and provide advance notice of arrivals. Since coming on board, Penske has focused on reducing and controlling inventory, improving the receiving area and boosting productivity.

"Inventory visibility is crucial. Warehouse inventory has to be able to interface with the production side of the business and they have to be able to connect within the supply chain to know what is in the warehouse and what is on a truck or stored in a trailer." —Dave Bushee, vice president of logistics technology, Penske Logistics

The large number of SKUs and customization increased the need for visibility. The manufacturer focuses on mass production, but the degree of vehicle customization options drives high SKU counts – more than 60,000, which is as much as six times the part numbers in an automotive manufacturer's warehouse. This manufacturer also has sequencing of 106 commodities and has three sizes of tractors on the production line, which creates more variability that must be managed.

Penske leverages a data repository that provides a single, high-level, comprehensive view of the manufacturer's overall operations, which allows the team to increase efficiency. Information about incoming and outbound products can be transmitted electronically between supply chain partners, and the information is automatically loaded into the core system.

The data gives users the opportunity to track a product from the initial receipt to the final pick down to the individual SKU, ensuring a quick response in the event of a recall or a spike in demand. Visibility also helps optimize door-to-door movement in the warehouse yard, and the system can track where trailers are as they move or are parked for later processing.

Inventory Control

Before Penske, the manufacturer's inventory levels had grown to cover for a lack of visibility, consuming space and hindering efficiency. Through its improved visibility and accurate inventory information, the manufacturer was able to reduce its inventory buffer, freeing up space and capital.

Penske created standardized processes which ensure inventory, and the production line keeps moving. With sequencing of 106 commodities, there is no margin for error. Through its warehouse management system (WMS), Penske tracks inventory levels and can guarantee the quality of the sequencing. The WMS also provides greater visibility of part location and counts, so associates can quickly locate inventory and get it to the line faster. "You're constantly trying to be efficient and maximize the number of picks that an associate can do in a facility while also touching products as little as possible. Data allows that to happen," said Bushee.

Penske's engineers examine data to create slotting algorithms that identify the ideal locations for products to be slotted and stored in the distribution center. SKUs that are "high runners" are slotted to a forward pick location, but because customer demand can shift quickly, information is constantly analyzed.

Increased Inventory Accuracy

Greater visibility into what is happening in the supply chain and when it takes place is essential to operational success. Penske created a series of checks and balances that allows Penske associates and the manufacturer to drive accuracy. The information is presented in a timely manner, which allows the manufacturer to quickly identify a problem and act when something is not correct. What's more, Penske and the manufacturer hold weekly and monthly scorecard reviews.

Labor Management Improvements

Increased visibility also helps operators manage the workforce in the warehouse. Operators can log into the system to see what is headed for the warehouse and when it is expected to arrive so they can schedule the appropriate labor. Labor in the warehouse can be planned by working backward from the shipment dispatch, which ensures employees are available when and where they are needed. In addition, inbound shipment information can be used to understand and balance warehouse labor requirements for handling inbound shipments.

Through the WMS, Penske and the manufacturer can define and document standard performance expectations and then measure, track and report the performance of employees, departments and facilities.

Improvements to inventory control enabled the addition of a second assembly line to the plant. Penske is also able to adjust headcount as production volumes flex, providing added value.

Operations in Mexico

Penske's local presence in Mexico adds to the service level, allowing its team to be more focused on local sourcing, quality and safety. Penske Logistics currently employs more than 2,100 associates in Mexico and has decades of cross-border operations experience. Penske Logistics maintains significant investments in the region, including strategic locations along the border.

If needed, Penske can bring in labor from other operations, tapping into people who speak the language and know the culture.

Continued Growth

Throughout Penske's relationship with the manufacturer, Penske has adapted its people and processes as changes occur at the facilities and on the production line.

Keep Up With Logistics News

Sign up to receive Penske Logistics' digital newsletter containing the latest industry information.

Thanks for Your Interest

Penske will send you our latest industry communication just as soon as it becomes available.

SOLUTION SNAPSHOT

  • Manage a difficult relationship with the incumbent logistics provider who was resistant to change.
  • Provide a high level of service and complete reliability.
  • A high degree of vehicle customization options drove high SKU counts—60,000+.
  • To cover for lack of visibility, inventory levels grew, consuming space and hindering efficiency.

Penske provides distribution center management for this global, industrial manufacturer.

  • Provides material handling services in Mexico
  • Handles large parts and modules
  • Provides inventory management at two facilities – one internal (150,000+ sq. ft.) and one external (400,000+ sq. ft.)
  • Manages receiving, storage, sequencing, kitting and repacking
  • Oversees shipping racks and the trailer yard
  • Monitors the flow of products to ensure the production lines keep moving
  • Designs and produces the material sequencing racks in-house
  • Inventory: Conducted an overall analysis and optimized the routing and mode selection
  • Improving the material receiving area/process
  • Inventory reduction and control (lean)
  • Productivity
  • Visibility: Implemented technology that allows for visibility

Related Links

Industrial Manufacturing Warehousing and Distribution Network Design

  • Supply Chain Management
  • Lead Logistics Provider
  • Consulting Services
  • Network Design
  • Dedicated Contract Carriage
  • Shared Dedicated Transportation
  • Freight Management
  • ClearChain ® Control
  • Transportation Services
  • Transportation Management Solutions
  • Truckload Shipping Services
  • Warehousing and Distribution
  • Warehouse Design
  • Warehouse Operations
  • Multi-Client Warehousing
  • Freight Brokerage
  • Freight Forwarding
  • Become a Carrier for Penske

Contact Penske Logistics about our services.

  • Noatum Group
  • Get to know us
  • Our Leadership
  • Recognition and awards
  • Our history
  • Certifications
  • Maritime Containers
  • Air Containers
  • Conversion Tables
  • Dangerous goods labels
  • Goods tariff code

Freight Management

  • Contract Logistics / Warehouse & Distribution
  • Customs services
  • International Supply Chain Management
  • Project cargo logistics
  • Reefer Logistics

Automotive & Aerospace

Chemical industry, construction.

  • Consumer Electronics
  • Industrial Manufacturing

Oil and Gas

  • Pharma & Healthcare

Renewable Energy

Case studies.

  • Location & Contact
  • Maritime containers
  • Air containers
  • Get a quote

Home / Case Studies

air transport for mining industry

Case Study – Air transport services for mining industry

Our client needed to transport a total of 8 cable reels of 23 tons each from Shanghai. The challenge was to make the shipment in the shortest possible time with reasonable costs.

case-study-healthcare-logistics

Case Study – Air Charter for Healthcare

The start of the Covid-19 vaccination campaign was imminent and our client needed regular shipments of syringes from China, where the factory was located, to Peru so they could ensure the vaccination campaign ran smoothly.

air-charter-mining

Case study – Air charter for the mining sector

Our client needed to urgently ship two conveyor belts from Santiago de Chile to Lima. These conveyor belts are used to move the mineral extracted from the mine into the storage area. Due to their size and weight, more than 60 tonnes, it was necessary to study in detail what would be the best transport solution to deliver in the shortest possible time.

case study in distribution management

Case Study – Automotive logistics

To create a cost saving solutions with enhanced service levels, whilst maintaining existing structures and warehouse facilities.

case study in distribution management

Case Study – Retail logistics: LG Harris

When understanding the LG Harris supply chain requirements, Noatum Logistics quickly identified that their buying terms were CIF (cost, insurance, freight) across the majority of their supply base. This prevented shipment visibility for LG Harris until the goods arrived into port. Accounting for over 1,000 TEU per annum was a major headache. The supply chain model was completely reactive with little or no reporting or key-performance-indicator (KPI) management. This created high demurrage charges, inbound-inventory and stock-control challenges at the LG Harris distribution centre (DC) located in the Midlands (UK).

case study in distribution management

Case Study – Personal care logistics

The customer felt its supply chain was working fine. No pain, no need to change! However, having worked with Noatum Logistics in the past, and experienced improved operations, the new leader was willing to let us review the company’s pricing and route information on outbound shipments to the United States, Japan, Taiwan, Malaysia and Australia.

case study in distribution management

Case Study – Outdoor retailer logistics

The retailer faced major challenges with days-in-inventory and capacity at its distribution center (DC). Days-in-inventory time continued to increase over the prior five years The single distribution center experienced overly high storage levels, delays with unloading railcars and shipping containers, and an overall worsening in port-to-DC transit times (hovering around 40 days).

case study in distribution management

Case Study – Oil & Gas industry

With each unit weighing approximately 32,000 pounds, the company faced high shipping costs for the pumping units sourced from China.

case study in distribution management

Case Study – Oil and Gas logistics

The customer suspected they were being overcharged for shipping. They were not using freight forwarders, instead allowing manufacturers to arrange for the ocean-freight shipping of the oilfield equipment from China to Canada. Cargo was shipped using fixed load plans with no optimization for larger batches.

case study in distribution management

Case Study – Mining logistics

An initial assignment was for the movement of Autoclave and Flash Vessel pieces from their manufacturing plant, located 30 miles inland from the Shanghai port, to the mining project 90 miles east of Lima, Peru. The equipment pieces were over size and over weight, requiring special loading/unloading procedures; ocean, rail and ground transportation; and infrastructure modifications.

case study in distribution management

Case Study – High Tech logistics

With a significant segment of the semiconductor wafer foundry base moving to Asia, our customer decided to relocate operations closer to their end user. Our customer opened an equipment integration facility in Singapore near their customer who provides wafer fabrication equipment. Unfortunately, this move created an increase in real estate and labor costs, thus denying our customer the warehouse space to stage components for assembly and integration.

case study in distribution management

Case Study – Pharma&Healthcare logistics

Sourcing product from Korea, the customer initially used Noatum Logistics to assist with international freight forwarding and the custom clearance process for shipments to the U.S. As the customer grew their customer base and product offering, it was apparent their outsourced warehouse solution in the U.S. could not keep up with their needs. The end customers’ orders frequently required special packing, rush deliveries, and special project handling, straining the customer’s inventory management practices.

case study in distribution management

Case Study – Fashion industry logistics: Gant

Capitalise on the retail expertise and capabilities of Noatum Logistics, including our robust warehouse management technologies and local capacity. The benefits of greater inventory visibility and control would cascade into other supply chain functions including transportation, warehousing, distribution and customer service.

case study in distribution management

Case Study – Consumer Electronics logistics

A leading manufacturer of cell phone accessories was in a crisis. Issues with an overseas partner completely shut down their supply chain. They needed a new logistics services provider to quickly step in and get shipments moving. The manufacturer also recognized the need to rethink its supply chain to gain better control over vendors, reduce costs and achieve more efficient handling of orders.

case study in distribution management

Case Study – Apparel retailer logistics

A retail client of Noatum Logistics for international freight forwarding services sought additional assistance for improving control over its global supply chain. The client recognized that greater visibility to purchase orders and shipments would lead to better purchasing, transportation and distribution decisions.

case study in distribution management

Case Study – Industrial Manufacturing logistics

Our customer is a leading multinational manufacturer of automobiles and agricultural machinery. The company entered the U.S. market in 2000; since 2002, Noatum Logistics has handled the company’s customs brokerage at Noatum Logistics’ Houston branch.

case study in distribution management

Case Study – Fashion industry logistics

Founded in 1920, New Era Cap Company is an American headwear company headquartered in Buffalo, New York. Best known for being the official on-field cap for Major League Baseball, the official sideline cap for the National Football League, and the official on-court cap for the National Basketball Association.

case study in distribution management

Case Study – High tech firm

The customer, a global provider of secure IP/Ethernet switching solutions, sources products from South China and Taiwan for sales in the United States. They identified cost containment objectives and wanted to improve the overall performance of their supply chain.

Logistics Services

  • Freight management

Logistics Solutions

Key industries.

  • Automotive Logistics
  • Chemicals Logistics
  • Construction Logistics
  • Fashion Logistics
  • Food Logistics
  • Furniture Logistics
  • Mining Logistics
  • Oil and Gas Logistics
  • Retail Logistics
  • Renewable Energy Logistics
  • Case studies

case study in distribution management

Noatum Logistics is a company of Noatum group

Reach out: [email protected] Whistleblowing: Online portal

© Copyright 2024. All Rights Reserved.

  • Livro de reclamaçoes
  • Privacy Policy
  • Legal notice
  • All our business are subject to Noatum Logistics USA LLC Terms & Conditions

Select your country

To read this content please select one of the options below:

Please note you do not have access to teaching notes, demand management in downstream wholesale and retail distribution: a case study.

Supply Chain Management

ISSN : 1359-8546

Article publication date: 21 September 2012

This case study aims to examine the role of demand management in balancing distribution efficiency and responsiveness to customer needs in the downstream of a retail supply chain.

Design/methodology/approach

A major machine part supplier in Australia is used as a case study to investigate the challenges faced by the industry in distributing goods to customers. The use of demand management techniques to help improve distribution efficiency without significantly impacting on responsiveness is also explored.

The findings of the case study reveal that appropriate demand management measures, such as customer segmentation and price discrimination, can help improve overall distribution efficiency of the supply chain while providing the required responsiveness to meet genuine customer needs. Other management attempts, such as vendor‐managed inventory and rationalisation of retail network, can facilitate demand aggregation and improve vehicle utilisation in distribution with minor impact on customer service. These changes require a full understanding of customer requirements and supply capabilities of the company as well as corresponding adjustments in business strategy, leadership style, and organisational culture.

Research limitations/implications

This study lends insight into the use of demand management techniques to improve efficiency in downstream wholesale and retail distribution, thereby enhancing sustainability and profitability of business. To serve mainly as a case study and an illustration of the approach, the scope of the study is limited to six stores in the distribution network of the case company.

Practical implications

Retailers can explore the use of demand management techniques to increase distribution efficiency and hence competitiveness of the company. The approach can also assist managers in adopting best practices among stores and facilitate more effective allocation of distribution resources to serve different market segments.

Social implications

Using demand management techniques to increase distribution efficiency can reduce delivery frequency and total travel distance. This will help lessen energy usage, carbon emission, traffic congestion, and other negative impacts on the environment.

Originality/value

Research in retail distribution efficiency to date focuses mainly on delivery optimisation through routing and scheduling. Attempts to link demand with supply and use demand management techniques to improve distribution efficiency are relatively limited. This paper fills the gap in the literature by investigating the value of demand management in distribution and explores empirically the significance of the approach to achieve higher wholesale and retail distribution efficiency.

  • Demand management
  • Customer segmentation
  • Price discrimination
  • Retail supply chain
  • Distribution
  • Distribution management
  • Process efficiency

Hung Lau, K. (2012), "Demand management in downstream wholesale and retail distribution: a case study", Supply Chain Management , Vol. 17 No. 6, pp. 638-654. https://doi.org/10.1108/13598541211269247

Emerald Group Publishing Limited

Copyright © 2012, Emerald Group Publishing Limited

Related articles

All feedback is valuable.

Please share your general feedback

Report an issue or find answers to frequently asked questions

Contact Customer Support

ICMR India

  • Case Studies

Nestlé India: Adopting a Regional Approach in its Distribution Strategy

Nestlé India: Adopting a Regional Approach in its Distribution Strategy

Case Code: OPER148
Case Length: 12 Pages
Period: 1959-2020
Pub Date: 2021
Teaching Note: Available
Price: Rs.300
Organization :
Industry :
Countries : India
Themes:

The case “Nestlé India: Adopting a Regional Approach in its Distribution Strategy” discusses the logistics and distribution strategy of Nestlé India Limited (NIL), the Indian subsidiary of the world’s largest food and beverage company, Nestlé SA. The case gives a brief insight into the distribution structure of Nestlé, and the terms of operations it employed for its intermediaries. It then provides details about how technology helped NIL’s outbound logistics system at NIL. The case moves on to discuss the possibilities of channel conflicts and stresses upon the need for NIL to strengthen its own distribution channel in order to avoid differences between prices of its products in different regions, product positioning, and promotional campaigns. The hyper local cluster approach of NIL is dealt with as well – wherein it divided India into various clusters and then crafted product placements, distribution, marketing, and promotions for each cluster. Suresh Narayanan, Chairman and Managing Director of NIL, was hopeful that NIL would continue to improve its distribution strategies to serve the Indian markets better.

  • Understand the importance of an efficient distribution and logistics management system in reducing costs and creating value for customers.
  • Get insights into the distribution operations and the distribution channels utilized by a leading FMCG company.
  • Devise ways to manage relationships with intermediaries.
  • Recognize the most common reasons for channel conflict.
  • Examine the role played by technology in the outbound logistics of a retail company.
  • Scrutinize how a company can alter its distribution strategy to cater to the varied tastes and preferences of customers in different regions.

Managing Distribution; Distribution Strategy; Relationships with Intermediaries; Hyper Local Cluster Approach; Stock Policy; Sales Forecasting; Target Setting; Technology in Outbound Logistics; Channel Conflict; Holt-Winters model; Demand Forecasting; and Supply Chain Management; Sales force Management; Retail Management; Production & Materials Management; FMCG

Buy this case study (Please select any one of the payment options)





Copyright © 2020 - 2025 All Rights Reserved - icmrindia.org

Academia.edu no longer supports Internet Explorer.

To browse Academia.edu and the wider internet faster and more securely, please take a few seconds to  upgrade your browser .

Enter the email address you signed up with and we'll email you a reset link.

  • We're Hiring!
  • Help Center

paper cover thumbnail

Logistics‐driven packaging innovation: a case study at IKEA

Profile image of 佳兴 李

Related Papers

Nofoma Conference Proceedings

Gunilla Jonson

case study in distribution management

International Journal of Production Economics

Chin-shan Lu

Lecture Notes in Economics and Mathematical Systems

M. Grazia Speranza

The International Journal of Logistics Management

Andrej Lisec

Chris Dominic

Today’s trends are the ever growing competition with increased globalization and sustainability. Together with ongoing technological developments it has made it easier to demand right quality of products and services, this has also resulted in increased demands for legislation and traceability. This A model has been created to increase knowledge of packaging logistics performance, which covers interaction between packaging system with its users. This also model includes the tool. 'Packaging Scorecard' that measures the packaging logistics performance and shows the packagingrelated deficiencies that exist in various levels of the value chain. Furthermore, the tool developed to enable efficient product development. The developed model will provide support for the development of packaging strategies to change the existing systems or develop new systems. The strategies also take into account the agents involved in the supply-demand chain by demonstrating the requirements on the packaging and how small changes in the packaging system contributes to a significant improvement in the value chain. Theoretical tool enables a better integration between in picking up the desired packaging information interacting with the agents and the right knowledge on packaging can be handled more efficiently. New functions and roles for companies operating in the various logistics processes were identified for example the research has identified a new type of service the Network Integrator that manages integrate the supply chain with the demand chain. This function was also identified in the packaging area and this agent named the Packaging Integrator.development has also an impact on packaging and packaging logistics. This dissertation deals with packaging, logistics and performance when packaging interacts with users and take a standpoint by finding answers to the research question: How can a systematic and holistic approach to packaging increase the logistics performance to create efficiency and effectiveness? The purpose of this work is to increase knowledge regarding the packaging and its interacting role with agents in the Supply-Demand Chain in order to improve Packaging Logistics Performance. Further the thesis aims to increase knowledge in the area of Packaging Logistics Performance. Performance in packaging logistics is about doing the right thing and things right as well as position products and services relative to its competitor. To increase understanding of the Supply-Demand Chain the tool CATWOE (Customer, Agents, Transformation processes, World view, Owners and Environment) was applied. This tool futher developed for to adapt with packaging logistics performance and complexity theory. The general methodology was action based research and case studies. The developed model illustrates packaging systems and how they perform in order to create conditions for better and more efficient packaging logistics performance. The thesis explores and presents ways to improve the opportunities that co-operate for better packaging, and integration of value chains. Research in theoretical contribution is to demonstrate knowledge of packaging systems, understanding the interactive roles and existing requirements in the Supply-Demand-Chain. Practical contributions were the valuable empirical knowledge and increased understanding of packaging requirements and its interactions with agent to create conditions for effectiveness, efficiency and differentiation.

The Asian Journal of Shipping and Logistics

Yapa Mahinda Bandara

Engineering costs and production …

Eero Eloranta

Engineering Costs and Production Economics, 21 (1991) 155169 Elsevier 155 Experiences of different approaches in logistics Eero Eloranta and AriPekka Hameri Helsinki University of Technology, Institute of Industrial Automation, Helsinki, Finland Kimmo Lahteenmaki ...

Garland Chow

Transportation Research Part E-logistics and Transportation Review

Silvia Morales Silva

Logistics and Transport

Róbert Magda

Transportation is essential for the functioning of the economy since mobility greatly supports growth and job creation. The transport sector in the EU employs about 10 million people and provides approximately 5% of the GDP. The efficiency of the transport systems is a prerequisite for competitiveness and significantly affects the quality of life of people. Logistics plays a key role in terms of sustainable and competitive mobility in Europe and other objectives, such as a cleaner environment, security of energy supply, and widely available transport facilities. The use of safe and environmentally friendly vehicles is the main priority of all modes of transportation. The key changes include alternative fuels, new materials, new propulsion systems as well as information technology and traffic management techniques. The organization of the transportation of raw materials and finished products within and outside the EU depends on the efficient operation of logistic networks. This is pr...

Loading Preview

Sorry, preview is currently unavailable. You can download the paper by clicking the button above.

RELATED PAPERS

XIX PANAM - Congreso Panamericano de Ingenieria de Transito, Transporte y Logistica

Orlando F O N T E S Lima Jr

Mercedes Gaitán-Angulo

GERMAN CASTRO

International Journal of Logistics Research and Applications

David Menachof

Transportation Journal

Sameer Kumar

International Handbook of Maritime Business. Ed.: K. Cullinane

Hercules Haralambides

leigh sparks

Johan Woxenius

European Journal of Service Management

Andrzej Bujak

Iwona Wasielewska-Marszałkowska

Haluk Cagri Kasimoglu , Seyda Topaloglu , Erdal Nebol , Fatih Cavdur

MESUT AKDAG

Saman Lohrasbi

Tim Maalsnes

David Keithly

Snezana Bardarova

Cathy Macharis

Decision Technologies and Applications

James H Bookbinder

Eduard Dinu

Springer eBooks

Diane Riopel

Norge Isaias Coello Machado

Project Management Scientific Journal | Published by: Dama Academic Scholarly & Scientific Research Society

Dama Academic Scholarly & Scientific Research Society

Zenodo (CERN European Organization for Nuclear Research)

Veronica Bulat

AARF Publications Journals

RELATED TOPICS

  •   We're Hiring!
  •   Help Center
  • Find new research papers in:
  • Health Sciences
  • Earth Sciences
  • Cognitive Science
  • Mathematics
  • Computer Science
  • Academia ©2024
  • Arts & Humanities
  • Communications

A Case Study on Distribution Management

Related documents.

Difference between merchandising, manufacturing & service

Add this document to collection(s)

You can add this document to your study collection(s)

Add this document to saved

You can add this document to your saved list

Suggest us how to improve StudyLib

(For complaints, use another form )

Input it if you want to receive answer

Event Management

What can an all-in-one event management platform do.

11 Jul 2024 | Jessica F. Lillian | 3 minutes

case study in distribution management

There’s no question that events deliver unique value. A rich and varied event calendar is a critical part of any effective business strategy. Each opportunity for interaction with prospects and clients contributes a wealth of data , new leads, relationship-building, and much more. 

But from small internal webinars to massive user conferences drawing thousands of attendees from around the world, every type of event also comes with particular requirements and specifications. Can one event platform do it all?

At RainFocus, we’ve always known that a single purpose-built event platform can do it all — and that a single, unified approach to event technology streamlines event planning and execution while fully unlocking the power of event data for memorable attendee experiences . 

We were excited to read “The All-in-One Event Management Platforms Landscape, Q3 2024.” This new report from Forrester, a leading research and advisory firm, recognizes RainFocus among “notable vendors” and discusses the many use cases for all-in-one event management platforms. 

“B2B events play a commanding role in B2B marketing, with aggregate spend across all formats consistently among the largest areas for the CMO. However, too often organizations treat events as siloed tactics,” the report explains. “Different teams plan and execute events and make decisions around event technology in isolation, with little consideration given to integrating the different formats to deliver more connected and personalized attendee journeys. Taking a more centralized approach and selecting and deploying an all-in-one event management platform to run all customer facing events mitigates this.” 

Sound familiar? That classic industry challenge has motivated us at RainFocus from the start. We believe the pivot to virtual events in 2020 and subsequent exuberant return to in-person events have highlighted the importance of a flexible event platform for in-person, virtual, and hybrid events. 

According to Forrester, the market for all-in-one event management platforms is considered “mature.” The report’s top identified current market dynamics in the event tech industry include macroeconomic factors and buyers’ budgetary pressures, the rise of AI as a disruptor, and the growing importance of fully integrating event platforms into the overall tech stack. 

“Deep, bilateral integrations help marketers deliver more customized attendee experiences, drive stronger alignment with sales, and augment demand and account-based marketing programs,” the report says. 

RainFocus also believes in the power of secure, effortless integrations to unlock the full power of events. We’ve built a growing network of technology partners, including Adobe. In addition, the recent launch of RainFocus for Salesforce supports sales teams’ involvement within their familiar daily tech ecosystem .

As a company that prioritizes innovation and continuous client-centric enhancements , we’re thrilled to see discussion of industry advancement from research and advisory firms and other unbiased expert observers. We can’t wait to see what comes next! 

BRE announces winners of BREEAM Awards 2024 - BRE Group

Bre announces winners of breeam awards 2024.

  • 10 July 2024

BRE has revealed the winners of its annual BREEAM Awards 2024 – a celebration of the projects and organisations leading the way in sustainable building design, development and management. These took place on Wednesday 10th July in London, bringing together the global built environment industry to celebrate achievements made in sustainable development and innovation. 

BREEAM has been the world-leading sustainability assessment method for planning projects, infrastructure and buildings for over 30 years. There are now 2.33 million BREEAM-registered buildings across 102 countries, with 610,000 having received certification to date.  Among this year’s winners was HAUT Amsterdam – one of the tallest timber-hybrid buildings in the world – which took home the award for the Best New Construction for a Residential Project. 

 alt=

GRESB partnered with BREEAM, their eighth year working together, to recognise responsible investment in the built environment and the role that BREEAM plays in supporting ESG strategy. Taking home the GRESB Portfolio Integration & Commitment Award was KKR, whose BREEAM certification of 39 industrial and residential properties across the United States provided a clear roadmap for value creation and risk mitigation, strengthening KKR’s competitive edge and aligning with GRESB goals and broader sustainability commitments.

A major industrial unit and an iconic Tudor Street landmark, both in London, picked up the BREEAM Lifecycle Award and Best Refurbishment & Fit Out Project respectively. SEGRO’s 33,000 sq ft facility at 2 Auriol Drive became the first industrial refurbishment of its kind to achieve BREEAM Outstanding and is expected to receive an EPC A+ rating. Meanwhile, JRA’s reimagination of the Grade II listed Northcliffe building, maintaining its industrial heritage as a 1920s print works, saw it achieve BREEAM Outstanding. 

case study in distribution management

Gillian Charlesworth, CEO of BRE, said: “We are thrilled to recognise some of the greatest sustainability achievements in the built environment at this year’s BREEAM Awards. 

“Embracing science-based sustainability methodologies like BREEAM can deliver significant impacts for businesses, investors and for society as a whole. It is inspiring to see the innovative ways in which sustainability is being fostered and put front-and-centre across all our award winners and wider BREEAM scheme members. 

“With our network of over 14,000 assessors ensuring rigorous sustainability practices across the globe, we look forward to continuing to drive net zero ambitions across the entire built environment.”

The full list of 2024 BREEAM Award winners announced yesterday includes:

  • HAUT Amsterdam 

Best New Construction Residential Project    

  • Unilever Hive 

Best New Construction Non-residential Project    

  • The Northcliffe 

Best Refurbishment & Fit-out Project    

  • Mark e.o. HUIZEN

Best BREEAM In-Use Residential Building

  • CTP Clubhaus

Best BREEAM In-Use Non-residential Building

GRESB Portfolio Integration & Commitment Award

  • Duurzaamheids Certificering 

BREEAM Assessor Company Award

  • 2 Auriol Drive

BREEAM Lifecycle Award

  • Fugro NewHQ

Peoples’ Choice Whole of BREEAM Award

Notes to Editors For all press enquiries, please contact [email protected]  For the full list of judges and sponsors at this year’s awards, please see here . 

About BRE & BREEAM BRE is a world leading, multi-disciplinary, building science centre with a mission to improve buildings and infrastructure, through cutting-edge research and knowledge generation. BRE maintains a range of products, services, standards and qualifications that are used around the world to bring about positive change in the built environment. Learn more at www.bregroup.com.

BREEAM is the world’s leading sustainability assessment methodology for master planning projects, infrastructure and buildings. It recognizes and reflects the value in higher performing assets across the built environment lifecycle, from new construction, through performance in operation, to refurbishment. BREEAM does this through third party certification of the assessment of an asset’s environmental, social and economic sustainability performance, using standards developed by BRE. This means BREEAM rated developments are more sustainable environments that enhance the well-being of the people who live and work in them, help protect natural resources and make for more attractive property investments. Learn more at www.breeam.com.

Register your interest for 2025

Discover more about BREEAM Awards

Browse all BREEAM Award 2024 winners' case studies:

Asset publisher.

case study in distribution management

HAUT Amsterdam first residential building in Netherlands to achieve BREEAM Outstanding

case study in distribution management

Heritage meets sustainability: The Northcliffe's journey to BREEAM Outstanding

case study in distribution management

BREEAM guides sustainable design and construction of Unilever HIVE’s food innovation hub

case study in distribution management

ASR elevates residential sustainability with Mark e.o. Huizen BREEAM In-Use project

case study in distribution management

CTP Clubhaus: leading the way with BREEAM Outstanding in sustainable industrial development

case study in distribution management

KKR scales sustainability with BREEAM across a diverse US property portfolio

case study in distribution management

Pioneering sustainability in the built environment with DuurzaamheidsCertificering BV, winners of the BREEAM Best Assessor Award 2024

case study in distribution management

Innovative refurbishment at 2 Auriol Drive sets new standards with BREEAM Outstanding achievement

  • Case Report
  • Open access
  • Published: 13 July 2024

Implantable cardiac monitor and leadless pacemaker in the management of syncope due to intermittent high-degree atrioventricular block: a case report

  • Nian Tang 1 ,
  • Xiaoxiao Chen 1 ,
  • Denghong Zhang 1 &
  • Hongfei Li 1  

Journal of Cardiothoracic Surgery volume  19 , Article number:  443 ( 2024 ) Cite this article

Metrics details

Lead dislodgements, tricuspid valve failure, and wound infections are prominent issues addressed by leadless pacemakers (LPM). These devises have emerged as viable alternatives to conventional transvenous pacemakers. LPMs offer minimized complications and effective pacing, particularly beneficial for elderly patients with a low body mass index (BMI) who are at heightened infection of risk. The Micra AV leadless pacemaker was released in the US in 2020, featuring a VDD pacing mode akin to conventional pacemakers. It senses atrial activity to pace ventricular beats while maintaining the natural atrioventricular activation sequence. Micra AV achieves atrioventricular synchronization through mechanical sensing principles. Ongoing research aims to assess its efficacy, implantation feasibility, and clinical safety.

Case presentation

An 83-year-old man with a history of syncope was the focus of this case study. An implantable cardiac monitor (ICM) recorded occasional high-degree atrioventricular block in the patient. Subsequently, the Micra AV was implanted via the left femoral vein, and its settings were adjusted in accordance with data obtained from the ICM. No significant issues regarding pacing threshold or impedance were found during the follow-up examinations post-surgery. Importantly, the patient experienced a noticeable reduction in symptoms compared to before the implantation.

This case underscores the significance of ICM monitoring in elucidating cardiac events leading to syncope and guiding appropriate treatment. It also highlights the successful outcomes and reliable implantation of the Micra AV for managing high-degree atrioventricular block. This study contributes to the growing body of evidence supporting the adoption of leadless pacemakers as a viable option for patients requiring cardiac pacing, particularly those vulnerable to complications associated with traditional pacemakers. It provides real-world evidence of Micra AV’s efficacy and safety, further validating its role in clinical practice.

Peer Review reports

Leadless pacemakers (LPM) have emerged as an alternative to traditional transvenous pacemakers, effectively avoiding problems such as wound infection, lead dislodgements, and tricuspid valve dysfunction. This is particularly beneficial for elderly patients with a low body mass index (BMI), who are at heightened risk of infection. In 2020, Micra AV, a leadless pacemaker featuring a VDD pacing function (ventricular pacing following atrial sensing, preserving the normal atrioventricular activation sequence), was launched in the United States. Micra AV achieves atrioventricular synchronization using mechanical sensing principles. Currently, its clinical safety, implantation feasibility, and effectiveness are undergoing post-marketing research and data collection.

Here, we present the case of an 83-year-old man with a history of syncope, who was found to have intermittent high-degree atrioventricular block using an Insertable Cardiac Monitor (ICM) (Fig.  1 ). Subsequently, Micra AV was implanted through the left femoral vein, and its parameters were adjusted based on the data collected by the ICM.

figure 1

ICM monitors 6:1 height atrioventricular block electrocardiogram

Case introduction

All procedures performed in this study adhere to the ethical standards of the institution and/or National Research Council guidelines, and the principles outlined in the Declaration of Helsinki (2013 revision). Written informed consent was obtained from the patient to publish this case report along with accompanying images. Copies of the written consent are available for review by the editorial board.

The patient, an 83-year-old man, was hospitalized due to recurrent syncope episodes over the past two years. Initially, he experienced sudden dizziness and weakness with subsequent loss of consciousness, followed by spontaneous recovery after a few minutes without significant discomfort. Similar intermittent episodes occurred intermittently thereafter. Echocardiography revealed left atrial enlargement with normal left ventricular systolic function. Coronary angiography indicated coronary atherosclerosis. Head MRI + MRA showed an old lacunar infarct in the left lateral ventricle and pontine area, alongside intracranial atherosclerosis. Electroencephalogram results were unremarkable. Holter ECG monitoring confirmed sinus rhythm with intermittent second-degree type I atrioventricular block, prompting a Class IIa recommendation for pacemaker implantation [ 1 ]. Further electrophysiological examination was advised to pinpoint the site of block or to implant an ICM to monitor cardiac events during syncope [ 2 ]. The patient opted for ICM implantation, which revealed evidence linking intermittent high-degree atrioventricular block to his syncope episodes. Given the risks of syncope and potential progression to permanent atrioventricular block, the patient’s pacing indication was upgraded to Class I, necessitating pacemaker implantation. Due to the patient’s advanced age, slender physique, limited life expectancy, and low anticipated ventricular pacing requirement, Micra AV was chosen and implanted via femoral vein.

Surgery procedure

Firstly, the left femoral vein was accessed for temporary pacemaker insertion. Subsequently, attempts to dilate the 8 F and 10 F sheaths placed via the right femoral vein revealed mild stenosis of the right lateral iliac vein during femoral venography (Fig.  2 a). Due to unsuccessful dilation, the approach was shifted to the left femoral vein. The temporary pacemaker from the left femoral vein was removed, and a new temporary pacemaker was inserted via the internal jugular vein. Left femoral venography confirmed patency of the left femoral vein, external iliac vein, and common iliac vein (Fig.  2 b). During the procedure, the patient experienced obvious distension pain and mild vasovagal reaction. Administration of atropine stabilized the patient’s vital signs, enabling successful delivery of the leadless pacemaker system through the sheath, crossing the tricuspid valve into the right ventricle. Contrast agent injection through the delivery system assessed positioning against the right ventricular septum in various body positions (Fig.  3 a and b).After satisfactory angiography, Micra AV was released, and a traction test confirmed secure fixation. Three surgeons confirmed stable positioning of the pacemaker head metal winglets in the myocardium. Pacing parameters post-implantation were as follows: threshold 0.63 V / 0.24ms, impedance 680Ω, R-wave sensing 10.7 mV, indicating satisfactory electrical function. The procedure was completed in 60 min without complications. There was no evidence of bleeding or fluid leakage at the puncture site on the first day after surgery. Program-controlled electrical parameters remained stable after the operation. The patient was discharged from the hospital on the second day post-surgery.

figure 2

Venography Results. ( a ) Right femoral venography showed mild stenosis of the iliac vein; ( b ) Left femoral venography showed clear blood vessels

figure 3

Post-implantation radiographs. Radiographs in the left and right anterior oblique projections ( a and b ) following implantation of the leadless pacemaker

At the 3-month follow-up, program-controlled examination of pacemaker showed stable pacing thresholds and impedance for Micra AV, with appropriate atrioventricular tracking. Atrial-ventricular (AM-VP) and ventricular pacing (VP) frequencies were 12.3% and 2.3%, respectively (Fig.  4 ). The patient continues to exhibit intermittent high-degree atrioventricular block as the underlying heart rhythm.

figure 4

Pacemaker remote interrogation at 3-month follow-up

While transvenous pacemakers remain a well-established treatment for chronic arrhythmias, complications related to eads and/or pocket management significantly restrict their utility. Leadless pacemakers have emerged as an alternative to traditional transvenous pacemakers. Our case identified the underlying cause of syncope through ECG events recorded by an ICM implantation, highlighting the feasibility and safety of dual-chamber leadless pacemaker implantation in elderly patients.

Unlike traditional pacemakers, safety and effectiveness of leadless pacemaker have been improved [ 3 ]. Micra AV is particularly suitable for patients at high risk of infection such as the elderly, those with severe wasting, abnormal venous anatomy, diabetes mellitus, and those undergoing hemodialysis. Micra AV utilizes a built-in triaxial acceleration sensor to detect blood flow acceleration during atrial contraction, thereby triggering ventricular pacing and providing atrioventricular synchronous pacing. The clinical study MARVEL II enrolled a total of 75 patients [ 4 ], with 40 cases included in the effectiveness analysis. The results showed that among patients with normal sinus rhythm and complete atrioventricular block, the median resting atrioventricular synchronization rate was 94.3%, with an average atrioventricular synchronization rate of 89.2%. These findings validate the efficacy of Micra AV in managing patients with atrioventricular block. With the emergence of Micra AV, more patients with atrioventricular block can now benefit from leadless pacemakers [ 5 ]. The decision to use the Micra AV leadless pacemaker in this case was guided by a comprehensive evaluation of the patient’s risk factors, anatomical considerations, and the potential clinical advantages of a leadless system. We believe that this approach yielded the most facorable outcome for the patient, aligning with our goals to minimize complications and maximize therapeutic efficacy. In summary, the patient, aged 83, diagnosed with intermittent high-degree atrioventricular block and normal sinus rhythm, alongside a slender physique, limited life expectancy, and low anticipated ventricular pacing requirements. The use of a VDD type leadless pacemaker like Micra AV was deemed particularly beneficial in this context.

Julius Jelisejevas et al. ‘s study [ 6 ] involved 143 patients who underwent continuous Micra TPS implantation, with 87% implanted via the right femoral vein and 13% via the left femoral vein. Left femoral vein access for Micra TPS implantation is safe, effective, comparable to traditional right femoral vein access, achieving excellent implantation success rates. In our case, left femoral vein access was chosen because the right iliac vein presented limitations, precluding passage. The implantation of Micra AV proceeded smoothly, with successful delivery, release, and secure fixation in the lower right ventricular space. The patient experienced transient mild vasovagal reaction due to distending pain during the procedure, but recovered promptly. Typically, conventional Micra TPS implantation through the right femoral vein targets median septum of the right ventricle. However, in this instance using the left femoral vein approach, the final positioning was in the middle to lower septum, influenced by the placement of the 27F delivery sheath closer to the right atrial lateral wall. The angle through the tricuspid ring differed, resulting in a distinct final device position.

In addition, the cardiac event recorded by ICM in this case was intermittent high-degree atrioventricular block. Consequently, the conduction mode switch was activated during parameter adjustment, transitioning the Micra AV from VDD pacing mode to VVI + mode, the pacemaker provides ventricular pacing support at a rate of 40 beats per minute when atrioventricular conduction recovers. The conduction function was monitored every 8 h, and if a ventricular rate greater than 40 beats per minute was detected, the pacemaker maintained VVI + mode. This configuration conserves battery power and extends the pacemaker’s lifespan while ensuring pacing needs are met, specifically tailored for patients with intermittent atrioventricular block. The parameters of the Micra AV were set based on ECG events recorded by the ICM, enhancing the safety and efficacy of pacing support provided to the patient.

We present the case of an elderly patient with atrioventricular block who underwent successful implantation of Micra AV via a left femoral vein approach following detection of an ECG event by an ICM. This case underscores the diagnostic utility of implantable ECG event monitors in investigating unexplained syncope episodes. It also validates the safety and effectiveness of the new Micra AV generation in elderly patients, expanding indications to include those with sinus rhythm and AVB.

Data availability

The datasets used and/or analysed during the current study are available from the corresponding author on reasonable request.

Abbreviations

Leadless Pacemakers

Insertable Cardiac Monitor

Glikson M, Nielsen JC, Kronborg MB, Michowitz Y, Auricchio A, Barbash IM, et al. 2021 ESC guidelines on cardiac pacing and cardiac resynchronization therapy. Eur Heart J. 2021;42(35):3427–520.

Article   PubMed   Google Scholar  

Brignole M, Moya A, de Lange FJ, Deharo JC, Elliott PM, Fanciulli A, et al. 2018 ESC guidelines for the diagnosis and management of syncope. Eur Heart J. 2018;39(21):1883–948.

Bodin A, Clementy N, Bisson A, Pierre B, Herbert J, Babuty D, et al. Leadless or Conventional Transvenous Ventricular Permanent pacemakers: a Nationwide Matched Control Study. J Am Heart Assoc. 2022;11(16):e025339.

Article   PubMed   PubMed Central   Google Scholar  

Steinwender C, Khelae SK, Garweg C, Chan JYS, Ritter P, Johansen JB, et al. Atrioventricular synchronous pacing using a Leadless Ventricular Pacemaker: results from the MARVEL 2 study. JACC Clin Electrophysiol. 2020;6(1):94–106.

Chinitz L, Ritter P, Khelae SK, Iacopino S, Garweg C, Grazia-Bongiorni M, et al. Accelerometer-based atrioventricular synchronous pacing with a ventricular leadless pacemaker: results from the Micra atrioventricular feasibility studies. Heart Rhythm. 2018;15(9):1363–71.

Jelisejevas J, Breitenstein A, Hofer D, Winnik S, Steffel J, Saguner AM. Left femoral venous access for leadless pacemaker implantation: patient characteristics and outcomes. Europace. 2021;23(9):1456–61.

Download references

Acknowledgements

Not applicable.

This study is supported by Research on the application value of left bundle branch pacing under the guidance of multi-parameter cardiac magnetic resonance technique (Grant number 202319).

Author information

Authors and affiliations.

Geriatric Diseases Institute of Chengdu/Cancer Prevention and Treatment Institute of Chengdu, Department of Cardiology, Chengdu Fifth People’s Hospital (The Second Clinical Medical College, Affiliated Fifth People’s Hospital of Chengdu University of Traditional Chinese Medicine), Chengdu, 611137, China

Nian Tang, Xiaoxiao Chen, Denghong Zhang & Hongfei Li

You can also search for this author in PubMed   Google Scholar

Contributions

NT and HL conceived the conception of the study. NT, XC, DZ and HL significantly contributed to data collection. NT, XC, DZ and HL supervised the conduct of this study. NT drafted the original manuscript and HL critically reviewed and revised the manuscript draft. All authors approved the final version of the manuscript to be published.

Corresponding author

Correspondence to Xiaoxiao Chen .

Ethics declarations

Ethics approval and consent to participate.

The protocol was approved by the Clinical Research Ethics Committee of Chengdu Fifth People’s Hospital with informed consent from patients and their families.

Consent for publication

Written informed consent was obtained from the patient for publication of this case report and any accompanying images.

Competing interests

The authors declare no competing interests.

Additional information

Publisher’s note.

Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Rights and permissions

Open Access This article is licensed under a Creative Commons Attribution 4.0 International License, which permits use, sharing, adaptation, distribution and reproduction in any medium or format, as long as you give appropriate credit to the original author(s) and the source, provide a link to the Creative Commons licence, and indicate if changes were made. The images or other third party material in this article are included in the article’s Creative Commons licence, unless indicated otherwise in a credit line to the material. If material is not included in the article’s Creative Commons licence and your intended use is not permitted by statutory regulation or exceeds the permitted use, you will need to obtain permission directly from the copyright holder. To view a copy of this licence, visit http://creativecommons.org/licenses/by/4.0/ . The Creative Commons Public Domain Dedication waiver ( http://creativecommons.org/publicdomain/zero/1.0/ ) applies to the data made available in this article, unless otherwise stated in a credit line to the data.

Reprints and permissions

About this article

Cite this article.

Tang, N., Chen, X., Zhang, D. et al. Implantable cardiac monitor and leadless pacemaker in the management of syncope due to intermittent high-degree atrioventricular block: a case report. J Cardiothorac Surg 19 , 443 (2024). https://doi.org/10.1186/s13019-024-02962-x

Download citation

Received : 02 April 2024

Accepted : 30 June 2024

Published : 13 July 2024

DOI : https://doi.org/10.1186/s13019-024-02962-x

Share this article

Anyone you share the following link with will be able to read this content:

Sorry, a shareable link is not currently available for this article.

Provided by the Springer Nature SharedIt content-sharing initiative

  • Implantable ECG event monitor
  • Leadless atrioventricular synchronous pacemaker micra AV
  • High atrioventricular block

Journal of Cardiothoracic Surgery

ISSN: 1749-8090

case study in distribution management

Cart

  • SUGGESTED TOPICS
  • The Magazine
  • Newsletters
  • Managing Yourself
  • Managing Teams
  • Work-life Balance
  • The Big Idea
  • Data & Visuals
  • Reading Lists
  • Case Selections
  • HBR Learning
  • Topic Feeds
  • Account Settings
  • Email Preferences

3 Lessons from The Washington Post’s Leadership Turmoil

  • Adam Bryant

case study in distribution management

What to do when a new leader gets off to a controversial or rocky start.

The leadership questions surrounding new Washington Post CEO Will Lewis serve as a case study in the challenges of bringing in an outsider to lead an organization, highlighting the importance of transparency and alignment with company values. This article offers three lessons leaders can draw from it — as well as advice on how the Post and Lewis can move forward.

It’s never good for a newspaper when it becomes the story.

  • Adam Bryant is the senior managing director of the ExCo Group, an executive mentoring and leadership development firm. He is a coauthor, with Kevin Sharer, of The CEO Test: Master the Challenges That Make or Break All Leaders (Harvard Business Review Press, 2021) and the author of The Leap to Leader: How Ambitious Managers Make the Jump to Leadership (Harvard Business Review Press, 2023).

Partner Center

Information

  • Author Services

Initiatives

You are accessing a machine-readable page. In order to be human-readable, please install an RSS reader.

All articles published by MDPI are made immediately available worldwide under an open access license. No special permission is required to reuse all or part of the article published by MDPI, including figures and tables. For articles published under an open access Creative Common CC BY license, any part of the article may be reused without permission provided that the original article is clearly cited. For more information, please refer to https://www.mdpi.com/openaccess .

Feature papers represent the most advanced research with significant potential for high impact in the field. A Feature Paper should be a substantial original Article that involves several techniques or approaches, provides an outlook for future research directions and describes possible research applications.

Feature papers are submitted upon individual invitation or recommendation by the scientific editors and must receive positive feedback from the reviewers.

Editor’s Choice articles are based on recommendations by the scientific editors of MDPI journals from around the world. Editors select a small number of articles recently published in the journal that they believe will be particularly interesting to readers, or important in the respective research area. The aim is to provide a snapshot of some of the most exciting work published in the various research areas of the journal.

Original Submission Date Received: .

  • Active Journals
  • Find a Journal
  • Proceedings Series
  • For Authors
  • For Reviewers
  • For Editors
  • For Librarians
  • For Publishers
  • For Societies
  • For Conference Organizers
  • Open Access Policy
  • Institutional Open Access Program
  • Special Issues Guidelines
  • Editorial Process
  • Research and Publication Ethics
  • Article Processing Charges
  • Testimonials
  • Preprints.org
  • SciProfiles
  • Encyclopedia

land-logo

Article Menu

case study in distribution management

  • Subscribe SciFeed
  • Recommended Articles
  • Google Scholar
  • on Google Scholar
  • Table of Contents

Find support for a specific problem in the support section of our website.

Please let us know what you think of our products and services.

Visit our dedicated information section to learn more about MDPI.

JSmol Viewer

Nonlinear relationship of multi-source land use features with temporal travel distances at subway station level: empirical study from xi’an city.

case study in distribution management

1. Introduction

2. related work, 3.1. research area, 3.2. built environment variables, 3.3. smart card data, 4. methodology, 4.1. xgboost algorithm, 4.2. ssa algorithm.

  • Define the problem’s fitness function: Train the XGBOOST model based on the hyperparameter combinations and evaluate the model performance using methods such as cross-validation. Use the evaluation metrics as the value of the fitness function.
  • Initialize the population: generate an initial set of hyperparameter combinations as the population.
  • Iterative search: in each generation, evaluate the population based on the fitness function and select individuals with higher fitness.
  • Generate new individuals: based on the selected individuals, use the operations of the Sea Cucumber Optimization Algorithm (such as foraging and predator avoidance) to generate new individuals.
  • Update the population: update the population based on the newly generated individuals.
  • Termination condition: stop the search when the predetermined number of iterations is reached or the stopping condition is met, and return the hyperparameter combination with the highest fitness.

4.3. SHAP Attribution Analysis

5.1. descriptive analysis, 5.2. hyperparametric results of ssa method, 5.3. significance contribution of built environment factors, 5.4. comparison of model results, 5.5. shap summary chart, 5.6. shap partial dependence, 6. discussion and conclusions, 6.1. key findings, 6.2. policy implications, 6.3. limitations and future work, author contributions, data availability statement, acknowledgments, conflicts of interest.

  • Liu, L.; Wang, Y.; Hickman, R. How Rail Transit Makes a Difference in People’s Multimodal Travel Behaviours: An Analysis with the XGBoost Method. Land 2023 , 12 , 675. [ Google Scholar ] [ CrossRef ]
  • Kwon, J.-H.; Cho, G.-H. The Long-Lasting Impact of Past Mobility Dependence on Travel Mode Share in a New Neighborhood: The Case of the Seoul Metropolitan Area, South Korea. Land 2023 , 12 , 1922. [ Google Scholar ] [ CrossRef ]
  • Kim, M.; Cho, G.-H. Analysis on bike-share ridership for origin-destination pairs: Effects of public transit route characteristics and land-use patterns. J. Transp. Geogr. 2021 , 93 , 103047. [ Google Scholar ] [ CrossRef ]
  • Yin, J.; Cao, X.J.; Huang, X. Association between subway and life satisfaction: Evidence from Xi’an, China. Transp. Res. Part D Transp. Environ. 2021 , 96 , 102869. [ Google Scholar ] [ CrossRef ]
  • Gan, Z.; Yang, M.; Feng, T.; Timmermans, H.J. Examining the relationship between built environment and metro ridership at station-to-station level. Transp. Res. Part D Transp. Environ. 2020 , 82 , 102332. [ Google Scholar ] [ CrossRef ]
  • Chen, E.; Ye, Z.; Bi, H. Incorporating smart card data in spatio-temporal analysis of metro travel distances. Sustainability 2019 , 11 , 7069. [ Google Scholar ] [ CrossRef ]
  • Tao, T.; Cao, J. Exploring nonlinear and collective influences of regional and local built environment characteristics on travel distances by mode. J. Transp. Geogr. 2023 , 109 , 103599. [ Google Scholar ] [ CrossRef ]
  • Peng, H.; Wen-xi, L.; Yan, L.; Qi, X. Spatial Patterns of Nonlinear Effects of Built Environment on Beijing Subway Ridership. J. Transp. Syst. Eng. Inf. Technol. 2023 , 23 , 187. [ Google Scholar ] [ CrossRef ]
  • Wang, A.; Peng, J.; Ren, P.; Yang, H.; Dai, Q. Impact of the built environment of rail transit stations on the travel behavior of persons with disabilities: Taking 189 rail transit stations in Wuhan City as an example. Prog Geogr 2021 , 40 , 1127–1140. [ Google Scholar ] [ CrossRef ]
  • Lin, Y.; Fu, H.; Zhong, Q.; Zuo, Z.; Chen, S.; He, Z.; Zhang, H. The influencing mechanism of the communities’ built environment on residents’ subjective well-being: A case study of Beijing. Land 2024 , 13 , 793. [ Google Scholar ] [ CrossRef ]
  • Guo, H.; Bai, Y.; Hu, Q.; Zhuang, H.; Feng, X. Optimization on metro timetable considering train capacity and passenger demand from intercity railways. Smart Resilient Transp. 2021 , 3 , 66–77. [ Google Scholar ] [ CrossRef ]
  • Shang, P.; Li, R.; Yang, L. Optimization of urban single-line metro timetable for total passenger travel time under dynamic passenger demand. Procedia Eng. 2016 , 137 , 151–160. [ Google Scholar ] [ CrossRef ]
  • Ta, N.; Zhao, Y.; Chai, Y. Built environment, peak hours and route choice efficiency: An investigation of commuting efficiency using GPS data. J. Transp. Geogr. 2016 , 57 , 161–170. [ Google Scholar ] [ CrossRef ]
  • Khan, M.; Kockelman, K.M.; Xiong, X. Models for anticipating non-motorized travel choices, and the role of the built environment. Transp. Policy 2014 , 35 , 117–126. [ Google Scholar ] [ CrossRef ]
  • Guzman, L.A.; Peña, J.; Carrasco, J.A. Assessing the role of the built environment and sociodemographic characteristics on walking travel distances in Bogotá. J. Transp. Geogr. 2020 , 88 , 102844. [ Google Scholar ] [ CrossRef ]
  • Long, Y.; Thill, J.-C. Combining smart card data and household travel survey to analyze jobs–housing relationships in Beijing. Computers, Environment and Urban Systems 2015 , 53 , 19–35. [ Google Scholar ] [ CrossRef ]
  • Wang, Z.; Hu, Y.; Zhu, P.; Qin, Y.; Jia, L. Ring aggregation pattern of metro passenger trips: A study using smart card data. Phys. A Stat. Mech. Appl. 2018 , 491 , 471–479. [ Google Scholar ] [ CrossRef ]
  • Gan, Z.; Feng, T.; Wu, Y.; Yang, M.; Timmermans, H. Station-based average travel distance and its relationship with urban form and land use: An analysis of smart card data in Nanjing City, China. Transp. Policy 2019 , 79 , 137–154. [ Google Scholar ] [ CrossRef ]
  • Xu, X.-Y.; Kong, Q.-X.; Ji, J.-M.; Liu, J.; Sun, Q. Analysis of spatio-temporal heterogeneity impact of built environment on rail transit passenger flow. J. Transp. Syst. Eng. Inf. Technol. 2023 , 23 , 194. [ Google Scholar ] [ CrossRef ]
  • Zhou, M.; Wang, D.; Guan, X. Co-evolution of the built environment and travel behaviour in Shenzhen, China. Transp. Res. Part D: Transp. Environ. 2022 , 107 , 103291. [ Google Scholar ] [ CrossRef ]
  • Chang, T.; Yang, D.; Yang, Y.; Huo, J.; Wang, G.; Xiong, C. Impact of urban rail transit on business districts based on time distance: Urumqi Light Rail. J. Urban Plan. Dev. 2018 , 144 , 04018024. [ Google Scholar ] [ CrossRef ]
  • Chen, F.; Wu, J.; Chen, X.; Wang, J. Vehicle kilometers traveled reduction impacts of transit-oriented development: Evidence from Shanghai City. Transp. Res. Part D Transp. Environ. 2017 , 55 , 227–245. [ Google Scholar ] [ CrossRef ]
  • Choi, K. The influence of the built environment on household vehicle travel by the urban typology in Calgary, Canada. Cities 2018 , 75 , 101–110. [ Google Scholar ] [ CrossRef ]
  • Kim, J.; Brownstone, D. The impact of residential density on vehicle usage and fuel consumption: Evidence from national samples. Energy Econ. 2013 , 40 , 196–206. [ Google Scholar ] [ CrossRef ]
  • Zhang, L.; Hong, J.; Nasri, A.; Shen, Q. How built environment affects travel behavior: A comparative analysis of the connections between land use and vehicle miles traveled in US cities. J. Transp. Land Use 2012 , 5 , 40–52. [ Google Scholar ] [ CrossRef ]
  • Choi, J.; Lee, Y.J.; Kim, T.; Sohn, K. An analysis of Metro ridership at the station-to-station level in Seoul. Transportation 2012 , 39 , 705–722. [ Google Scholar ] [ CrossRef ]
  • Iseki, H.; Liu, C.; Knaap, G. The determinants of travel demand between rail stations: A direct transit demand model using multilevel analysis for the Washington DC Metrorail system. Transp. Res. Part A Policy Pract. 2018 , 116 , 635–649. [ Google Scholar ] [ CrossRef ]
  • Eliasson, J. Will we travel less after the pandemic? Transp. Res. Interdiscip. Perspect. 2022 , 13 , 100509. [ Google Scholar ] [ CrossRef ]
  • Wang, X.; Pei, T.; Li, K.; Cen, Y.; Shi, M.; Zhuo, X.; Mao, T. Analysis of changes in population’s cross-city travel patterns in the pre-and post-pandemic era: A case study of China. Cities 2022 , 122 , 103472. [ Google Scholar ] [ CrossRef ]
  • Liu, J.; Cao, Q.; Pei, M. Impact of COVID-19 on adolescent travel behavior. J. Transp. Health 2022 , 24 , 101326. [ Google Scholar ] [ CrossRef ]
  • Chen, K.; Steiner, R. Longitudinal and spatial analysis of Americans’ travel distances following COVID-19. Transp. Res. Part D Transp. Environ. 2022 , 110 , 103414. [ Google Scholar ] [ CrossRef ]
  • An, D.; Tong, X.; Liu, K.; Chan, E.H. Understanding the impact of built environment on metro ridership using open source in Shanghai. Cities 2019 , 93 , 177–187. [ Google Scholar ] [ CrossRef ]
  • Caset, F.; Blainey, S.; Derudder, B.; Boussauw, K.; Witlox, F. Integrating node-place and trip end models to explore drivers of rail ridership in Flanders, Belgium. J. Transp. Geogr. 2020 , 87 , 102796. [ Google Scholar ] [ CrossRef ]
  • Chen, E.; Ye, Z.; Wang, C.; Zhang, W. Discovering the spatio-temporal impacts of built environment on metro ridership using smart card data. Cities 2019 , 95 , 102359. [ Google Scholar ] [ CrossRef ]
  • Liu, M.; Liu, Y.; Ye, Y. Nonlinear effects of built environment features on metro ridership: An integrated exploration with machine learning considering spatial heterogeneity. Sustain. Cities Soc. 2023 , 95 , 104613. [ Google Scholar ] [ CrossRef ]
  • Chen, E.; Ye, Z.; Wu, H. Nonlinear effects of built environment on intermodal transit trips considering spatial heterogeneity. Transp. Res. Part D Transp. Environ. 2021 , 90 , 102677. [ Google Scholar ] [ CrossRef ]
  • Su, S.; Wang, Z.; Li, B.; Kang, M. Deciphering the influence of TOD on metro ridership: An integrated approach of extended node-place model and interpretable machine learning with planning implications. J. Transp. Geogr. 2022 , 104 , 103455. [ Google Scholar ] [ CrossRef ]
  • Yan, X.; Liu, X.; Zhao, X. Using machine learning for direct demand modeling of ridesourcing services in Chicago. J. Transp. Geogr. 2020 , 83 , 102661. [ Google Scholar ] [ CrossRef ]
  • Teixeira, J.F.; Lopes, M. The link between bike sharing and subway use during the COVID-19 pandemic: The case-study of New York’s Citi Bike. Transp. Res. Interdiscip. Perspect. 2020 , 6 , 100166. [ Google Scholar ] [ CrossRef ]
  • Yu, L.; Cong, Y.; Chen, K. Determination of the peak hour ridership of metro stations in Xi’an, China using geographically-weighted regression. Sustainability 2020 , 12 , 2255. [ Google Scholar ] [ CrossRef ]
  • De Gruyter, C.; Butt, A.; Davies, L. Exploring the potential for unbundling off-street car parking in residential apartment buildings. Transport Policy 2024. [ CrossRef ]
  • Yang, L.; Yu, B.; Liang, Y.; Lu, Y.; Li, W. Time-varying and non-linear associations between metro ridership and the built environment. Tunn. Undergr. Space Technol. 2023 , 132 , 104931. [ Google Scholar ] [ CrossRef ]
  • Yang, H.; Zhao, Z.; Jiang, C.; Wen, Y.; Muneeb Abid, M. Spatially Varying Relation between Built Environment and Station-Level Subway Passenger-Distance. J. Adv. Transp. 2022 , 2022 , 7542560. [ Google Scholar ] [ CrossRef ]
  • Zhao, J.; Deng, W.; Song, Y.; Zhu, Y. What influences Metro station ridership in China? Insights from Nanjing. Cities 2013 , 35 , 114–124. [ Google Scholar ] [ CrossRef ]
  • Sohn, K.; Shim, H. Factors generating boardings at Metro stations in the Seoul metropolitan area. Cities 2010 , 27 , 358–368. [ Google Scholar ] [ CrossRef ]

Click here to enlarge figure

VariableDescriptionMeanSTDUnit
LU Area of commercial land around station120.018107.658Acre
LU Area of recreational land around station19.80535.065Acre
LU Area of residential land around station626.096288.492Acre
LU Area of working land around station61.44156.512Acre
LU Area of secondary school land around station6.6346.508Acre
LU Area of university land around station14.64029.219Acre
LU Degree of land use mix around station0.3430.232
POI Number of condominiums around station56.28755.451
POI Number of sports and leisure centers around station32.33333.693
POI Number of scenic spots around station6.34510.959
POI Number of cultural services around station69.45976.169
POI Number of hotel residences around station51.41461.134
POI Number of shopping points around station8.6678.537
POI Number of catering services around station179.655154.154
POI Number of companies around station103.436132.414
SURR Density of road network around station3.3681.504km/km
SURR Number of bus lines around station89.97747.165
SURR House prices around station11,149.72697.441CNY
SURR Number of houses around station12,720.33411,057.133
STAT Distance from station to city center7.4944.035km
IDSwipe TimeType of Entry/Exit StationLineStation
1F02270220201123062152129860
1F02271120201123062217131600
1F02410820201123083509213300
1F02531A2017112306210523258
HyperparameterizationExplanationRange of ValuesPreferred Value
max_depthMaximum depth of the tree[1, 10]4
learning_rateLearning rate[0.01, 0.1]0.09
subsampleSubsampling rate[0.5, 0.9]0.75
colsample_bytreeColumn sampling rate[0.5, 0.9]0.62
n_estimatorsNumber of regression trees[100, 200]154
GammaLeaf node splitting threshold[0, 5]0
Morning Peak Evening Peak
VariableRelative
Importance (%)
RankingVariableRelative
Importance (%)
Ranking
STAT 43.2101STAT 66.3391
POI 27.9972SURR 10.2592
SURR 6.2153SURR 6.1913
LU 5.3494SURR 6.1344
LU 3.9965LU 2.7795
SURR 3.8436LU 1.5166
LU 2.0097POI 1.1597
POI 1.4638LU 1.0578
POI 1.0999LU 0.9839
LU 1.01110POI 0.90110
Peak PeriodModelR-SquaredMAERMSE
Morning peakSSA-XGBOOST0.6331114.6601420.421
XGBOOST0.6111145.2511468.254
GBDT0.5771215.8021515.450
OLS0.4151315.4541592.725
Evening peakSSA-XGBOOST0.5831277.1251572.279
XGBOOST0.5441312.2521624.201
GBDT0.5111342.2511671.007
OLS0.4081411.0521715.445
The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

Li, P.; Yang, Q.; Lu, W. Nonlinear Relationship of Multi-Source Land Use Features with Temporal Travel Distances at Subway Station Level: Empirical Study from Xi’an City. Land 2024 , 13 , 1021. https://doi.org/10.3390/land13071021

Li P, Yang Q, Lu W. Nonlinear Relationship of Multi-Source Land Use Features with Temporal Travel Distances at Subway Station Level: Empirical Study from Xi’an City. Land . 2024; 13(7):1021. https://doi.org/10.3390/land13071021

Li, Peikun, Quantao Yang, and Wenbo Lu. 2024. "Nonlinear Relationship of Multi-Source Land Use Features with Temporal Travel Distances at Subway Station Level: Empirical Study from Xi’an City" Land 13, no. 7: 1021. https://doi.org/10.3390/land13071021

Article Metrics

Article access statistics, further information, mdpi initiatives, follow mdpi.

MDPI

Subscribe to receive issue release notifications and newsletters from MDPI journals

  • Environment
  • Science & Technology
  • Business & Industry
  • Health & Public Welfare
  • Topics (CFR Indexing Terms)
  • Public Inspection
  • Presidential Documents
  • Document Search
  • Advanced Document Search
  • Public Inspection Search
  • Reader Aids Home
  • Office of the Federal Register Announcements
  • Using FederalRegister.Gov
  • Understanding the Federal Register
  • Recent Site Updates
  • Federal Register & CFR Statistics
  • Videos & Tutorials
  • Developer Resources
  • Government Policy and OFR Procedures
  • Congressional Review
  • My Clipboard
  • My Comments
  • My Subscriptions
  • Sign In / Sign Up
  • Site Feedback
  • Search the Federal Register

The Federal Register

The daily journal of the united states government.

  • Legal Status

This site displays a prototype of a “Web 2.0” version of the daily Federal Register. It is not an official legal edition of the Federal Register, and does not replace the official print version or the official electronic version on GPO’s govinfo.gov.

The documents posted on this site are XML renditions of published Federal Register documents. Each document posted on the site includes a link to the corresponding official PDF file on govinfo.gov. This prototype edition of the daily Federal Register on FederalRegister.gov will remain an unofficial informational resource until the Administrative Committee of the Federal Register (ACFR) issues a regulation granting it official legal status. For complete information about, and access to, our official publications and services, go to About the Federal Register on NARA's archives.gov.

The OFR/GPO partnership is committed to presenting accurate and reliable regulatory information on FederalRegister.gov with the objective of establishing the XML-based Federal Register as an ACFR-sanctioned publication in the future. While every effort has been made to ensure that the material on FederalRegister.gov is accurately displayed, consistent with the official SGML-based PDF version on govinfo.gov, those relying on it for legal research should verify their results against an official edition of the Federal Register. Until the ACFR grants it official status, the XML rendition of the daily Federal Register on FederalRegister.gov does not provide legal notice to the public or judicial notice to the courts.

Updates to Floodplain Management and Protection of Wetlands Regulations To Implement the Federal Flood Risk Management Standard

A Rule by the Federal Emergency Management Agency on 07/11/2024

Document Details

Information about this document as published in the Federal Register .

Document Statistics

Enhanced content.

Relevant information about this document from Regulations.gov provides additional context. This information is not part of the official Federal Register document.

Regulations.gov Logo

  • FFRMS_Policy_For_Rulemaking_Appendix_A
  • FEMA FFRMS Policy
  • FFRMS_Final_Rule_RIA_20240703 CLEAN
  • Regulatory Impact Analysis
  • FFRMS Regulatory Impact Analysis
  • FFRMS CISA-State-of-the-Science-Report
  • FFRMS Appendix A
  • FEMA Proposed Policy_Federal Flood Risk Management Standard (FFRMS)
  • FEMA FFRMS FloodPlain Determination Job Aid
  • 2022 Nonresidential FFRMS Report

Published Document

This document has been published in the Federal Register . Use the PDF linked in the document sidebar for the official electronic format.

Enhanced Content - Table of Contents

This table of contents is a navigational tool, processed from the headings within the legal text of Federal Register documents. This repetition of headings to form internal navigation links has no substantive legal effect.

FOR FURTHER INFORMATION CONTACT:

Supplementary information:, i. executive summary, a. purpose of the regulatory action, b. summary of the notice of proposed rulemaking (nprm), c. summary of changes from the nprm to the final rule, d. impacts of the final rule, ii. background and legal authority, a. executive order 11988 , “floodplain management”, b. statutory authority to require ffrms under fema grant programs, c. 44 cfr part 9 , “floodplain management and protection of wetlands”, d. executive order 13690 , the federal flood risk management standard and subsequent amendments to executive order 11988 , and revisions to the 1978 guidelines, e. substantive components of the ffrms, ffrms approach 1: cisa, ffrms approach 2: fva, ffrms approach 3: 0.2pfa, ffrms approach 4: update to ffrms, further guidance on application of the ffrms approaches to establishing the floodplain, f. summary of the 2023 proposed rule and proposed ffrms policy, severability, conforming changes to definitions, distinction between “actions subject to the ffrms” and other fema actions, emphasis on nature-based approaches, proposed ffrms policy, updated ffrms resources, g. summary of fema's final rule and updated policy, ffrms policy, iii. discussion of public comments and fema's responses, a. summary of public comments, b. comments in support of the rule, c. comments in general opposition to the rule, d. fema's authority for part 9 and revisions, e. definitions, 1. general comments on definitions, 4. critical action, 5. federal action, 6. floodplain, 7. nature-based approaches, 8. natural and beneficial values of floodplains and wetlands and natural features, 9. new construction, 10. practicable, 11. restore, 12. structures and facilities, 13. wetlands, 14. additional definitions requested, f. ffrms applicability, 1. generally, 2. fema specific programs, 3. facilities, g. ffrms approaches, general comments, cisa implementation, cisa applicability, cisa and equity considerations, 4. fourth approach, 5. alternatives to ffrms approaches, h. fema's ffrms policy approach, 2. application of the ffrms approaches for critical and non-critical actions, 3. alternative policy approaches, 4. comments on fema's ffrms policy, i. the ffrms and floodplain/wetland determination data, 1. data availability, 2. methodology, 3. use of state and/or local cisa data, 4. other data concerns, fema's regulatory mapping products, interagency tools, flooding characteristics, best available information, other data concerns, j. ffrms implementation, compliance/enforcement, costs and delays, appeals process, other implementation concerns, 2. coordination with other federal agencies, coordination with specific agencies, coordination with non-federal agencies, 3. outreach, 4. equity and environmental justice, k. emphasis on nature-based approaches, 1. general support, 2. implementation of nature-based solutions, l. other 8-step process comments, 2. wetlands identification and floodplain and wetlands preservation, 3. public notice, 4. impacts to floodplains and/or wetlands, 5. zero/no rise, 6. prohibiting the use of fill, 7. practicability, m. other comments, n. accessibility, o. regulatory impact analysis comments, 1. alternatives, 2. discount rates, 4. benefits, 5. benefit cost analysis (bca), 6. other ria comments, iii. discussion of changes, iv. regulatory analyses, a. executive order 12866 , regulatory planning and review, as amended, and executive order 13563 , improving regulation and regulatory review, pa projects, ia projects, hma projects, need for regulation, affected population, pa interim policy, hma interim policy, total costs, total benefits, total transfer payments, b. regulatory flexibility act, 1. assessment of small entities affected by the regulations, 2. analysis and steps taken to comply with the regulatory flexibility act, c. unfunded mandates reform act of 1995, d. paperwork reduction act of 1995, e. privacy act, f. executive order 13175 , consultation and coordination with indian tribal governments, g. executive order 13132 , federalism, h. national environmental policy act of 1969 (nepa), i. executive orders 12898 and 14096 on environmental justice, j. executive order 12630 , taking of private property, k. executive order 12988 , civil justice reform, l. executive order 13045 , protection of children from environmental health risks and safety risks, m. federal participation in the development and use of voluntary consensus standards and in conformity assessment activities, omb circular a-119, n. congressional review of agency rulemaking, list of subjects in 44 cfr part 9, part 9—floodplain management and protection of wetlands, appendix a to part 9 [removed], enhanced content - submit public comment.

  • This feature is not available for this document.

Enhanced Content - Read Public Comments

Enhanced content - sharing.

  • Email this document to a friend

Enhanced Content - Document Print View

  • Print this document

Enhanced Content - Document Tools

These tools are designed to help you understand the official document better and aid in comparing the online edition to the print edition.

These markup elements allow the user to see how the document follows the Document Drafting Handbook that agencies use to create their documents. These can be useful for better understanding how a document is structured but are not part of the published document itself.

Enhanced Content - Developer Tools

This document is available in the following developer friendly formats:.

  • JSON: Normalized attributes and metadata
  • XML: Original full text XML
  • MODS: Government Publishing Office metadata

More information and documentation can be found in our developer tools pages .

Official Content

  • View printed version (PDF)

This PDF is the current document as it appeared on Public Inspection on 07/10/2024 at 8:45 am. It was viewed 0 times while on Public Inspection.

If you are using public inspection listings for legal research, you should verify the contents of the documents against a final, official edition of the Federal Register. Only official editions of the Federal Register provide legal notice of publication to the public and judicial notice to the courts under 44 U.S.C. 1503 & 1507 . Learn more here .

Federal Emergency Management Agency, Department of Homeland Security.

Final rule.

On October 2, 2023, the Federal Emergency Management Agency (FEMA) published a notice of proposed rulemaking (NPRM) and supplementary policy that proposed to implement the Federal Flood Risk Management Standard (FFRMS) and update the agency's 8-step decision-making process for floodplain reviews by changing how FEMA defines a floodplain with respect to certain actions and how FEMA uses natural systems, ecosystem processes, and nature-based approaches when developing alternatives to locating a proposed action in the floodplain. After a careful review of the public comments received, FEMA is now issuing a final rule that implements the proposed rule, with some minor amendments.

This rule is effective September 9, 2024.

Portia Ross, Policy and Integration Division Director, Office of Environmental Planning and Historic Preservation, Resilience, DHS/FEMA, 400 C St. SW, Suite 313, Washington, DC 20472-3020. Phone: (202) 709-0677; Email: [email protected] .

The purpose of this regulatory action is to finalize a rulemaking that will improve the preparedness and resilience of communities and Federal assets against the increasing impacts of flooding. All Federal agencies, including FEMA, have long taken action to reduce the risk of flood loss, to minimize the impact of floods on human safety, health, and welfare, and to restore and preserve the natural and beneficial values served by floodplains when carrying out certain agency functions. Federal agencies accomplish this by applying the longstanding 8-step decision-making process to any action they take in floodplains to ensure they avoid, to the extent possible, the long- and short-term adverse impacts associated with the occupancy and modification of floodplains, and to avoid direct or indirect support of floodplain development wherever there is a practicable alternative.

This framework was originally established in 1977 by Executive Order 11988 , “Floodplain Management,” ( 42 FR 26951 ) which was issued in furtherance of the National Environmental Policy Act of 1969 (NEPA) ( 42 U.S.C. 4321 et seq. ), the National Flood Insurance Act of 1968 as amended (NFIA) ( 42 U.S.C. 4001 et seq. ), and the Flood Disaster Protection Act of 1973, as amended (Flood Disaster Protection Act) (Pub. L. 93-234, 87 Stat. 975). Executive Order 11988 was supplemented by guidance called “Floodplain Management Guidelines” issued in 1978 by the U.S. Water Resources Council (“1978 Guidelines”). [ 1 ] FEMA implemented Executive Order 11988 in 1980 through the promulgation of regulations at 44 CFR part 9 , “Floodplain Management and Protection of Wetlands,”  [ 2 ] which applies the 8-step decision-making process to all actions FEMA directly takes and to all actions that it funds through grants to eligible State, local, Tribal, and territorial (SLTT) governments, certain private non-profits, and individuals and households for pre- and post-emergency or disaster-related projects.

The first step in the 8-step process is to determine whether the action FEMA proposes to take or fund will occur in a floodplain or wetland. [ 3 ] Section (6)(c) of Executive Order 11988 defined the term “floodplain” to mean, at a minimum, “that area subject to a one percent or greater chance of flooding in any given year,” which is recognized as the “base floodplain.” Executive Order 11988 and the base floodplain definition remained unchanged from 1977 until 2015. In 2015, President Barack Obama amended Executive Order 11988 by adding a new flood risk reduction standard to the existing 8-step decision-making process to improve the Nation's resilience against the increasing impacts of flooding. [ 4 ] The flood risk reduction standard, called the Federal Flood Risk Management Standard (FFRMS), is a flexible framework to define the floodplain that allows agencies to choose among several approaches to expand the base floodplain to a higher vertical elevation and corresponding horizontal extent for all Federally Start Printed Page 56930 funded projects. Federally funded projects are defined as actions where Federal funds are used for new construction, substantial improvement, or repairs to address substantial damage to structures and facilities. [ 5 ] The amendments also direct agencies to use natural systems, ecosystem processes, and nature-based approaches when developing alternatives to locating the action in the floodplain. The Water Resources Council then updated the 1978 Guidelines and issued the “Guidelines for Implementing Executive Order 11988 , Floodplain Management, and Executive Order 13690 , `Establishing a Federal Flood Risk Management Standard and a Process for Further Soliciting and Considering Stakeholder Input' ” (“Revised Guidelines”)  [ 6 ] to provide additional information on the use of the FFRMS.

FEMA first partially implemented the FFRMS in its grant programs through policy using an interim approach that applied higher elevation requirements to eligible projects in existing floodplains. [ 7 ] FEMA then proposed to fully implement the FFRMS in its October 2, 2023 NPRM and supplementary policy. [ 8 ] FEMA proposed to prioritize the use of the Climate-Informed Science Approach (CISA) in its FFRMS implementation. The CISA establishes the required vertical elevation and corresponding horizontal floodplain, through the best-available, actionable hydrologic and hydraulic data and methods that integrate current and future changes in flooding based on climate science, in accordance with the Revised Guidelines. When such data is not available, FEMA's NPRM and supplementary policy proposed the use of other approaches depending on the criticality of the action. FEMA also proposed to require the use of natural systems, ecosystem processes, and nature-based approaches where possible.

FEMA has authority to require application of the FFRMS as a condition of funding in its grant programs based on the grant programs' authorizing statutes. Congress granted FEMA the authority to provide Federal assistance through multiple grant programs under the Robert T. Stafford Disaster Relief and Emergency Assistance Act (Stafford Act), [ 9 ] the NFIA, [ 10 ] the Homeland Security Act of 2002, [ 11 ] the Federal Fire Prevention and Control Act of 1974, [ 12 ] the Earthquake Hazards Reduction Act of 1977, [ 13 ] and various other appropriations acts. Under each of these authorities, FEMA may set grant eligibility criteria consistent with the respective purposes of such programs and FEMA's mission, including to protect Federal investments from the risks of further damage. [ 14 ] Under the Stafford Act and the NFIA, which authorize the programs that fund the majority of the actions subject to the FFRMS, FEMA has general rulemaking authority. [ 15 ] Further, FEMA has explicit authority under the Stafford Act to set the minimum standards for safe land use and construction standards required in the repair or construction of private and public facilities. [ 16 ]

This rule is an important first step toward mitigating future flood risk that will ultimately benefit communities by allowing them to recover from future disasters more efficiently and effectively. The United States is experiencing increased flooding and flood risk from changing conditions. [ 17 ] The full extent of future changes in flood risk has not yet been estimated across the full inventory of Federal, State, local, Tribal, and territorial properties. However, in a survey of Federal properties alone, an assessment identified over 40,000 individual Federal buildings and structures with a combined replacement cost of $81 billion (in 2020 dollars) located in the current 1 percent floodplain and approximately 160,000 structures with a total replacement cost of $493 billion (in 2020 dollars) located in the current 0.2 percent floodplain. [ 18 ] Approximately 10,250 individual Federal buildings and structures were identified in coastal areas with a combined replacement cost of $32.3 billion that would be severely impacted by an eight-foot sea-level rise scenario and over 12,195 individual Federal buildings and structures were identified with a combined replacement cost of over $43.7 billion under a ten-foot “worst case” sea level rise scenario. [ 19 ] The Federal fiscal exposure presented above can be reduced by enhancing resilience. This final rule will enhance resilience by ensuring that actions subject to the FFRMS are designed to be resilient to both current and future flood risks to minimize the impact of floods on human health, safety, and welfare and to protect Federal investments by reducing the risk of flood loss.

On October 2, 2023, FEMA published the NPRM “Updates to Floodplain Management and Protection of Wetlands Regulations to Implement the Federal Flood Risk Management Standard.”  [ 20 ] FEMA also published “FEMA Proposed Policy: Federal Flood Risk Management Standard (FFRMS)” with the proposed rule. [ 21 ] The proposed rule sought to change how FEMA defines a floodplain with respect to certain actions taken by the agency and require that FEMA use natural systems, ecosystem process, and nature-based approaches, where possible, when developing alternatives to locating a proposed agency action in the floodplain.

The FFRMS is a flood resilience standard that is required for Federally funded projects and provides a flexible framework to increase resilience against flooding and help preserve the natural values of floodplains and wetlands. For actions subject to the FFRMS, the NPRM proposed to update the definition of “floodplain” to the definition used in the Revised Guidelines, which allows the agency to establish the floodplain using any of the following three approaches or a fourth approach resulting from any other method in an update to the FFRMS:

  • Approach 1: Climate-Informed Science Approach (CISA): Utilizing the best-available, actionable hydrologic and hydraulic data and methods that integrate current and future changes in flooding based on climate science;
  • Approach 2: Freeboard Value Approach (FVA): The elevation and corresponding horizontal floodplain that result from using the freeboard  [ 22 ] value, reached by reached by adding 2 feet to the base flood elevation (BFE) for non-critical actions (+2' FVA) and from adding 3 feet to the BFE for critical actions (+3' FVA).
  • Approach 3: 0.2-percent-annual-chance Flood Approach (0.2PFA): 0.2 percent annual chance flood (also known as the 500-year flood); or
  • Approach 4: the elevation and flood hazard area that result from using any other method identified in an update to the FFRMS.

In many cases, each of these approaches would result in a larger floodplain and a requirement to design projects to be resilient at a higher vertical elevation. For actions that do not meet the definition of an action subject to the FFRMS, FEMA would continue to use the historical floodplain definition, with minor clarifying revisions to help stakeholders better understand the terminology. The NPRM further proposed the use, where possible, of natural systems, ecosystem processes, and nature-based approaches in the development of alternatives for all actions proposed in a floodplain. FEMA proposed other edits to 44 CFR part 9 , including edits to clarify the applicability of 44 CFR part 9 to specific FEMA programs and update the monetary thresholds in § 9.5, edits to incorporate the use of the internet in public notice requirement in § 9.8, edits to consolidate temporary housing requirements in § 9.13, and other clarifying edits to update citations and remove outdated terminology.

In this final rule, FEMA adopts the changes proposed in the NPRM and FFRMS policy with clarifications in consideration of the relevant comments. Consistent with comments received, FEMA's edits in this final rule add a Federal agency (the National Park Service) to the best available information sources list and incorporate the use of Indigenous Knowledge by adding Indian Tribal governments to that list. The best available information sources list appears at 44 CFR 9.7(c)(3) . The list is a non-exhaustive list of resources that FEMA may use to make floodplain determinations. Additional clarifying edits are included in §§ 9.5 and 9.7. The edits to the FFRMS policy accompanying this final rule clarify the use of the 0.2PFA in coastal areas and clarify FEMA's use of the Federal Flood Risk Management Floodplain Determination Job Aid (FFRMS Job Aid). FEMA describes these changes in detail below.

FEMA estimated the total impacts of this rule by analyzing the impact of the FVA, 0.2PFA and CISA for FEMA's Public Assistance (PA), Individual Assistance (IA), and Hazard Mitigation Assistance (HMA) grant programs. FEMA did so by examining the number of projects that would be subject to the proposed requirements in the first 10 years after the rule's publication. [ 23 ] FEMA's analysis focused on the costs, benefits, and transfer payments ( i.e., impacts on FEMA grants) that would result over a 50-year period from applying the requirements of the rule to those projects, for a total period of analysis spanning 60 years. Tables 1 and 2 show the total impacts under the three approaches for each of the affected programs.

case study in distribution management

Table 3 provides the estimated number of structures and facilities affected by the rule over the first 10 years, assuming that each approach is the only expansion option. Structures, which are walled and roofed buildings, would comply with the FFRMS through elevating or floodproofing to the required height. Facilities, which are any human-made or human-placed items other than a structure such as roads and bridges, would require different mitigation measures to comply with the increased resilience standard. The monetized impacts of this rule are representative of the floodproofing and elevation mitigation measures that are required of structures. However, for reasons explained in more detail later, FEMA was unable to monetize the impacts of the rule for facilities.

case study in distribution management

Quantified estimates of the benefits of this rule are available for only non-residential PA Category E projects, which are for structures. Due to the project-specific nature of facilities projects and numerous options for making them resilient, FEMA could not estimate the costs of improving flood resilience of facilities. [ 27 ] Table 2 shows that the total 60-year benefits for non-residential PA Category E projects in the first 10 years is $54.4 million (7 percent). This benefit is for adding one foot of freeboard, assuming a 59-inch sea level rise (SLR). [ 28 ] Although the cost for PA Category E projects is $133.3 million, this cost represents 5 feet of freeboard (FEMA's assumption for CISA). [ 29 ] FEMA does not have data to quantify the benefits of additional freeboard and thus the quantified benefits represent only a portion of the increased risk reduction that would be achieved through this rule. Ensuring projects are built to the height necessary to avoid additional loss scenarios would provide additional unquantified benefits of avoided damages to the structure, decreased cleanup time and disruption to the community, and increased public health and safety. Moreover, FEMA's use of CISA as its preferred approach would use the best available and actionable scientific data to tailor future flooding risk to each project ensuring that projects are built only to the height necessary and thus maximizing net benefits. Accordingly, FEMA believes the benefits of the rule—quantified and unquantified—would justify its costs.

The President issued Executive Order 11988 ( 42 FR 26951 , May 25, 1977) as amended by Executive Order 13690 , “Establishing a Federal Flood Risk Management Standard (FFRMS) and a Process for Further Soliciting and Considering Stakeholder Input,” ( 80 FR 6425 , Feb. 4, 2015) and Executive Order 14030 , “Climate-Related Financial Risk,” ( 86 FR 27967 , May 25, 2021) in furtherance of the NFIA ( 42 U.S.C. 4001 et seq. ); the Flood Disaster Protection Act of 1973, as amended (Pub. L. 93-234, 87 Stat. 975); and the NEPA ( 42 U.S.C. 4321 et seq. ). Each agency is responsible for implementing Executive Order 11988 , as amended, as allowed by and consistent with applicable law within their existing statutory authorities. [ 30 ]

Section II.A below describes Executive Order 11988 , the 1978 Guidelines, and the statutory authority underlying the Executive Order. Executive Order 11988 , along with the 1978 Guidelines, established an 8-step decision-making process by which Federal agencies carry out Executive Order 11988 's direction to avoid the long- and short-term adverse impacts associated with the occupancy and modification of the floodplain, and avoid the direct or indirect support of floodplain development whenever there is a practicable alternative.

Next, Section II.B describes FEMA's statutory authority to require its grant recipients to carry out repairs or construction in accordance with specific standards. Section II.C describes FEMA's implementing regulations at 44 CFR part 9 , which closely follow the model decision-making process under Executive Order 11988 . Section II.D describes the development of Executive Order 13690 , the FFRMS, and additional guidance in the Revised Guidelines issued in 2015, as well as subsequent amendments to Executive Order 11988 . Section II.E describes the substantive components of the FFRMS. Section II.F. describes FEMA's NPRM and supplementary policy implementing the FFRMS.

The President issued Executive Order 11988 ( 42 FR 26951 , May 25, 1977) in furtherance of the NFIA ( 42 U.S.C. 4001 et seq. ); the Flood Disaster Protection Act of 1973, as amended (Pub. L. 93-234, 87 Stat. 975); and the NEPA ( 42 U.S.C. 4321 et seq. ). The NFIA, as amended by the Flood Disaster Protection Act establishes a multi-purpose program to provide flood insurance, minimize exposure of property to flood losses, minimize the damage caused by flood losses, and guide the development of proposed construction, where practicable, away from floodplains. [ 31 ] The NFIA and the Flood Disaster Protection Act highlight coordination of flood insurance with land management programs in flood-prone areas. NEPA requires Federal agencies to analyze the reasonably foreseeable environmental effects of proposed major Federal actions and evaluate a reasonable range of alternatives to those actions, which includes the evaluation of the impacts of proposed actions in floodplains. [ 32 ] NEPA mandates that agencies “attain the widest range of beneficial uses of the environment without degradation, risk to health or safety, or other undesirable and unintended consequences.”  [ 33 ]

In furtherance of and consistent with this statutory foundation, Executive Order 11988 directs Federal agencies to avoid, to the extent possible, the long- Start Printed Page 56935 and short-term adverse impacts associated with the occupancy and modification of floodplains, where there is a practicable alternative. The Executive Order directs each Federal agency to provide leadership and take action to reduce the risk of flood loss, to minimize the impact of floods on human safety, health, and welfare, and to restore and preserve the natural and beneficial values served by floodplains in carrying out its responsibilities for: (1) acquiring, managing, and disposing of Federal lands and facilities; (2) providing federally undertaken, financed, or assisted construction and improvements; and (3) conducting Federal activities and programs affecting land use, including but not limited to water and related land resources planning, regulating, and licensing activities. Each agency has a responsibility to evaluate the potential effects of any actions it may take in a floodplain; to ensure that its planning, programs, and budget requests reflect consideration of flood hazards and floodplain management; and to prescribe procedures to implement the policies and requirements of the Executive Order.

To meet this direction, each agency, before taking an action, must determine whether the proposed action will occur in a floodplain. [ 34 ] Section (6)(c) of Executive Order 11988 defined the word “floodplain” to mean “the lowland and relatively flat areas adjoining inland and coastal waters including floodprone areas of offshore islands, including at a minimum, the area subject to a one percent or greater chance of flooding in any given year.”  [ 35 ] If the action will occur in a floodplain, the agency must consider alternatives to avoid adverse effects and incompatible development in the floodplain. If the agency finds that the only practicable alternative requires the action to occur in the floodplain, the agency must, prior to taking the action, design or modify the action to minimize potential harm to or within the floodplain. Additionally, the agency must prepare and circulate a notice explaining why the proposed action is located in the floodplain. Particularly relevant to FEMA, the Executive Order also requires agencies to provide appropriate grant funding guidance to applicants to encourage them to evaluate the effects of their proposals in floodplains, prior to submitting grant applications.

Executive Order 11988 directs agencies to prepare implementing procedures in consultation with the Water Resources Council (WRC), [ 36 ] FEMA, and the Council on Environmental Quality (CEQ). As noted, the WRC issued the 1978 Guidelines, the authoritative interpretation of Executive Order 11988 . [ 37 ] The 1978 Guidelines provided a section-by-section analysis, defined key terms, and outlined an 8-step decision-making process for carrying out the directives of Executive Order 11988 .

FEMA has authority to require application of the FFRMS as a condition of funding in its grant programs based on the grant programs' authorizing statutes. Congress granted FEMA the authority to provide Federal assistance through multiple grant programs under the Stafford Act, [ 38 ] the NFIA, [ 39 ] the Homeland Security Act of 2002, [ 40 ] the Federal Fire Prevention and Control Act of 1974, [ 41 ] the Earthquake Hazards Reduction Act of 1977, [ 42 ] and various other appropriations acts. Under each of these authorities, FEMA may set grant eligibility criteria consistent with the respective purposes of such programs and FEMA's mission, including to protect Federal investments from the risks of further damage. [ 43 ]

Congress enacted the Stafford Act  [ 44 ] to “provide an orderly and continuing means of assistance” to State and local governments in carrying out their responsibilities to alleviate the suffering and damage that result from disasters by, among other responsibilities, “encouraging hazard mitigation measures to reduce losses from disasters, including the development of land use and construction regulations” and “identifying the climate and natural hazard resilience of vulnerable communities.”  [ 45 ] FEMA has general authority under the Stafford Act to “prescribe such rules and regulations as may be necessary and proper to carry out the provisions of [the Stafford Act], and may exercise, either directly or through such Federal agency as the President may designate, any power or authority conferred to the President by [the Stafford Act].”  [ 46 ] The Stafford Act further grants FEMA explicit authority to set the minimum standards for safe land use and construction standards required in the repair or construction of private and public facilities. [ 47 ]

Congress enacted the NFIA to authorize a flood insurance program which is designed to “promote the public interest by providing appropriate protection against the perils of flood losses and encouraging sound land use by minimizing exposure of property to Start Printed Page 56936 flood losses” and the objectives of which should be “integrally related to a unified national program for flood plain management.”  [ 48 ] FEMA has general authority under the NFIA to “issue such regulations as may be necessary” to carry out its provisions. [ 49 ] Section 404 of the NFIA grants FEMA the authority to provide flood mitigation grant funding and requires the activities funded to be consistent with floodplain management criteria developed by the Administrator. [ 50 ]

Consistent with the NFIA, the Flood Disaster Protection Act, and NEPA, FEMA promulgated regulations implementing Executive Order 11988 at 44 CFR part 9 , “Floodplain Management and Protection of Wetlands.”  [ 51 ] Part 9 closely follows the 1978 Guidelines in setting forth FEMA's policy and procedures for floodplain management relating to disaster planning, response and recovery, and hazard mitigation. Part 9 generally applies to FEMA actions, including FEMA direct actions and FEMA's disaster and non-disaster assistance programs. [ 52 ] Pursuant to section 8 of Executive Order 11988 , part 9 does not apply to assistance provided for emergency work essential to save lives and protect property and public health and safety, performed pursuant to sections 403 and 502 of the Stafford Act, as amended ( 42 U.S.C. 5170b and 5192 ). In addition, FEMA applies part 9 programmatically to the National Flood Insurance Program (NFIP). [ 53 ] FEMA does not apply part 9 to site-specific actions under the NFIP because the establishment of programmatic criteria, rather than the application of the programmatic criteria to individual situations, is the action with the potential to influence or affect floodplains. [ 54 ]

Part 9 outlines FEMA's 8-step decision-making process for conducting floodplain management reviews before performing certain actions, including approval of grant funding. The 8-step decision making process is:

(1) Determine whether the proposed action is located in a wetland or floodplain and its potential to affect or be affected by a wetland or floodplain;

(2) Notify the public of the intent to carry out the proposed action within or affecting a wetland or floodplain, and involve the affected and interested public in the decision-making process;

(3) Identify and evaluate practicable alternatives to locating the proposed action in a floodplain or wetland, including alternative sites, actions, and the “no action” option;

(4) Identify the potential direct and indirect impacts associated with the occupancy or modification of floodplains and wetlands and the potential direct and indirect support of floodplain and wetland development that could result from the proposed action;

(5) Minimize the proposed action's potential adverse impacts and support to or within the floodplains and wetlands identified under Step 4;

(6) Re-evaluate the proposed action and other practicable alternatives identified in step 3 based on new information gained in steps 4 and 5;

(7) Inform the public of any final decision that the floodplain or wetland is the only practicable alternative; and

(8) Implement the action.

There are certain exclusions from all or some of the 8-steps for certain categories of actions being funded by FEMA. [ 55 ]

On January 30, 2015, the President issued Executive Order 13690 , “Establishing a Federal Flood Risk Management Standard (FFRMS) and a Process for Further Soliciting and Considering Stakeholder Input.”  [ 56 ] Executive Order 13690 amended Executive Order 11988 and established the FFRMS. It required FEMA to publish an updated version of the 1978 Guidelines (revised to incorporate the changes required by Executive Order 13690 and the FFRMS) in the Federal Register for notice and comment. Executive Order 13690 also required the WRC to issue final Guidelines to provide guidance to agencies on the implementation of Executive Order 11988 , as amended, consistent with the FFRMS. FEMA, acting on behalf of the Mitigation Framework Leadership Group (MitFLG), published a Federal Register notice for a 60-day notice and comment period seeking comments on a draft of the Revised Guidelines on February 5, 2015. [ 57 ] FEMA received over 556 separate submissions. [ 58 ] The final Revised Guidelines were issued on October 8, 2015. [ 59 ]

The Revised Guidelines contain an updated version of the FFRMS (located at Appendix G of the Revised Guidelines), reiterate key concepts from the 1978 Guidelines, and explain the new concepts resulting from the Start Printed Page 56937 FFRMS. In response to public comments, the MitFLG clarified the distinction between “actions” and “Federally funded projects.” On August 22, 2016, FEMA published an NPRM entitled “Updates to Floodplain Management and Protection of Wetlands Regulations To Implement Executive Order 13690 and the Federal Flood Risk Management Standard” in the Federal Register ( 81 FR 57402 ). The rulemaking would have revised FEMA's regulations on “Floodplain Management and Protection of Wetlands” to implement Executive Order 13690 . FEMA also proposed a supplementary policy entitled “FEMA Policy: Guidance for Implementing the Federal Flood Risk Management Standard (FFRMS)” (FEMA Policy 078-3), which would have further clarified how FEMA would apply the FFRMS. The notice of availability and request for comments for the supplementary policy also published in the August 22, 2016, Federal Register at 81 FR 56558 . On September 20, 2016, FEMA published a notice of data availability regarding a draft report, the 2016 Evaluation of the Benefits of Freeboard for Public and Nonresidential Buildings in Coastal Areas, which had been added to the docket for the proposed rule ( 81 FR 64403 ).

On August 15, 2017, the President issued Executive Order 13807 (“Establishing Discipline and Accountability in the Environmental Review and Permitting Process for Infrastructure Projects”) which revoked Executive Order 13690 . See 82 FR 40463 , Aug. 24, 2017. Accordingly, on March 6, 2018, in light of the revocation of Executive Order 13690 , FEMA withdrew the August 22, 2016, NPRM and supplementary policy ( 83 FR 9473 ). On May 20, 2021, the President issued Executive Order 14030 (“Climate-Related Financial Risk”)  [ 60 ] reinstating Executive Order 13690 , thereby reestablishing the FFRMS. Executive Order 14030 also states the Revised Guidelines issued in 2015 were never revoked and remain in effect. As such, FEMA reviewed its prior NPRM and proposed policy, and revised its approach to implementation based on lessons learned during and since the 2016 rulemaking process. Specifically, FEMA first partially implemented the FFRMS by policy with respect to covered projects in existing floodplains in its Public Assistance and Hazard Mitigation Assistance programs. [ 61 ] FEMA next proposed to fully implement the FFRMS through the NPRM, which proposed updates to FEMA regulations and a supplemental FFRMS policy. [ 62 ]

The FFRMS is a flexible framework to increase resilience against flooding and help preserve the natural values of floodplains and wetlands. [ 63 ] Incorporating the FFRMS will expand the floodplain and require projects to increase their resilience to flooding. Applying the FFRMS will help ensure that Federally funded projects will last as long as intended. In addition, the FFRMS and Revised Guidelines require the evaluation of natural features and nature-based approaches, where possible, in the analysis of practicable alternatives of the decision-making process for all Federal actions. Nature-based approaches can also help minimize an action's impacts to the floodplain and assist in restoring the natural and beneficial functions of floodplains.

Under the FFRMS, a Federal agency may establish the floodplain for actions subject to the FFRMS using any of the following approaches:

  • Approach 2: Freeboard Value Approach (FVA): Freeboard (1 percent annual chance flood elevation + X, where X is 3 feet for critical actions and 2 feet for other actions);
  • Approach 4: the elevation and flood hazard area that result from using any other method identified in an update to the FFRMS. [ 64 ]

The four approaches are described in further detail below.

The Revised Guidelines state that the CISA is the preferred approach, and that Federal agencies should use this approach when data to support such an analysis are available and actionable. The CISA uses existing, sound science and engineering methods ( e.g., hydrologic and hydraulic analysis and methods used to establish current flood elevations and floodplain maps), supplemented with best available and actionable climate science and consideration of impacts from projected land cover/land use changes, long-term erosion, and other processes that may alter flood hazards over the lifecycle of the Federal investment. [ 65 ] For areas vulnerable to coastal flood hazards, the CISA includes consideration of the regional sea-level rise variability during the lifecycle of the Federal action. This includes use of global mean sea-level-rise scenarios adjusted to the local relative sea-level conditions and would be combined with surge, tide, and wave data using state-of-the-art science in a manner appropriate to policies, practices, criticality, and consequences. For areas vulnerable to riverine flood hazards ( i.e., flood hazards stemming from a river source), the CISA would account for changes in riverine conditions due to current and future changes in climate and other factors such as land use, by applying state-of-the-art science in a manner appropriate to policies, practices, criticality, and consequences (risk). The CISA for critical actions would utilize the same methodology as used for non-critical actions that are subject to Executive Order 11988 , as amended, but with an emphasis on criticality as one of the factors for agencies to consider when conducting the analysis.

The FFRMS and Revised Guidelines define freeboard values as an additional 2 feet added to the 1 percent annual chance flood elevation, or, for critical actions, an additional 3 feet added to the 1 percent annual chance flood elevation. In other words, the floodplain established by the FVA is the equivalent of the 1 percent annual chance floodplain, plus either 2 or 3 feet of vertical elevation, as applicable based on criticality, and a corresponding increase in the horizontal extent of the floodplain. The increased horizontal extent will not be the same in every case. When the same vertical increase is applied in multiple actions subject to the FFRMS in different areas, the amount of the increase in the horizontal extent of the respective floodplains will depend upon the topography of the area surrounding the proposed location of the action.

Agencies may use available 0.2 percent annual chance (or “500-year”) flood data as the basis of the FFRMS elevation and corresponding floodplain extent. Under this approach, the same floodplain and elevation is used for critical and non-critical actions. The FFRMS and Revised Guidelines note that often the 0.2 percent annual chance flood elevation data provided by FEMA in coastal areas only considers storm-surge hazards; this data does not include local wave action or storm-induced erosion that are considered in the computation of flood elevations. The FFRMS and Revised Guidelines encourage agencies to obtain or develop the necessary data, including wave heights, to ensure that any 0.2 percent annual chance flood data applied will achieve an appropriate level of flood resilience or use the FVA approach instead for the proposed investment.

The MitFLG, in consultation with the Federal Interagency Floodplain Management Task Force (FIFM-TF), must reassess the FFRMS annually after seeking stakeholder input and provide recommendations to the WRC to update the FFRMS, if warranted. The WRC must issue an update to the FFRMS at least every 5 years. The updates ensure the floodplain determination process for actions subject to the FFRMS reflects current methodologies.

The FFRMS and Revised Guidelines state that when an agency does not use the CISA in a coastal flood hazard area and where the FEMA 0.2 percent annual chance flood elevation does not include wave height, or a wave height has not been determined, the 0.2 percent annual chance elevation should not be used, and the FVA should be used instead. The FFRMS and Revised Guidelines note that where the 0.2 percent annual chance flood elevation does not consider wave action, the result will likely either be lower than the current base flood elevation or the base flood elevation plus applicable freeboard. Where wave action has been incorporated into the 0.2 percent annual chance elevation, the 0.2 percent annual chance elevation can be used.

The Revised Guidelines state that for riverine flood hazard areas, agencies may select either the FVA or 0.2PFA (or a combination of approaches, as appropriate) when actionable science is not available, and an agency opts not to follow the CISA. The agency is not required to use the higher of the elevations but may opt to do so. The elevation standards of the FFRMS are not intended to supplant applicable State, Tribal, territorial, or local floodplain protection standards. If such standards exceed the FFRMS, an agency should apply those standards if the agency determines the application of the standards is reasonable considering the goals of Executive Order 11988 , as amended. [ 66 ]

The proposed rule set forth how FEMA would implement Executive Order 11988 , as amended, the FFRMS, and the Revised Guidelines as part of FEMA's floodplain management regulations, while also updating FEMA's 8-step process. The proposed rule included the following provisions, which remain unchanged in this final rule except as indicated in section I.C of this preamble.

The NPRM proposed to amend § 9.3 to remove the authorities section as redundant and to replace it with a severability section. FEMA did not receive any comments on its proposal to include a severability provision. The proposed severability provision is therefore incorporated in § 9.3 of this final rule without change. FEMA believes that its authority to require an 8-step decision making process and incorporate the FFRMS into it is well-supported in law and policy and should be upheld in any legal challenge. However, in the event that any portion of the proposed rule is declared invalid, FEMA intends that the various provisions of 44 CFR part 9 be severable. The provisions are not so interconnected that the rule's efficacy depends on every one of them remaining in place—implementation of the different provisions is sufficiently distinct that FEMA's aim of updating the 8-step process and incorporating the FFRMS would still be furthered by maintaining the other provisions. For example, if a court were to find unlawful FEMA's inclusion of the FFRMS approaches in § 9.7(c), FEMA intends to retain the inclusion of consideration of nature-based approaches in the appropriate steps of the 8-step decision making process and all other amendments to the 44 CFR part 9 not affected by the court decision. Similarly, if a court were to find unlawful FEMA's chosen approach in the proposed policy, FEMA intends to retain the regulatory changes implementing the FFRMS. Those provisions that are unaffected by a legal ruling can be implemented by an agency without requiring a new round of rulemaking simply to promulgate provisions that are not subject to a court ruling.

The NPRM proposed to amend § 9.4 to reflect the new definitions required by the FFRMS and Revised Guidelines, while also updating other definitions to clarify terms and leverage common usage that has evolved since the regulation was issued. The most significant definitional change proposed by the FFRMS was the change to the meaning of “floodplain.” To harmonize this change in § 9.4, the NPRM proposed to revise a few existing definitions and removed other definitions. In addition, the NPRM proposed to revise the remaining sections of 44 CFR part 9 that Start Printed Page 56939 refer generally to the floodplain or refer specifically to the base (or 100-year) floodplain or the 0.2 percent annual chance (or 500-year) floodplain, for clarity.

Step 1 in the 8-step process is to determine whether the proposed action is in the floodplain. Because Executive Order 11988 , as amended, and the FFRMS revised the definition of the “floodplain” that agencies use for “Federally funded projects,” the NPRM proposed to revise the first step to require FEMA to determine whether the proposed action falls within the definition of an “action subject to the FFRMS.” Under the proposed rule, if FEMA determined that the action is a Federally funded project, i.e., if FEMA determined that the action uses FEMA funds for new construction, substantial improvement, or to address substantial damage to a structure or facility, the FFRMS floodplain would apply. Alternatively, if FEMA determined that the action did not fall under the definition of an action subject to the FFRMS, the existing floodplain analysis would remain in place. For example, if the action was considered non-critical, the 1 percent annual chance floodplain applied, and if the action was considered critical, the 0.2 percent annual chance floodplain applied.

Executive Order 11988 , as amended, directs agencies to use, where possible, natural systems, ecosystem processes, and nature-based approaches in the development of alternatives for Federal actions in the floodplain. The NPRM proposed to incorporate this requirement in § 9.9, which addresses the requirement to consider practicable alternatives when determining whether to locate an action in the floodplain. This proposed requirement would apply regardless of whether the proposed action is a FEMA Federally funded project. To further explain this proposed requirement, the NPRM proposed to add a definition of “nature-based approaches,” meaning features designed to mimic natural processes and provide specific services such as reducing flood risk and/or improving water quality. The NPRM also proposed to add a definition of “natural features,” meaning the characteristics of a particular environment that are created by physical, geological, biological, and chemical processes and exist in dynamic equilibrium.

Consistent with the Revised Guidelines, FEMA proposed to update the factors integrated into its impact analysis and minimization measures (Step 4 and Step 5) to identify those opportunities for beneficial floodplain and wetland values, to include natural values related factors that prioritize water resource values, living resource values, and agricultural, aquacultural, and forestry resource values. Applying natural features or nature-based approaches as alternatives furthers the goals in 44 CFR part 9 and allows for FEMA to further encourage those actions that increase the natural and beneficial functions of the floodplain.

The NPRM proposed to update Step 1 of the 8-step process to describe the floodplain determination for those actions that are subject to the FFRMS, and Step 3 to require the consideration of natural features and nature-based approaches in the identification and evaluation of practicable alternatives. The NPRM also proposed to incorporate certain additional exclusions from all or some of the 8-steps for certain categories of actions being funded by FEMA. Specifically, FEMA proposed to remove private bridges and debris clearance and removal under section 502 of the Stafford Act from the 8-step process, while also updating the monetary thresholds for actions under sections 406 and 407 of the Stafford Act.

The proposed FFRMS policy outlined the FFRMS approach FEMA would use for actions subject to the FFRMS. FEMA's proposed FFRMS policy would be applicable to actions in the FFRMS floodplain where FEMA funds were used for new construction, substantial improvement, or to address substantial damage. Specifically, the proposed policy would require FEMA to determine the FFRMS floodplain according to the Climate-Informed Science Approach (CISA) for all locations where the best-available, actionable hydrologic and hydraulic data methods that integrate current and future changes in flooding based on climate science exist. When the CISA data was not available and not actionable for a critical action, the proposed FFRMS policy would require FEMA to determine the FFRMS floodplain as the area that would be inundated by the higher of either the 0.2 percent annual chance flood or the 3 feet of freeboard above the base flood elevation (BFE) for that location (the Freeboard Value Approach or FVA). When the CISA is not available and actionable for a non-critical action, the proposed FFRMS policy would require FEMA to determine the FFRMS floodplain as the area that would be inundated by the lower of either the 0.2 percent annual chance flood or the 2 feet of freeboard above the BFE for that location (the FVA). In coastal areas where the CISA data is not available and actionable, the proposed FFRMS policy would require the FVA be used if the available 0.2 percent annual chance flood elevation does not account for wave action.

FEMA noted in the policy and the NPRM that it was coordinating across the Federal government to develop tools, such as the FFRMS Job Aid published in the public docket associated with this rulemaking, [ 67 ] to assist agencies and stakeholders in determining the FFRMS floodplain and would rely on those tools as the best available information in making its determinations. The FFRMS Job Aid presents a general methodology to identify the FFRMS floodplain for each of the three approaches that relies on information from available FEMA FIRMs, U.S. Geological Survey (USGS) ground elevations, and the 2022 Sea Level Rise Technical Report sea level rise estimates. [ 68 ]

FEMA's proposed FFRMS policy also required that nature-based solutions and natural features be considered and implemented where possible to all actions that are subject to Step 3 of the 8-step decision-making process and not just those actions subject to the FFRMS. Nature-based solutions and natural features must be considered as an alternative action in Step 3. Where it is not possible to use natural features and nature-based solutions as an alternative on their own, they would be considered in conjunction with the proposed action as a minimization measure in Step 5.

The FFRMS approaches include the CISA, an “approach that uses the best-available, actionable hydrologic and hydraulic data and methods that integrate current and future changes in flooding based on climate science.” The Revised Guidelines and Appendix H help to define the “best available and actionable science,” stating that best-available generally refers to science, data or information that is: Start Printed Page 56940

  • transparent—clearly outlines assumptions, applications, and limitations;
  • technically credible—transparent subject matter or more formal external peer review, as appropriate, of processes and source data;
  • usable—relevance and accessibility of the information to its intended users; and
  • legitimate—perceived by stakeholders to conform to recognized principles, rules, or standards.

Legitimacy might be achieved by existing government planning processes with the opportunity for public comment and engagement. [ 69 ]

Actionable science includes theories, data, analyses, models, projections, scenarios and tools that are:

  • relevant to the decision under consideration;
  • reliable in terms of its scientific or engineering basis and appropriate level of peer review;
  • understandable to those making the decision;
  • supportive of decisions across wide spatial, temporal, and organizational ranges, including those of time-sensitive operational and capital investment decision-making;
  • co-produced by scientists, practitioners, and decisionmakers, and meet the needs of and are readily accessible by stakeholders. [ 70 ]

Appendix H further defines a general framework for the CISA by identifying types of changes that should be considered and discussing the importance of considering operational life; provides an approach for incorporating uncertainty into the CISA; and discusses a range of data sources. The document does not prescribe or direct agencies to use specific resources or methods.

In 2023, the Science Subgroup convened by the Flood Resilience Interagency Working Group of the National Climate Task Force published the FFRMS CISA State of the Science Report (“FFRMS CISA State of the Science Report”). [ 71 ] This report provides a review and update of the best-available, actionable science that can support application of the CISA, reflecting science and technology advancements made since 2015. Like Appendix H from the Revised Guidelines, the FFRMS CISA State of the Science Report provides non-prescriptive, scientific, and engineering guidance for use by Federal agencies, their non-Federal partners, and other entities in determining future flood hazards under the FFRMS' CISA option. The FFRMS CISA State of the Science Report refines the initial framework from Appendix H to define two specific workflows for applying the CISA, [ 72 ] while acknowledging that technical competencies and capabilities needed to fully apply the CISA vary and may exceed those available in most Federal agencies and many non-Federal users. [ 73 ] The Report states that workflow implementation can be scaled to meet resource level and project requirements. [ 74 ]

The FFRMS CISA State of the Science Report specifically identifies the latest sea level rise projections from the National Climate Assessment as actionable. [ 75 ] The FFRMS State of the Science Report states each agency should factor projected regional/local sea level change into Federal investment decisions located as far inland as the extent of estimated tidal influence, now and in the future, using the most appropriate methods for the scale and consequence of the decision. [ 76 ] The FFRMS CISA State of the Science Report also suggests that along low-lying coastal shorelines on the Atlantic and Gulf Coasts not subject to runup or overtopping, the appropriate sea level rise estimates can be used similar to freeboard. [ 77 ]

This is the basis of the interagency implementation and supporting tools such as the FFRMS Job Aid. [ 78 ] The FFRMS Job Aid is a resource to help Federal agencies and their non-Federal partners (including potential Federal financial aid recipients) conduct a screening to determine if a proposed Federally funded action will be located in an FFRMS floodplain, based on the CISA, FVA, or 0.2PFA. While Appendix H of the Revised Guidelines and the FFRMS CISA State of the Science Report provide more general approaches that could be used to apply the CISA with sufficient time, money and expertise, [ 79 ] FEMA does not believe the data and science for these broader approaches are sufficiently available and actionable for FEMA to implement at scale. As explained below, FEMA prioritized the type and criticality of the action involved, the availability and actionability of the data, and equity concerns, and determined that applying the CISA through these broader, more complex approaches is not appropriate at this time given the agency's role in helping people recover from disasters in an expedited manner. FEMA instead decided to use consensus interagency approaches that are readily accessible to implement the CISA.

To help FEMA implement the FFRMS, the agency will leverage interagency tools. Specifically, FEMA will follow the methodology laid out in the FFRMS Job Aid to determine whether a site for a proposed action subject to the FFRMS is located within an FFRMS floodplain and if so, the FFRMS flood elevation for that site. FEMA will follow the CISA, FVA, or 0.2PFA Job Aid methodologies according to FEMA's FFRMS policy. Consistent with the FFRMS Job Aid, FEMA finds that the CISA is currently available and actionable for low-lying coastal shorelines on the Atlantic and Gulf Coasts. [ 80 ] If a site poses other complexities, such as steep bluffs or shorelines armored by large seawalls or similar flood-control structures, the CISA is not available and actionable  [ 81 ] and FEMA will instead use the FVA or 0.2PFA, per the agency's policy. For the CISA, FVA and 0.2PFA, FEMA will follow the processes outlined in 44 CFR 9.7 and in FEMA Policy 104-008-2: Guidance on the Use of Available Flood Start Printed Page 56941 Hazard Information. [ 82 ] For example, if a preliminary FIRM has more restrictive flood hazard data than an effective FIRM, FEMA will use the preliminary FIRM to identify the appropriate flood elevation. [ 83 ]

Consistent with the FFRMS Job Aid, to determine whether a proposed site is located within the FFRMS floodplain under the CISA and FVA approaches, FEMA will compare the ground elevation at the site (using the U.S. Geological Survey National Map) with the FFRMS flood elevation. [ 84 ] To identify the FFRMS flood elevation under the CISA and FVA, FEMA will identify the BFE at the site or the BFE at the nearest mapped floodplain if the site is outside of the 1% annual chance floodplain. Any relevant characteristics of the action or site will be noted at this stage ( e.g., service life, criticality, and flood characteristics). [ 85 ] For the CISA, FEMA will determine the FFRMS flood elevation by using the NOAA Sea Level Rise Viewer. [ 86 ] FEMA will use the service life of the action to select the scenario year. [ 87 ] For non-critical actions, FEMA will use the intermediate scenario, and for critical actions, FEMA will use the intermediate high scenario. [ 88 ] FEMA will then add the appropriate amount of sea level rise to the BFE to reach the FFRMS CISA flood elevation. If the site elevation is less than the CISA flood elevation, then the site is in the FFRMS CISA floodplain. For the FVA, 2 feet will be added to the BFE for non-critical actions or 3 feet for critical actions to determine the FFRMS FVA flood elevation. [ 89 ] If the site elevation is less than the FVA flood elevation, then the site is in the FFRMS FVA floodplain. [ 90 ] For the 0.2PFA, FEMA will compare the location of the site with the horizontal extent of the 0.2 percent annual chance floodplain using the FEMA Map Service Center or National Flood Hazard Layer. [ 91 ] If the site is within the floodplain, then it is within the FFRMS 0.2PFA floodplain. [ 92 ]

FEMA published these additional resources in the public docket with this rulemaking  [ 93 ] to further assist the public in understanding the FFRMS and the approaches utilized, including the availability and actionability of the CISA data and how FEMA would implement the FFRMS through application of the FFRMS Job Aid methodology. FEMA will continue to collaborate across the Federal government to develop tools to facilitate the implementation of CISA and the FFRMS. The IWG recently released for comment a beta version of the Federal Flood Standard Support Tool (FFSST), a novel, interactive, map-based tool that incorporates new data to help users identify if a Federally funded project is in the FFRMS floodplain. [ 94 ]

This final rule implements Executive Order 11988 , as amended, the FFRMS, and the Revised Guidelines, while also updating FEMA's 8-step process. Consistent with the changes proposed in the NPRM, FEMA is incorporating a severability clause into part 9; updating definitions to implement the FFRMS and reflect current policy and practice; providing the applicable effective date for the changes made in the final rule and further clarifying the rule's scope; updating how FEMA determines whether an action is in a floodplain, consistent with the FFRMS approaches when the action is subject to the FFRMS; and adding an emphasis on nature-based approaches in the 8-step process consistent with Executive Order 11988 , as amended.

In this final rule, FEMA incorporates edits to reflect commenter feedback. Specifically, in § 9.7(c)(3), FEMA is adding agencies from Federal and Indian Tribal governments as potential sources of information in making the floodplain determination. These changes better ensure that FEMA will effectively consider relevant and appropriate data in making the floodplain determination under part 9. FEMA is also making clarifying edits in § 9.5(a)(3) to clarify that copies of the legacy regulations will be available on the agency's website and to § 9.7(c)(3) to clarify that FEMA may consider information from the entities listed. FEMA is also making minor technical edits in § 9.7(c)(1)(i)(C) and § 9.11(d)(3)(ii).

FEMA's FFRMS policy is also being finalized with the publication of this rule and will be effective with the rule's implementation. The FFRMS policy provides guidance on how FEMA will implement the FFRMS across FEMA's programs and further incorporate nature-based solutions into the 8-step process. FEMA is making minor clarifying edits to the FFRMS policy consistent with commenters' suggestions by further clarifying the use of the 0.2PFA in coastal areas and making other technical edits to the document for readability. FEMA is also clarifying in the FFRMS policy that the agency will leverage the FFRMS Job Aid when implementing the FFRMS.

The NPRM public comment period closed on December 1, 2023, and FEMA received 47 germane comments. [ 95 ] Commenters included non-profit organizations; individuals; local governments; State governments and State government organizations; and for-profit entities. The majority of comments were supportive of FEMA's rule and policy approach to implementing the FFRMS and other updates to part 9. Commenters focused on the regulatory impact analysis (RIA) accompanying the rule; the CISA and the data FEMA would use to determine each of the FFRMS approaches; FEMA's implementation of the FFRMS; and the 8-step process detailed in part 9. FEMA describes the specific revisions in the final rule and addresses commenters' specific concerns below.

The majority of commenters were generally supportive of the rule and accompanying FFRMS policy. [ 96 ] Commenters noted appreciation of FEMA's rulemaking efforts to enhance the resilience and sustainability of communities and ecosystems that are vulnerable to flooding. These commenters stated the FFRMS was a critical policy tool to reduce risks and promote sound floodplain management and wetlands protection practices, as well as fiscal responsibility.

Commenters were supportive of the agency's use of the FFRMS approaches in the rulemaking and accompanying FFRMS policy document. A commenter noted the incorporation of the CISA, FVA, and 0.2PFA reflected FEMA's commitment to using diverse and Start Printed Page 56942 adaptive strategies based on the best-available scientific knowledge. Another commenter supported the floodplain definition revisions, stating that an expanded floodplain definition would ensure that more projects were built with resilience in mind when compared to current projects. A commenter stated FEMA's preferred CISA approach would result in Federally funded projects that were more resilient to current and future flooding and ensured a wiser use of taxpayer dollars. The commenter stated stronger standards were feasible to implement, as many jurisdictions already have existing stronger building and land-use standards. Commenters also indicated support for FEMA's emphasis on using natural systems, ecosystem processes, and nature-based approaches.

Comment: Some commenters supporting the rule requested FEMA quickly finalize and implement the final rule. While requesting FEMA work quickly to finalize and implement the rule, one commenter noted that the partial implementation policies in place did not fully implement FFRMS as they did not extend the horizontal floodplain. This commenter requested FEMA also integrate FFRMS into the minimum floodplain management standards for the NFIP. The commenter also stated FEMA should ensure FFRMS was sufficiently staffed and should develop a comprehensive plan to track enforcement and any concerns such as environmental justice to ensure effective implementation of the rule.

FEMA Response: FEMA agrees with the commenters on the importance of finalizing and implementing the rule and FFRMS policy. FEMA is issuing this final rule with an effective date of September 9, 2024. As explained in § 9.5(a)(3), the FFRMS applies only to new actions for which assistance is made available pursuant to declarations under the Stafford Act that are commenced on or after the effective date of the final rule, and new actions for which assistance is made available pursuant to notices of funding opportunity that publish on or after the effective date of the final rule. [ 97 ]

FEMA declines to accommodate the commenter's request to integrate the FFRMS into the minimum floodplain management standards for the NFIP because it is beyond the scope of this rulemaking. The NFIP is a program through which property owners in participating communities can purchase Federal flood insurance as a protection against flood losses. [ 98 ] As a condition of eligibility, a community must adopt and enforce floodplain management regulations that meet or exceed the NFIP minimum floodplain management criteria developed by the Administrator. [ 99 ] Further information regarding FEMA's minimum floodplain management standards for the NFIP can be found at 44 CFR part 59 et seq. Because this rule only applies to “actions subject to the FFRMS,”  [ 100 ] this rule does not change any FEMA standards applicable to community or individual participation in any aspect of the NFIP. In general, changes to 44 CFR part 59 et seq would require a rulemaking to revise the appropriate sections of the CFR.

As an illustrative example, if an NFIP-participating community owns a structure in a floodplain that has been substantially damaged and the community decides to repair it using community funds, funding from a flood insurance payment, or other funding that is not FEMA grant funding, the community's floodplain management regulations, not the FFRMS, would apply to the repair project. However, if that same structure was substantially damaged by a disaster event, and the community applied for assistance under a FEMA grant program like the Public Assistance program, the FFRMS would apply to that repair project.

FEMA agrees with the commenter that it is important to adequately staff for FFRMS implementation. FEMA is accordingly ensuring that sufficient staff at headquarters and regional offices are appropriately trained to provide technical assistance. FEMA currently leverages the 8-step process detailed in 44 CFR part 9 as the mechanism to implement Executive Order 11988 . Step 8 of the process found at 44 CFR 9.6(b) requires FEMA to review the implementation and post-implementation phases of the proposed action to ensure that the requirements stated in § 9.11 are fully implemented. Under this provision, oversight responsibility is integrated into existing processes associated with FEMA's grant management requirements. FEMA is not making changes to these requirements in the final rule and will continue to use the current process to ensure compliance with the FFRMS and Executive Order 11988 , as amended. 2 CFR 200.339 also allows FEMA to take action to remedy a recipient's noncompliance with federal requirements, including those required by 44 CFR part 9 , such as imposing new conditions on the award or deobligating funding for the award if a recipient does not adhere to the requirements set forth during the part 9 review process.

Four commenters expressed opposition to the rule overall. Those commenters raised concerns about the complexity of the FFRMS approaches, uncertainty about the CISA standard, and the application of FFRMS to specific types of FEMA actions. The commenters stated concerns with the potential increased costs associated with implementing FFRMS and with FEMA's economic impact analysis accompanying the rule. The commenters also stated concerns with implementing the FFRMS given conflicting Federal, State, local, and other requirements. Commenters stated the FFRMS was a “one-size-fits-all” approach that lacked the flexibility to address regional and local needs. Commenters stated the use of the CISA introduced uncertainty into the regulations contrary to the fundamental principles outlined in Executive Orders 12866 and 13563. Commenters also stated FEMA's analysis of the costs and benefits associated with the rulemaking did not adequately quantify the costs and benefits of several components of the risk reduction strategies in the rule. Commenters raised questions regarding FEMA's statutory authority to implement the rule. One commenter Start Printed Page 56943 stated Congress should define the floodplain. This commenter raised similar concerns regarding the use of the CISA and lack of data sources that map the FFRMS floodplain. FEMA responds to some of the general comments in opposition to the rule in the comment summaries and responses immediately below and responds in more detail to the remainder of the comments in the following sections of the preamble.

Comment: One commenter requested FEMA extend the comment deadline associated with the rule for an additional 60 days. The commenter requested an extension of the comment period given the complexity of the rule and policy and to implement extensive public outreach.

FEMA Response: FEMA received 48 comments to the public docket associated with this rulemaking and no other requests to extend the comment period were received. The 60-day comment period provided is consistent with 44 CFR 1.3(b) and Executive Orders 12866 and 13563. This timeframe provided a reasonable opportunity for public comment and is particularly appropriate given FEMA's prior engagement on this topic. FEMA completed extensive outreach in 2015 as part of the development and publication of the Revised Guidelines, and also sought public input in connection with the agency's prior NPRM in 2016. [ 101 ] Additional outreach will be completed as part of the rule's implementation as FEMA will distribute additional information to SLTT partners and the public explaining again what the FFRMS is and how the agency will further implement the Executive Orders. FEMA's FFRMS policy will also be reassessed on a four-year cycle to ensure the approach continues to meet the goals of Executive Order 11988 , as amended. During the four-year review process, FEMA's FFRMS policy will be reviewed, revised, extended, and/or rescinded as appropriate.

FEMA does not believe additional engagement is needed to finalize this rule. All but a few of commenters expressed support for the rule and FEMA's FFRMS policy and many requested swift implementation, consistent with the need to protect federal dollars and communities from increasing flood risk.

Comment: One commenter stated the rulemaking was premature in the absence of a clearly defined process for implementing the CISA and urged FEMA to withdraw the rule from consideration. The commenter expressed concern that FEMA will take a haphazard approach—completing each analysis of the extent and elevation of the CISA floodplain on a case-by-case basis and doing so using data that may not be complete or is not be widely known or available to the public. The commenter stated that in the end, neither the process nor the outcome will be predictable or replicable.

FEMA Response: FEMA disagrees. This rulemaking is not premature, and FEMA provided information in and accompanying the NPRM explaining how the CISA and the FFRMS will be implemented. Each analysis will be completed on a case-by-case basis consistent with the current 8-step process, which has been in place for over four decades, to determine the floodplain, but the data used to make the analysis is publicly available and replicable using the FFRMS CISA State of the Science Report, the FFRMS Job Aid, and FEMA's FFRMS policy. As explained above, the FFRMS CISA State of the Science Report identifies the latest sea level rise projections from the National Climate Assessment as available and actionable data and the appropriate sea level rise estimates can be used to approximate future 1 percent annual chance flood levels. These estimates can simply be added to the current 1 percent annual chance flood elevation to approximate the future 1 percent annual chance flood level, in low-lying coastal shorelines on the Atlantic and Gulf Coasts not subject to runup or overtopping. The FFRMS Job Aid  [ 102 ] provides the methodology FEMA will use to determine the floodplain and elevation under the CISA where data is actionable and available (namely in low-lying coastal shorelines on the Atlantic and Gulf Coasts consistent with the FFRMS CISA State of the Science Report). FEMA's FFRMS policy further explains that the CISA is used where actionable and available and provides alternatives where such data is not actionable and/or available. The CISA analysis can be completed using these publicly available materials for areas with actionable and available data. FEMA anticipates actionable and available data will increase over time and the interagency tools provided will be updated to reflect the new data.

Comments: Two commenters requested FEMA complete additional analyses before finalizing the rule. Both commenters referenced other flood-related regulatory and policy actions, including the Technical Mapping Advisory Council (TMAC)'s proposal to increase the regulatory floodplain and increase the NFIP floodplain management standards for land management and use; Risk Rating 2.0 for flood insurance premiums; and USACE's proposed levee safety updates as well as risk informed decision making.

One commenter requested the rule be deferred until FEMA completed a cumulative impacts assessment and considered associated actions to mitigate the impacts of the actions above on communities participating in the NFIP, mapping and accreditation, low to moderate income families, and disadvantaged communities. The commenter further requested FEMA withdraw the rule until a regulatory analysis applying sound cost-benefit analysis principles and a comprehensive socio-economic impact analyses to address the full and intended scope of FFRMS were completed. The commenter stated the regulatory impact analysis should address cumulative impacts and the need for mitigation of impacts to community property values, tax bases, the distribution of real income, as well as the impacts on affordable housing and low to moderate income families and disadvantaged communities.

The other commenter stated that different flood regulations and policies may overlap with or duplicate each other and potentially lead to redundancy, confusion, and additional costs. The commenter requested FEMA conduct a more thorough quantitative cost-benefit analysis, considering the Start Printed Page 56944 cumulative effects of recent floodplain governing rules to make well informed decisions regarding appropriate risk reduction strategies and ensure a thorough understanding of the overall impact of the rule's implementation. The commenter requested FEMA conduct a comprehensive assessment of cumulative impacts to ensure a more informed and coordinated approach and requested that FEMA provide additional documentation on how FFRMS would impact other Federal agencies' programs, such as USACE's civil works projects and whether FEMA's FFRMS policy would supersede other Federal agencies' rules and regulations. The commenter stated FEMA relied on a subjective assessment of the rule's costs and benefits. The commenter asked FEMA to closely coordinate with other agencies that typically co-regulate projects, including USACE with water resources projects.

The commenter also stated that the FFRMS could lead to further deterioration of key infrastructure, where meeting the new, higher standards is not technically or financially feasible, resulting in communities leaving the infrastructure to deteriorate in place and not serve the public need. The commenter stated that these types of costs should be considered in the regulatory analyses.

FEMA Response: FEMA disagrees this rule should be deferred. While FEMA understands the commenters' interest in the policy activities mentioned, the agency does not believe those actions are relevant to this rulemaking or require additional analysis to finalize this rule. The commenters reference a recommendation made by the TMAC in a recent annual report  [ 103 ] that FEMA expand the NFIP regulatory floodplain as defined in 44 CFR 59.1 to which the NFIP's minimum floodplain management criteria set forth in 44 CFR 60.3 applies, and the commenters suggest that FEMA must delay this rulemaking until it has analyzed the effects of that recommendation. That is not necessary because FEMA has not implemented the TMAC recommendation and therefore it has no current effect on communities. The TMAC is a Federal advisory committee established to review and make recommendations to FEMA on matters related to the national flood mapping program authorized under the Biggert-Waters Flood Insurance Reform Act of 2012. [ 104 ] The national flood mapping program requires FEMA to review, update, and maintain NFIP rate maps. [ 105 ] It is outside the scope of this rule.

The commenters also refer to the NFIP's pricing approach  [ 106 ] for NFIP policyholders as a new “flood regulation” that requires analysis prior to finalizing this rulemaking. However, this rulemaking does not impact the NFIP's site-specific actions, such as how FEMA rates the premium for a flood insurance policy. Further, the population of NFIP policyholders is much larger than the number of FEMA grant recipients who will be impacted by this rule.

One commenter states FEMA needs to account for how the rule will impact mapping and accreditation under the NFIP; however, the rule does not appreciably impact those areas of the NFIP. This rule and the accompanying policy implement the FFRMS for actions where FEMA funds are used for new construction, substantial improvement or repairs to address substantial damage, and requires that nature-based solutions and natural features be considered and implemented where possible to all actions that are subject to Step 3 of the 8-step decision-making process. Nature-based solutions and natural features must be considered as an alternative action in Step 3. Where it is not possible to use natural features and nature-based solutions as an alternative on their own, they would be considered in conjunction with the proposed action as a minimization measure in Step 5. Neither FEMA's flood mapping program nor its accreditation of levees under the NFIP are actions subject to the FFRMS and, to the extent that any programmatic or policy change to either of those areas are required to undergo the 8-step process under 44 CFR part 9 , it is unlikely that a consideration of nature-based solutions will result in changes with demonstrable impacts. FEMA cannot address the other actions referenced, such as the USACE's civil works projects and levee safety updates, as these involve other Federal agencies, and questions regarding those actions are best addressed by those agencies directly.

FEMA believes that the commenter's concerns about this rule's economic impacts is inconsistent with this rule's relatively limited applicability. FEMA defines an “action subject to the FFRMS” as “any action where FEMA funds are used for new construction, substantial improvement, or to address substantial damage to a structure or facility,” consistent with Executive Order 11988 , as amended, and the Revised Guidelines. The FFRMS applies to grants for projects funding the new construction, substantial improvement, or repair of substantial damage under FEMA programs such as the IA, PA, and HMA programs, and grants processed by FEMA's Grants Programs Directorate (GPD) (involving grants for preparedness activities). This rule does not regulate privately funded activity in the floodplain. As such, the implementation of the FFRMS will have negligible impacts on community property values, tax bases, and the distribution of real income. Additionally, FEMA expects the impacts on affordable housing for low to moderate income households and disadvantaged communities to be minimal since most actions subject to FFRMS requirements are non-residential. FEMA only funds residential construction in the IA and HMA programs; FEMA funds 153 residential IA projects and 268 HMA residential projects per year on average. The majority of the costs associated with FFRMS requirements will be covered by FEMA funding.

Comment: A commenter stated the FFRMS policy and rule were one-sided, as they limited how people could use and live in flood-prone areas without a clear goal to support economic growth or sensible development within reasonable limits. The commenter stated Congress likely would not endorse a flood risk strategy that did not consider using flood-prone areas optimally for the country's benefit. The commenter stated the rule's benefits were unclear given the emphasis on constraints and a lack of consideration for economic development as part of resilience. The commenter recommended that FEMA adjust the policy to include efficient and smart use of flood-prone areas while acknowledging the limitations on development.

FEMA Response: The revisions to part 9 are consistent with FEMA's long-standing requirement as part of implementation of Executive Order 11988 , as amended, to only perform or fund actions within or affecting floodplains and wetlands if those actions are the only practicable alternative. FEMA's regulations provide for consideration of the need for economic development and community resilience, while also bolstering the resilience of communities and Federal Start Printed Page 56945 assets against the impacts of flooding. For instance, through the 8-step process, FEMA considers alternative locations, alternative actions, natural features, nature-based approaches, and the no action alternative under the practicability analysis. The definition of “practicable” makes clear that practicability depends on the situation and includes consideration of all pertinent factors, such as natural environment, social concerns, economic aspects, legal constraints, and agency authorities. In addition, if there is no practicable alternative, FEMA will perform or fund the action in the floodplain or wetland and will minimize any adverse impacts when doing so. Under § 9.9 as well, in determining the practicability of the alternatives, FEMA considers economic aspects.

Two commenters wrote comments concurring with FEMA's statutory and other authority for the rulemaking.

Comments: Both commenters stated the rule was a valid use of FEMA's regulatory authority, citing to the NFIA, as amended by the Flood Disaster Protection Act ( 42 U.S.C. 4001 et seq. ), the Stafford Act ( 42 U.S.C. 5121 et seq. ), and the NEPA ( 42 U.S.C. 4321 et seq. ). One commenter noted the Congressional intent in the Stafford Act for the Federal Government to develop land use and construction regulations to help State and local governments mitigate risk and reduce losses and FEMA's broad discretion to define “safe land use and construction practices” as a condition of Stafford Act funding for both public and private structures. [ 107 ] The commenter stated section 101 of NEPA required FEMA to use all practicable means to ensure Federal plans, programs, and resources “(1) fulfill the responsibilities of each generation as trustee of the environment for succeeding generations; (2) assure for all Americans safe, healthful, productive, and esthetically and culturally pleasing surroundings; [and] (3) attain the widest range of beneficial uses of the environment without degradation, risk to health or safety, or other undesirable and unintended consequences” among other priorities. [ 108 ] The commenter stated the FFRMS reflects a tradition of executive action to enforce reasonable floodplain management and wetland protection. Another commenter noted the NFIA and Flood Disaster Protection Act require FEMA to establish land use criteria for floodplain management  [ 109 ] and that NEPA requires Federal agencies to evaluate the environmental and related social and economic effects of their proposed actions, which includes the evaluation of the impacts of proposed actions in the floodplains. [ 110 ] Further, the commenter stated the Stafford Act directed FEMA to encourage “hazard mitigation measures to reduce losses from disasters, including development of land use and construction regulations.”  [ 111 ] The commenter stated FEMA's regulations were consistent with these legislative directives.

FEMA Response: FEMA agrees with the commenter that the agency has statutory authority to implement FFRMS. Please refer to section II.B for a description of FEMA's statutory authority to implement grant programs and to require its grant recipients to carry out repairs or construction in accordance with specific standards.

Three commenters raised concerns regarding FEMA's legal authority to amend part 9 and implement FFRMS.

Comment: One commenter stated Congress should establish the definition of floodplains. The commenter acknowledged defining the geographic scope of a floodplain was not an easy task, but stated the implications on landowners and others made it a job best left for Congress. The commenter stated that Congress drafted and debated language over the last twenty plus years on the issue and stated that Congress has had the opportunity to revisit and refine Federal floodplain policies as part of NFIP regular reauthorization process. The commenter stated it was bad public policy to delegate defining the limits of Federal authority to the agencies, citing to challenges other agencies have had defining “waters of the United States” and reiterating the need for Congressional action.

FEMA Response: This comment appears to confuse the definition of floodplain under the NFIP with the definition of floodplain that is being altered with this rulemaking, and, as such, makes incorrect statements and assumptions about the role Congress has played or should play. This rulemaking is not altering the definition of floodplain under the NFIP. The NFIP is a program through which property owners in participating communities can purchase Federal flood insurance as a protection against flood losses. [ 112 ] As a condition of eligibility, a community must adopt and enforce floodplain management regulations that meet or exceed the NFIP minimum floodplain management criteria developed by the Administrator. [ 113 ] The floodplain and other definitions governing the NFIP can be found at 44 CFR 59.1 . This rulemaking is updating the definition of floodplain in 44 CFR part 9 as applied to actions subject to the FFRMS, defined as actions where FEMA funds are used for new construction, substantial improvement, or repairs to address substantial damage to structures and facilities. [ 114 ] As set forth, in section II.B, Congress has authorized FEMA to implement grant programs and to require its grant recipients to carry out repairs or construction in accordance with specific standards.

Comment: Two commenters requested FEMA cite the specific and clear Congressional authority for each objective and mandate of FFRMS. Both commenters noted the President may have the authority to impose mandates on Federal projects as cost-saving measures, but regulation of private and non-Federal activities within the floodplain was limited to those jurisdictions where local communities have imposed upon themselves the burden of floodplain regulation as a condition of participation in the NFIP. The commenters stated that applying the FFRMS to private and non-Federal government entities under other regulatory programs was outside FEMA's statutory authority.

FEMA Response: Please refer to section II.B for a description of FEMA's statutory authority to implement grant programs and to require its grant recipients to carry out repairs or construction in accordance with specific standards. Contrary to the commenter's assertions, this rule applies the FFRMS to FEMA funded projects for new construction, substantial improvement, and repairs to address substantial damage. It does not regulate privately funded activity in the floodplain, it does not alter the definition of floodplain under the NFIP, and it does not apply Start Printed Page 56946 the FFRMS to any programs other than FEMA's grant programs.

Comment: One of the commenters stated that FEMA was acting without clear statutory authority as implementing the FFRMS fell within the scope of a major question because of the standard's aggregate economic impacts over time. Two commenters recommended FEMA remove any application of FFRMS to private and non-Federal activities covered by permitting, loan, or grant-in-aid programs administered by Federal agencies except where clear statutory authority has been granted and also sever any and all objectives related to regulating floodplain activities to protect wetlands. The commenters stated Federal authority over wetlands was limited by the Clean Water Act and recent Supreme Court rulings, including Sackett v. EPA. [ 115 ]

FEMA Response: FEMA disagrees the aggregate economic impacts over time associated with this rulemaking are a matter of such “deep economic and political significance” as to constitute a “major question,” as described by the Supreme Court in West Virginia v. EPA . [ 116 ] While FEMA expects that this rule would carry important benefits and would ultimately save significant taxpayer dollars, this rule is not akin to the rule in West Virginia, where the agency's “own modeling concluded that the rule would entail billions of dollars in compliance costs (to be paid in the form of higher energy prices), require the retirement of dozens of coal-fired plants, and eliminate tens of thousands of jobs across various sectors.”  [ 117 ] This rulemaking requires FEMA grant recipients to build a subset of the construction projects that FEMA funds to a higher standard in an expanded floodplain. There is an increase in the costs associated with this more resilient building standard, but that increase is paid primarily by FEMA and is ultimately a fraction of what grant recipients might already spend using Federal funds to accomplish such construction.

Even if the major questions doctrine did apply, there is clear statutory authority and longstanding precedent for the rule. FEMA has authority to require application of the FFRMS as a condition of funding in its grant programs based on the grant programs' authorizing statutes. Congress granted FEMA the authority to provide Federal assistance through multiple grant programs under the Robert T. Stafford Disaster Relief and Emergency Assistance Act (Stafford Act), [ 118 ] the NFIA, [ 119 ] the Homeland Security Act of 2002, [ 120 ] the Federal Fire Prevention and Control Act of 1974, [ 121 ] the Earthquake Hazards Reduction Act of 1977, [ 122 ] and various other appropriations acts. Under each of these authorities, FEMA may set grant eligibility criteria consistent with the respective purposes of such programs and FEMA's mission, including to protect Federal investments from the risks of further damage. [ 123 ] Under the Stafford Act and the NFIA, which authorize the programs that fund the majority of the actions subject to the FFRMS, FEMA has general rulemaking authority. [ 124 ] Further, FEMA has explicit authority under the Stafford Act to set the minimum standards for safe land use and construction standards required in the repair or construction of private and public facilities. [ 125 ] Further, in the time since Executive Order 11988 was first issued in 1977 and FEMA issued its implementing regulations at 44 CFR part 9 in 1979 and 1980, Congress has amended FEMA's governing authorities multiple times without overriding part 9. [ 126 ] Consistent with the approach that FEMA has taken for decades, this rule revises part 9 pursuant to FEMA's statutory authorities and in line with Executive Order 11988 , as amended.

Finally, the comments related to wetlands and the Supreme Court's decision in Sackett v. EPA are not germane to this rulemaking. FEMA's proposed changes to the definition of wetlands within the regulation was limited to reorganizing the placement of examples within the definition and removing an outdated resource. FEMA's proposed changes do not change how the agency makes wetland determinations.

FEMA received over 40 specific comments on the proposed rule's definitions in § 9.4. Commenters were generally supportive of the proposed revisions but sought clarification or offered suggestions to enhance the definitions provided in the proposed rule. FEMA has carefully reviewed the commenters' suggestions and is not revising the NPRM definitions in this final rule but is providing multiple clarifications below.

Comments: Commenters requested additional clarity regarding definitions and additional engagement on definitions generally. A commenter requested FEMA provide clear definitions and describe abbreviations before they are used in the rulemaking, policy, and any additional guidance or resources provided. The commenter provided an example of the term “AC floodplain” used in a graphic without definition. Another commenter requested FEMA engage stakeholders from a range of relevant backgrounds in the review process to gather varied perspectives and ensure that definitions are clear and universally understood.

FEMA Response: FEMA will distribute additional resources to the public and SLTT partners after the rule's publication to ensure that stakeholders understand what the FFRMS is and how the agency will implement the revised part 9. These resources will include additional examples to help applicants better understand the FFRMS as they apply for FEMA programs. FEMA appreciates the Start Printed Page 56947 commenter's concern and has updated Figure 1 in the FFRMS policy to clarify “AC floodplain” means “annual chance floodplain.”

FEMA engaged stakeholders as part of the development and publication of the Revised Guidelines, which contain most of the definitions FEMA uses in this rulemaking. Stakeholders also provided specific feedback on the definitions in § 9.4 as part of this rulemaking effort and FEMA addresses their concerns in this final rule.

Comment: A commenter expressed support for the definition of the 0.2 percent annual chance flood elevation (0.2PFA), agreeing with the use of the terminology similar to annual exceedance probability for defining flow, floodplains, and water surface elevation in the floodplain.

FEMA Response: FEMA appreciates the commenter's consideration of the definition.

Comment: One commenter requested clarification on how the term “agency” was defined under part 9.

FEMA Response: FEMA defines “agency” in § 9.4 as “the Federal Emergency Management Agency (FEMA).” FEMA is not changing the definition of “agency” in this final rule.

Comments: Five commenters asked FEMA to further clarify the definition of “critical action,” stating the definition was too vague and left too much room for interpretation. Commenters asked for a list of examples of critical actions to support the definition in § 9.4 and/or sufficient information to distinguish between critical and non-critical actions. One commenter asked FEMA to provide examples related to the transportation sector and recommended roadways, bridges, and culverts not be considered critical actions. One commenter requested a process for local representatives to provide input on what constitutes critical action/critical facilities.

FEMA Response: FEMA's definition of “critical action” is consistent with Executive Order 11988 , as amended, through the 1978 Guidelines and further clarified in the Revised Guidelines. FEMA notes the term “critical action” is not new but was developed and implemented initially with Executive Order 11988 in 1977. The Revised Guidelines provide further details on what constitutes a critical action. FEMA will leverage the information in the Revised Guidelines when providing additional guidance to stakeholders. The determination of whether an action to create or extend the useful life of a structure or a facility is a critical action is generally made on a case-by-case basis consistent with the information found in the Revised Guidelines. Local representatives have input on whether a particular action is a “critical action” as part of the agency's 8-step process.

Comment: Two commenters sought clarification on the term “Federal action.” Commenters sought clarification on what is a “Federal action” subject to the FFRMS and stated confusion and inconsistency could result among different Federal agencies and programs implementing the FFRMS. One commenter asked for additional clarification on whether specific FEMA programs were subject to the FFRMS. That commenter also sought clarification on how the FFRMS would interact with other Federal laws and regulations that govern floodplain management, such as the NFIP, NEPA, and the Endangered Species Act (ESA).

FEMA Response: In this rulemaking, FEMA revises § 9.4 to define “action subject to the FFRMS” as “any action where FEMA funds are used for new construction, substantial improvement, or to address substantial damage to a structure or facility.” As explained above, the requirements of this rule apply to grants for projects funding the new construction, substantial improvement, or repair of substantial damage under FEMA programs such as IA, PA, and HMA programs, and grants processed by FEMA's GPD.

Part 9 only applies to FEMA actions. Other Federal agencies will implement FFRMS through their own regulations and/or policies. To ensure consistency, all Federal agencies will utilize the Revised Guidelines in their own FFRMS implementation. Per 44 CFR 9.11(d)(6) , no action may be taken if it is inconsistent with the NFIP or any more restrictive Federal, State, or local floodplain management standards.

FEMA funding actions are also evaluated pursuant to the NEPA, ESA, and other environmental and historic preservation requirements. The Federal action will not be approved unless it meets all applicable environmental and historic preservation requirements.

Comments: A commenter requested FEMA coordinate with the agency's TMAC to ensure the new rule's definition of “floodplain” in § 9.4 accounts for potential changes in the definition and mapping of floodplains recommended by the TMAC. Another commenter asked how the floodplain would be defined in the FFRMS and if the floodway would be considered a regulatory floodplain. The commenter stated it was unclear how the expanded horizontal FFRMS floodplain would impact future State Department of Transportations' maintenance work in coordination with the Federal Highway Administration (FHWA).

FEMA Response: FEMA appreciates the commenter's concerns. The purpose of TMAC is to provide analysis under the NFIA. The requirements of Executive Order 11988 , as amended, are distinct from TMAC recommendations and thus FEMA disagrees with the commenter that coordination with TMAC is required to finalize this rule. As explained above, the TMAC is a Federal advisory committee established to review and make recommendations to FEMA on matters related to the national flood mapping program authorized under the Biggert-Waters Flood Insurance Reform Act of 2012. [ 127 ] The national flood mapping program requires FEMA to review, update, and maintain NFIP rate maps. [ 128 ] While the framework FEMA uses in part 9 is distinct from mapping recommendations for flood prone areas TMAC made in their recent annual report, FEMA believes that the flexibility outlined in 44 CFR 9.7 and the practice of using the best available information will allow the application of part 9 to adjust to any change made in the mapping process should FEMA adopt any of the TMAC recommendations.

As explained in the NPRM in 44 CFR 9.4 , FEMA defines the “Federal Flood Risk Management Standard Floodplain” as the floodplain established using one of the approaches described in 44 CFR 9.7(c) . The floodway and the regulatory floodway are also defined in 44 CFR 9.4 and are within the floodplain for purposes of part 9. The requirements of this rule will apply to actions funding the new construction, substantial improvement, or repair of substantial damage under FEMA programs such as IA, PA, and HMA programs, and grants processed by FEMA's GPD. Roads that are under the jurisdiction of another Federal agency, such as those under the FHWA, are subject to that agency's requirements as they generally are ineligible for funding under FEMA's grant assistance programs. Start Printed Page 56948

While some commenters expressed support for the definition of “nature-based approaches” in the rule, other commenters requested specific revisions.

Comment: One commenter stated the definition of “nature-based approaches” failed to take into account a design intent to protect or restore natural processes; and did not include reference to hybrid gray/green solutions that might be required for restoring habitat, attenuating floods, and keeping communities safe. The commenter suggested a definition closer to the “nature-based solutions” definition published on FEMA's website. The commenter requested FEMA work with other Federal agencies to agree on common definitions for key terminology. Further, the commenter recommended that FEMA remove language stating that nature-based approaches “generally, but not always, must be maintained in order to reliably provide the intended level of service,” because maintenance requirements are highly variable and are also generally necessary to maintain grey infrastructure. The commenter stated that “nature-based solutions specifically aim to work with nature (as opposed to grey infrastructure solutions that often are designed to control or work against nature processes) and therefore can be less susceptible to catastrophic failure or repeated maintenance and can require lower maintenance costs overall.” This commenter also requested FEMA include “green infrastructure” when describing the definition. The commenter recommended FEMA include a broader range of ecosystem-based activities in the description of natural and nature-based actions, especially those more appropriate for larger or more rural floodplains. The commenter provided specific scenarios of nature-based approaches.

FEMA Response: FEMA appreciates the commenter's concerns and believes the definition as written is appropriate. The definition is consistent with the glossary definition in the Revised Guidelines. The Revised Guidelines provide broad guidance in implementing Executive Order 11988 , as amended and “offer a common point of reference so that each agency can use or amend their procedures as appropriate.”  [ 129 ] Consistency with the Revised Guidelines definition helps ensure more consistent implementation of nature-based approaches across the Federal government and meets the commenter's request for FEMA to utilize common terminology with other Federal agencies. Changes such as those proposed by the commenter would increase the potential for inconsistency and stakeholder confusion working on projects involving multiple Federal agencies.

FEMA notes that the Revised Guidelines state that nature-based approaches can restore natural processes, and the agency does not believe the definition excludes either protecting or restoring natural processes. For purposes of part 9, nature-based solutions are specific to floodplains and wetlands, and the commenter's references to nature-based solutions on the agency's website reflects the full range of natural hazards FEMA programs may mitigate. Regarding maintenance, FEMA believes the language is appropriate in the definition as written. The use of “maintenance” is to differentiate between nature-based approaches and natural features. Nature-based approaches are designed to mimic natural processes, but they are not wholly naturally occurring. As such, they may require some form of maintenance to ensure they are performing as intended. In comparison, natural features are those characteristics of the environment that are naturally occurring and exist in a dynamic equilibrium, so should require little to no maintenance in serving their purpose. FEMA understands the commenter's concern that “green infrastructure” is more expansive than stated in the NPRM and plans to provide additional resources that will incorporate examples to address some of the specific scenarios raised by the commenter. FEMA notes the definition of “nature-based approaches” states that nature-based approaches are sometimes referred to as “green infrastructure.”

Comments: Two other commenters requested edits to the definition of “nature-based approaches” to incorporate restoration and conservation of natural systems. The commenters stated that such edits would ensure all relevant nature-based approaches are adequately considered. Another commenter recommended expanding the definition of “nature-based approaches” by removing the reference to “green infrastructure” at the beginning of the definition and incorporating the statement “Nature-based approaches include green infrastructure practices, as well as conservation approaches such as the restoration of wetland and floodplain hydrology and other river processes” into the definition while also revising the language regarding maintenance to state such approaches can be self-sustaining or need ongoing maintenance.

FEMA Response: While FEMA appreciates the commenters' concerns to include restoration or conservation of naturally occurring systems and processes and concerns related to green infrastructure, FEMA's definitions are consistent with the glossary definition in the Revised Guidelines and the changes proposed by the commenters could result in inconsistencies including inconsistent implementation across other Federal agencies. As explained above, the Revised Guidelines help ensure key terminology is consistent across Federal agencies implementing FFRMS. The Revised Guidelines state that nature-based approaches can restore natural processes, and FEMA does not believe the definition excludes restoring or conserving natural systems. FEMA will provide additional resources with additional examples of nature-based approaches including more information on green infrastructure to address the commenters' concerns. FEMA will also coordinate with other Federal agencies regarding the use of nature-based solutions as part of the FFRMS implementation.

FEMA appreciates the commenter's suggestion to specifically reference “the restoration of wetland and floodplain hydrology and other river processes” in the definition of “nature-based approaches,” but disagrees that such an edit is needed to the definition to address the commenter's concerns.

FEMA's longstanding requirements in 44 CFR 9.11 outline the agency's requirements to restore and preserve the natural and beneficial values served by floodplains and wetlands. This requirement to restore and preserve the values served by floodplains and wetlands, see, e.g., 44 CFR 9.11(b)(3) & (e), applies to all actions located within a floodplain or wetland or that affect a floodplain or wetland, including actions that use nature-based approaches.

As explained above, the use of “maintenance” is to differentiate between nature-based approaches and natural features and FEMA does not believe the changes suggested by the commenter are appropriate. Nature-based approaches are designed to mimic natural processes, but they are not wholly naturally occurring. As such, they may require some form of maintenance to ensure they are performing as intended. In comparison, natural features are those characteristics of the environment that are naturally occurring and exist in a dynamic Start Printed Page 56949 equilibrium, so should require little to no maintenance in serving their purpose. FEMA understands the commenter's concern that “green infrastructure” is more expansive than stated in the NPRM and plans to provide additional resources that will incorporate examples to address some of the specific scenarios raised by the commenter. FEMA notes the definition of “nature-based approaches” states that nature-based approaches are sometimes referred to as “green infrastructure” and the proposed changes merely restate language already incorporated into the definition.

Comment: One commenter restated concerns from a 2016 NPRM comment that the current definition listed “green roofs” or “downspout disconnection” as examples of nature-based approaches, and recommended FEMA provide more applicable examples of nature-based approaches, including “property acquisitions and relocations;” “dam removal;” “levee notching, setbacks, or removal;” and “stream crossing upgrades.” The commenter also recommended FEMA expand the definition of nature-based approaches to encompass the restoration and conservation of natural features, providing added emphasis on the use of actions to bolster natural flood risk and water quality management services.

FEMA Response: FEMA's definition of “nature-based approaches” in the final rule, like the definition in the NPRM, does not contain “green roofs” or “downspout disconnection.” FEMA's definition is consistent with the Revised Guidelines glossary definition and, as explained above, the changes proposed by the commenter could result in inconsistencies including inconsistent implementation across other Federal agencies. While FEMA appreciates the commenters' concerns to include restoration or conservation of naturally occurring systems and processes and concerns related to green infrastructure, the Revised Guidelines help ensure key terminology is consistent across Federal agencies implementing FFRMS. Although the Revised Guidelines state that nature-based approaches can restore natural processes, FEMA does not believe the definition excludes either protecting or restoring natural processes.

FEMA referred to green roofs and downspout disconnection in the preamble to the NPRM as potential examples of green infrastructure, but not as part of the proposed regulatory definition. See 88 FR at 67890. As part of implementing this final rule, FEMA will provide additional resources with additional examples to address the commenter's concerns as explained above.

Comment: One commenter asked how FEMA defines natural systems and ecosystem processes.

FEMA Response: FEMA defined “nature-based approaches” and “natural features” in proposed § 9.4. FEMA believes those definitions are sufficient and the terms the commenter used are generally accepted terms found in Executive Order 11988 , as amended, that do not require additional definition in this final rule.

FEMA received three comments on the definitions of “natural and beneficial values of floodplains and wetlands” and “natural features.”

Comment: One commenter requested FEMA incorporate more explicit references to biodiversity, ecosystem functioning, and natural values into the regulation and requested “habitat connectivity” be added to the definition of “natural and beneficial values of floodplains and wetlands” as an example under “Living Resource Values.”

FEMA Response: FEMA respectfully declines the commenter's request, as the agency believes the concept habitat connectivity is adequately addressed under Living Resource Values through the changes made in this final rule. Specifically, the final rule describes Living Resource Values as “providing habitats and enhancing biodiversity for fish, wildlife, and plant resources.” This language adequately encompasses habitat connectivity, and no edits are required to the final rule.

Comment: A commenter requested FEMA include “functions” in addition to values when referring to protecting or restoring floodplains and wetlands to read “the beneficial functions and values of floodplains and wetlands.”

FEMA Response: FEMA's definition of “natural and beneficial values of floodplains and wetlands” incorporates functions and FEMA does not believe additional edits are required.

Comment: One commenter supported the changes proposed to the definitions of “natural and beneficial values of floodplains and wetlands,” and “wetlands” and additional definitions for “nature-based approaches” and “natural features” and requested FEMA develop post-regulatory guidance on functional floodplains and wetlands and nature-based solutions.

FEMA Response: FEMA agrees the changes to the definitions of “natural and beneficial values of floodplains and wetlands” and “wetlands” and the addition of definitions for “nature-based approaches” and “natural features” are helpful features of the rule. FEMA will distribute additional resources to SLTT partners and the public identifying what the FFRMS is, and how the agency will further implement the Executive Orders and part 9.

Comment: One commenter recommended the definition of “new construction” include “allowed new construction” associated with systems that must be located in the floodplain for supplementing water supply. The commenter requested the rule require consideration of specific stormwater runoff requirements for construction that must be completed in the floodplain and that FEMA recognize managed aquifer recharge (MAR)-related activities might be subject to other State and/or Federal regulation.

FEMA Response: The definition of “new construction” in part 9 must be broad in nature to support the various types of projects and activities FEMA may perform or fund. FEMA specifically incorporated examples in the definition of “new construction” to relate to typical FEMA actions, but those examples are not exhaustive. Under the 8-step decision-making process, FEMA identifies and evaluates practicable alternatives. If there is no practicable alternative outside of the floodplain, such as for functionally dependent uses, [ 130 ] the action may be carried out in the floodplain. The types of actions described by the commenter (managed aquifer recharge floodwater storage retention, spillways, injection wells and other built systems that must be located in the floodplain for their intended purpose of supplementing water supply), would be determined to be functionally dependent uses with likely no alternative outside of the floodplain. FEMA believes no changes are required to the regulation language, as those types of actions would be allowable subject to the application of the FFRMS and the minimization requirements outlined in 44 CFR 9.11 . FEMA notes some agency actions will also be subject to other Federal, State, Tribal, territorial, and/or local requirements and FEMA addresses this issue in the FFRMS policy.

Comments: Two commenters were supportive of the definition of “practicable.”

FEMA Response: FEMA agrees with the commenters that the updated definition of “practicable” in § 9.4 ensures nature-based approaches are considered as practicable alternatives consistent with Executive Order 11988 , as amended.

Comment: One commenter stated the definition of “practicable” was extremely vague and might not provide sufficient guidance to ensure meaningful comparison of alternatives. Recognizing the agency's need for a broad definition to account for differences in situations, the commenter noted the definition did not provide much guidance to determine what is truly “practicable,” as opposed to merely expedient. The commenter requested FEMA require consideration of long-term environmental, community, and economic benefits and costs of an alternative, to ensure practicability determinations were not skewed towards grey infrastructure or in-floodplain actions. The commenter wrote those actions appeared cheaper or more convenient in the short-term but carried greater long-term adverse effects, risks, and/or costs.

FEMA Response: FEMA did not make significant changes to the definition of “practicable.” The changes made in the NPRM and finalized in this rule add an agency authorities factor to clarify the agency's statutory and regulatory authorities may also limit FEMA's actions. These changes also updated the factors for consistency with the Revised Guidelines. FEMA does not believe additional changes are required to the definition of “practicable” as the factors listed are not all inclusive. The regulatory text in § 9.9 also provides examples and FEMA will provide additional examples in resources to SLTTs and the public to further clarify as appropriate.

Comment: One comment requested the agency provide examples of what “natural functions” of the floodplain means and specifically include “wildlife habitat and connectivity, carbon sequestration, and water quality improvement.”

FEMA Response: FEMA's definition of “restore” in § 9.4 does not require the revisions requested. FEMA's definition of the “natural and beneficial values of floodplains and wetlands” provides examples of what natural functions of the floodplain mean and additional edits are not required to address the commenter's concerns. Specifically, the definition provides some examples but is not all inclusive. FEMA can provide additional examples in resources to SLTTs and the public to further clarify as appropriate.

Comment: One commenter recommended linear transportation structures not fall under the definition of “structures.”

FEMA Response: FEMA defines both “structures” and “facilities” in § 9.4 and the agency believes these definitions are sufficiently clear. In the FFRMS policy, FEMA addresses both structures and facilities and how the agency will apply FFRMS to each. See section G of the FFRMS policy for more guidance on facilities. FEMA edited the FFRMS Policy accompanying this final rule to further clarify that section G.2 applies to “facilities.” Linear transportation structures fall under the definition of “facilities” for purposes of this part.

While one commenter wrote in support of the revised definition of “wetlands,” three other commenters requested revision to the definition.

Comment: One commenter stated the use of the United States Fish and Wildlife Service (USFWS) 's wetlands definition was problematic, stating in their experience, USFWS declined to engage on projects unless the projects involved species protected by the Endangered Species Act (ESA) and their habitat. The commenter noted water projects and developments involve regulation by the U.S. Army Corps of Engineers (USACE) more often than with USFWS, and recommended FEMA revise the definition of “wetlands” to use the USACE's long-standing wetland definition.

FEMA Response: FEMA appreciates the commenter's suggestion and declines to change the definition as the agency believes the reference to USFWS is more appropriate than to USACE's definition. FEMA's definition is consistent with the definition of “wetlands” in Executive Order 11990 and the agency is implementing that Executive Order with this regulation. FEMA believes changes to this definition may result in conflating the implementation of Executive Order 11990 with the Clean Water Act. While the commenter is correct that the USACE definition focuses on flood attenuation or mitigation, FEMA's part 9 implementation goes beyond those considerations for wetlands. FEMA also notes the agency performs Section 7 consultation with USFWS under ESA for actions that affect protected species or critical habitat.

Comment: One commenter recommended FEMA retain the reference to the specific publication provided in the definition of “wetlands.” The commenter stated the publication provided extensive examples and further clarification of what should be considered wetlands and was still used in the definition by the USFWS. The commenter requested the definition be updated to the correct year of publication in the final rule.

FEMA Response: FEMA's definition is consistent with the definition of “wetlands” in Executive Order 11990 , and the agency is implementing that Executive Order with this regulation. FEMA believes deleting the reference to a specific publication in the regulations will not result in a less specific definition as the commenter states. Eliminating references to specific publications helps reduce the potential for the regulations to be outdated if the publication is updated or replaced. As the commenter pointed out, the current regulatory text does not reference the correct year of the publication and the final rule will eliminate confusion around this point. FEMA still anticipates remaining consistent with the USFWS definition for purposes of part 9.

Comment: One commenter recommended the final rule specify whether artificially induced and/or isolated wetlands were included and add clearer agency expectations for subsections under the agency's FFRMS policy, particularly those involving wetlands.

FEMA Response: FEMA has not changed how the 8-step process applies to wetlands and does not intend to as part of FFRMS implementation in this rulemaking. FEMA's definition is consistent with the definition of “wetlands” in Executive Order 11990 and the agency is implementing that Executive Order with this regulation. FEMA believes the commenter is conflating the implementation of Executive Order 11990 with the Clean Water Act and FEMA's part 9 implementation goes beyond those considerations for wetlands.

In addition to the new and revised definitions provided in the NPRM, commenters requested FEMA add definitions to the final rule.

Comment: One commenter stated the need for clearer definitions was paramount to avoiding ambiguity and ensuring a shared understanding of key Start Printed Page 56951 terms. The commenter referenced the Climate-Informed Science Approach (CISA) as a term lacking a definition in the rule as an example of the need for more clarity.

FEMA Response: FEMA appreciates the commenter's concerns but changes to the final rule are not required to resolve those concerns. FEMA's explanation of the Climate-Informed Science Approach is consistent with Executive Order 11988 , as amended, and the Revised Guidelines. Rather than providing specific definitions in regulatory text, FEMA describes each approach in § 9.7(c) and in the FFRMS policy. FEMA believes these explanations are sufficiently clear and, because they are consistent with the Executive Order and Revised Guidelines, will not result in ambiguity.

Comment: One commenter recommended adding a definition of “development” for consistency with the NFIP at 44 CFR part 59 . The commenter also recommended adding a definition of “non-critical actions” to help define structures and facilities that clearly do not fall under the critical action standard and reduce misunderstandings.

FEMA Response: FEMA defines “support of floodplain and wetland development” in § 9.4 and a definition of “development” is incorporated into that definition. In the FFRMS policy, FEMA clarifies what constitutes a non-critical action as any activity that does not meet the definition of critical action. FEMA does not believe a specific definition in the regulatory text is necessary given the definition of “critical action” already provided in § 9.4.

Commenters requested clarification on the applicability of FFRMS generally as well as to specific types of actions.

Comments: Two commenters sought clarification on the Federal actions that are subject to FFRMS. Both commenters stated that the term “action subject to the FFRMS” could cause misinterpretation or confusion among different Federal agencies implementing the FFRMS. Another commenter asked whether the regulation and FFRMS policy would affect only new construction funded by FEMA. The commenter recommended a clarification to help States understand where FEMA's regulations implementing the FFRMS apply and whether FFRMS applied to State DOT projects funded through FHWA. The commenter also recommended FEMA clarify how the FFRMS applied to FEMA-funded, non-FEMA but still Federally-funded, and State-funded activities.

FEMA Response: FEMA defines “action subject to the FFRMS” as “any action where FEMA funds are used for new construction, substantial improvement, or to address substantial damage to a structure or facility,” consistent with Executive Order 11988 , as amended, and the Revised Guidelines. FEMA believes this definition is sufficiently clear. As explained in the preamble to the NPRM, 44 CFR part 9 applies to FEMA actions. As explained above, the requirements of this rule apply to grants funding the new construction, substantial improvement, or repair of substantial damage under FEMA programs such as IA, PA, and HMA programs, and grants processed by FEMA's GPD (involving grants for preparedness activities). All Federal agencies will utilize the Revised Guidelines for their own FFRMS implementation. Roads that are under the jurisdiction of another Federal agency, such as those under the FHWA, are subject to that agency's requirements as they generally are ineligible for funding under FEMA's grant assistance programs.

As explained in § 9.5(a)(3), FEMA will apply FFRMS only to new actions for which assistance is made available pursuant to declarations under the Stafford Act that are commenced on or after the effective date of the final rule, and new actions for which assistance is made available pursuant to notices of funding opportunity that publish on or after the effective date of the final rule. Ongoing projects will not be impacted by this final rule. [ 131 ]

Comment: A commenter requested FEMA clearly define how Federally funded expansions, renovations, rebuild, rehabilitations and similar activities would be impacted by the FFRMS. The commenter noted many infrastructure projects are not static structures, but rather periodically require rehabilitation, renovation, and/or expansion and thus would include a combination of rehabilitation of existing construction, modification of existing infrastructure, and entirely new infrastructure elements that would be combined during a project to create the “new” final structure and/or system. The commenter stated that FFRMS seemed to apply only to new structures that can be sited or elevated without moving or damaging existing construction and requested confirmation of that understanding. Another commenter commended FEMA's proposed policy provisions for identifying actions that might be subject to determinations of substantial damage or substantial improvement.

FEMA Response: Part 9 does not apply only to new structures, and FEMA believes the rule and FFRMS policy are sufficiently clear on this point. As stated above, FEMA defines “action subject to the FFRMS” as “any action where FEMA funds are used for new construction, substantial improvement, or to address substantial damage to a structure or facility,” consistent with Executive Order 11988 , as amended, and the Revised Guidelines.

In § 9.4, FEMA defines “new construction” in this final rule as “the construction of a new structure or facility or the replacement of a structure or facility which has been totally destroyed. New construction includes permanent installation of temporary housing units because even though such housing may initially have been planned to be temporary, when it is permanently installed, it becomes a permanent housing solution for survivors. New construction in wetlands includes draining, dredging, channelizing, filling, diking, impounding, and related activities.” Also in § 9.4, FEMA further defines “substantial improvement” as any repair, reconstruction or other improvement of a structure or facility, which has been damaged in excess of, or the cost of which equals or exceeds, 50 percent of the pre-disaster market value of the structure or replacement cost of the facility (including all “public facilities” as defined in the Stafford Act) (1) before the repair or improvement is started, or (2) if the structure or facility has been damaged and is proposed to be restored. Substantial improvement includes work to address substantial damage to a structure or facility. As it related to the commenter's stated concern, if a facility is an essential link in a larger system, the percentage of damage will be based on the cost of repairing the damaged facility relative to Start Printed Page 56952 the replacement cost of the portion of the system which is operationally dependent on the facility. The term “substantial improvement” does not include any alteration of a structure or facility listed on the National Register of Historic Places or a State Inventory of Historic Places. Where an action falls under one of the definitions above, it would be considered an action subject to FFRMS.

The revisions to part 9 do not change FEMA's long-standing requirement as part of implementing Executive Order 11988 , as amended, to only perform or fund actions within or affecting floodplains if those actions are the only practicable alternative. Through the 8-step process, FEMA considers alternative locations, alternative actions, nature-based solutions, and the no action alternative under the practicability analysis. If there is no practicable alternative, FEMA will perform or fund the action and will minimize any adverse impacts when doing so.

Commenters also commented on the applicability of FFRMS to specific FEMA programs.

Comments: Some commenters stated support for FEMA's policy regarding FFRMS applicability to temporary and permanent housing. One commenter requested FEMA give careful consideration to potentially unintended consequences of greatly expanded requirements for victims of a catastrophic disaster in need of emergency federal disaster assistance. The commenter cited a study related to the impacts of Hurricane Ian and discussed how the flood extent in many areas was approximated by the Special Flood Hazard Area (SFHA) boundaries, noting without constraints in development in the SFHA, flood damages for the area studied would have skyrocketed. Another commenter expressed concern that the proposed rule could increase local costs and delay affordable housing projects. The commenter requested FEMA consider ways to advance affordable housing projects, such as through expansion of its “Housing Mitigation Assistance” grants and requested the agency make accommodations for such projects to support a more expeditious regulatory process.

FEMA Response: FEMA appreciates the commenter's interest in the agency's Individuals and Households Program. FEMA's revisions in § 9.13 reflect the agency's consideration of the need for disaster survivors to quickly recover, while also addressing the need for more resilient housing. FEMA notes this rulemaking will not expand the SFHA for NFIP purposes nor does it apply to a local community's permitting processes under the NFIP's floodplain management regulations. Those regulations are found at 44 CFR part 59 et seq. FEMA notes the agency does not have “Housing Mitigation Assistance” grants, but where FEMA provides funding for housing, the agency will consider social concerns and economic aspects as part of the practicability analysis in the 8-step process.

Comments: Multiple commenters referenced the NFIP and FFRMS applicability. One commenter stated that FEMA only applies the 8-step process programmatically to the NFIP as a whole. The commenter further noted the FFRMS would only apply to new construction or substantial improvement to existing structures or facilities that receive FEMA funding. The commenter stated support for exempting all privately funded activities from the FFRMS as those activities were beyond the scope of FEMA's authority and would create challenges in determining the geographic scope of the FFRMS defined floodplain and increased construction costs that would negatively impact housing affordability.

Another commenter wrote asking if the FFRMS policy would impact where new flood insurance policies could be issued. The commenter recommended FEMA consider coordinating with other Federal agencies and expanding the Coastal Barrier Resources Act (CBRA) and/or identifying additional areas where new flood insurance policies could not be issued based on FFRMS approaches.

A third commenter wrote the work needed to restore floodplain connectivity should have a streamlined regulatory process and additional financial and technical support to meet regulatory burdens. The commenter stated a fundamental tenet of the NFIP was to discourage increases in base flood elevation from “traditional development,” whereas floodplain restoration projects are intended to increase the base flood elevation in areas where it is safe and socially acceptable to do so. The commenter stated floodplain restoration work was urgently needed in many flood-prone areas, but the NFIP requirements hindered federal investments in floodplain restoration work. The commenter stated that regulatory reforms are needed to ensure Federal restoration dollars could be leveraged to help reduce flood risks and damages.

FEMA Response: FEMA agrees with the commenter that privately funded activities are not subject to this rule. This rulemaking is not regulating privately funded action; instead, this rulemaking applies to actions subject to the FFRMS, i.e., Federally funded projects for new construction, substantial improvement, and repairs to address substantial damage. For the purposes of regulating private activities, the NFIP's floodplain management standards will continue to generally apply in NFIP participating communities. [ 132 ] The commenter is also correct that FEMA applies part 9 programmatically to the NFIP. [ 133 ] Notwithstanding the programmatic application of part 9 to the NFIP, the expanded floodplain established under this rule has no impact on where new flood insurance policies may be issued (including community eligibility for the NFIP participation and individual premiums) because the expanded floodplain only applies to actions subject to the FFRMS.

In short, part 9 does not apply to the issuance of flood insurance policies. This rule and accompanying policy will have no effect on where new flood insurance policies may be issued. FEMA notes that only Congress can expand CBRA, and USFWS has primary authority for the implementation of CBRA. While FEMA appreciates the commenter's concerns regarding floodplain restoration, regulatory reforms to the NFIP suggested by the commenter are beyond the scope of this rulemaking.

Four commenters had questions regarding the applicability of the final rule and FFRMS policy to facilities.

Comment: A commenter recommended FEMA clarify special considerations for infrastructure projects by providing more information and guidance on how to implement FFRMS for “facilities.” The commenter stated essential facilities like roadways, bridges, and utilities might be vulnerable to flood damage and required even more attention, but the rule was largely silent as to how FFRMS applied to these projects.

The same commenter wrote of their experience with agencies struggling to adequately assess relevant flood risks when evaluating vital facilities and Start Printed Page 56953 recommended incorporating language into Steps 1 and 5 of the 8-step process, clarifying appropriate considerations and methods to apply the FFRMS to facilities. The commenter requested FEMA set forth factors to consider when defining the FFRMS floodplain for facilities (such as considering a larger project area and vulnerability of nearby assets that could be affected) to encourage better, more informed decisions. The commenter also recommended FEMA revise § 9.11 to clarify that although elevation is not universally required for facilities, mitigation measures for facilities subject to the FFRMS must be designed to be resilient to the FFRMS flood elevation.

Another commenter encouraged FEMA to provide more information and guidance in the final rule on implementing the FFRMS for facilities. The commenter stated that most facilities would likely require different implementation considerations and standards than those defined in the rule for structures. The commenter stated that elevation may not be an appropriate means to improve or achieve resilience for facilities and requested that the final rule and related guidance provide variables to consider, which could help define appropriate resilience measures in addition to or in place of elevation.

FEMA Response: FEMA appreciates the commenter's references to challenges with assessing relevant flood risks for vital facilities and infrastructure. As the commenter notes, several factors must be considered when implementing the FFRMS for facilities. FEMA believes that the agency's 8-step process and implementing policy account for the specific concerns raised in the examples provided. The agency's policy reflects a preference for using the CISA that considers sea level rise and FEMA's practicability analysis incorporates social concerns and economic aspects into the 8-step process. FEMA's revisions to part 9 reflect consideration of the type and criticality of the action involved, the availability and actionability of the data, and equity concerns in the implementation of Executive Order 11988 , as amended. FEMA also has an agency-wide initiative focused on reducing barriers and increasing opportunities so that all people, including those from vulnerable and underserved communities, can get help when they need it. [ 134 ] Additionally, FEMA reviews all proposed FEMA-funded actions for potential disproportionate and adverse human health and environmental effects on communities with environmental justice concerns using a standardized environmental justice compliance review process.

For the reasons described below, FEMA's current proposed FFRMS policy uses the FFRMS flood elevation and corresponding floodplain to establish the minimum level to which a structure or facility must be resilient. For facility projects that are subject to the FFRMS, the FFRMS flood elevation represents the magnitude of flooding that must be considered in incorporating flood resilient design features into project designs. This approach allows the FFRMS to be integrated as one element of project-specific comprehensive design methods and leaves open the possibility of more prescriptive design requirements as infrastructure design methods improve, better incorporating consideration of continually changing hazard conditions.

Due to the vast diversity of facilities, the highly project-specific nature of facilities projects, and numerous options for making them resilient, infrastructure standards (in terms of narrowly scoped specifications) to reduce risk from climate change and future conditions currently do not exist on a national level. This lack of established standards, and the long timeline necessary to develop them, requires consideration of less prescriptive approaches. In the absence of such standards, Federal agencies that oversee construction of infrastructure projects such as the FHWA and USACE apply project-specific risk assessment and adaptive management approaches, which generally require data collection, detailed studies, benefit-cost analyses, and consideration of various alternatives, adaptation, and mitigation measures. [ 135 ]

FEMA already incorporates many of these approaches into its grant requirements. FEMA Recovery Interim Policy 104-009-11 Version 2.0, “Consensus-Based Codes, Specifications and Standards for Public Assistance” (December 20, 2019) requires “application of the latest nationwide consensus-based codes, specifications and standards that incorporate hazard resistance for PA funded projects,” including buildings, electric power, roads, bridges, potable water, and wastewater. [ 136 ] Appendix A of the policy includes an extensive list of risk assessment and adaptive management methods which applicants are required to use “as the minimum design criteria for eligible projects.” Eligibility for Hazard Mitigation Assistance funding requires SLTT partners to have up-to-date hazard mitigation plans, which incorporate community-wide risk assessment and adaptive management approaches applicable to facilities or linear infrastructure.

Further, FEMA does not believe changes to the final rule are required as the regulation applies the 8-step process to any action, as defined in 44 CFR 9.4 , which includes facilities. In the 8-step process, FEMA considers not just whether proposed actions would be in a floodplain or wetland, but also whether the proposed action would affect a floodplain or wetland. FEMA has routinely applied Steps 1 and 5 to facilities. FEMA also applies Step 4, which identifies impacts of a proposed action at and beyond the proposed action location. FEMA will distribute additional resources for the public and SLTT partners to help identify what the FFRMS is, and how the agency will implement the Executive Orders. These resources will help applicants better understand the FFRMS as they apply for FEMA programs.

Section G.2. of FEMA's FFRMS policy discusses flood risk minimization for facilities. FEMA's FFRMS policy uses the FFRMS flood elevation and corresponding floodplain to establish the minimum level to which a structure or facility must be resilient. For facilities projects that are subject to the FFRMS, the FFRMS flood elevation represents the magnitude of flooding that must be considered in incorporating flood resilient design features into facility project designs. Start Printed Page 56954 This approach allows the FFRMS to be integrated as one element of project-specific comprehensive design methods, and leaves open the possibility of more prescriptive design requirements as infrastructure design methods improve, better incorporating consideration of continually changing hazard conditions.

FEMA further believes that revising the text of § 9.11 to clarify that mitigation measures for facilities subject to FFRMS must be designed to be resilient to the FFRMS flood elevation, as the commenter requested, is not necessary. As the commenter noted, this point is made in the FFRMS policy, and FEMA does not believe changes to the regulatory text are required to achieve the FFRMS resilience.

Comment: One commenter raised several questions regarding FFRMS implementation and facilities. The commenter stated that building transportation infrastructure to survive extreme events is a good investment, but the FFRMS is overly conservative and based on risk of low probability. The commenter asked about the applicability of part 9 and the FFRMS to a range of potential actions from linear transportation structures to roadways, bridges, and culverts and raised concerns with how FFRMS application to these types of actions might raise conflicts with other Federal, State, or local agencies. The commenter also stated concerns about elevating facilities and provided an example of where the FFRMS would elevate a bridge to a height greater than the flood-prone height of the connecting roads. The commenter recommended FEMA clarify roadways and associated bridges and culverts were not required to perform an alternatives analysis for their location in a floodplain.

FEMA Response: FEMA appreciates the commenter's concerns regarding the applicability of FFRMS and part 9 to specific infrastructure projects. FEMA defines both “structures” and “facilities” in § 9.4 and the agency believes these definitions are sufficiently clear to explain FFRMS and part 9 applicability to specific actions. Executive Order, 11988, as amended, requires both structures and facilities be resilient against current and future flood hazards. FEMA believes that, as described by the commenter, roadways, bridges, culverts, and linear transportation structures would fall under the definition of “facilities” for this part and thus would not necessarily be exempt from part 9.

As explained above, FEMA defines “action subject to the FFRMS” as “any action where FEMA funds are used for new construction, substantial improvement, or to address substantial damage to a structure or facility.” The FFRMS applies to grants for projects funding the new construction, substantial improvement, or repair of substantial damage under FEMA programs such as IA, PA, and HMA programs, and grants processed by FEMA's GPD. FEMA does not fund repairs or improvements to Federal-aid roads, and this rulemaking would not be applicable to those roads. Rather, the FHWA regulations would govern those actions. Where FEMA may provide funding, FEMA's FFRMS policy provides details on how FEMA will coordinate with other agencies when implementing actions in the same area as another Federal agency. See FFRMS policy Section H, page 9. When coordinating with other Federal agencies, FEMA generally defaults to the FFRMS policy approach in FEMA's FFRMS policy, as appropriate. Where FEMA provides funding for these activities, FFRMS applies to improve resilience to facilities against both current and future flood risks.

In the FFRMS policy, FEMA addresses both structures and facilities and how the agency will apply FFRMS to each. See section G of the FFRMS policy for more guidance on facilities. Note FEMA edited the FFRMS policy accompanying this final rule to further clarify that section G.2 applies to “facilities,” by using the term “Facilities” instead of the term “Non-Structure Facilities.”

Further, § 9.11(d)(6) states when FEMA is providing funding, a more restrictive Federal, State, or local floodplain management standard will be applied. Section G.2 of FEMA's FFRMS policy further discusses flood risk minimization for facilities and clarifies that FEMA would also allow methods other than elevation to be used to improve resilience against flooding up to the flood elevation of the FFRMS floodplain in conjunction with any other applicable codes and standards. [ 137 ]

FEMA's FFRMS policy uses the FFRMS flood elevation and corresponding floodplain to establish the minimum level to which a structure or facility must be resilient. The minimization requirements are similar to how FEMA currently implements part 9 for the 1 percent and 0.2 percent annual chance floods. For facility projects that are subject to the FFRMS, the FFRMS flood elevation represents the magnitude of flooding that must be considered in incorporating flood resilient design features into facility project designs. This approach allows the FFRMS to be integrated as one element of project-specific comprehensive design methods and leaves open the possibility of more prescriptive design requirements as infrastructure design methods improve, better incorporating consideration of continually changing hazard conditions. Further, as explained above, FEMA already incorporates FHWA Hydraulic Engineering Circulars 17 and 25 ( Highways in the River Environment and Highways in the Coastal Environment ) into its Public Assistance grant requirements.

To address the commenter's concerns regarding overly conservative methods, FEMA notes the FFRMS is a flexible framework to define the floodplain that allows agencies to choose among several approaches to expand the base floodplain to a higher vertical elevation and corresponding horizontal extent for all Federally funded projects. FEMA's FFRMS policy is not a one-size-fits-all approach. Rather, FEMA's policy approach is flexible to address criticality of the action being taken, data availability based on the location of the action, and equity concerns.

Finally, the final rule does not change many of the current requirements for proposed actions. Proposed actions involving roadways, bridges, and culverts located in or impacting floodplains and wetlands continue to be subject to alternatives analysis under Executive Order 11988 , as amended, and part 9. For certain small-scale actions under FEMA's PA program, the proposed rule increases the dollar value thresholds for projects that are exempt from the 8-step process or that are subject to an abbreviated 8-step review.

Comment: The same commenter stated that enhancing resilience should be the responsibility of the States to enable community-specific strategies. The commenter requested clarification on whether States and localities could use Federal funds for resilience measures, such as raising or widening roadways and bridges to meet the increased vertical elevation and expanded horizontal floodplain while still qualifying for FEMA funding. The commenter further stated the FFRMS would remove risk to structures from risk-based design criteria some States had in place and would require a one-size-fits-all approach for bridge-sized Start Printed Page 56955 structures. The commenter also noted some non-Federal partners might not allow States to select the FFRMS approach. The same commenter stated the FFRMS approaches added an unnecessary factor of safety for proposed actions, as many States would replace a structure multiple times before the CISA floodplains would take place. The commenter stated it was impossible to accurately predict change over long periods of time due to the nature of these systems.

FEMA Response: FEMA agrees that States and localities should lead their own efforts to enhance resilience. FFRMS is required for Federal actions that are subject to the FFRMS to protect against current and future flood risks and help ensure that Federally-funded projects last as long as intended. FEMA's FFRMS policy is not a one-size-fits-all approach. Rather, FEMA's policy approach is flexible to address criticality of the action being taken, data availability based on the location of the action, and equity concerns. Risk is an inherent factor in applying all of the FFRMS approaches. FEMA considers the criticality of the action in determining the level of risk that must be considered in minimizing flood hazards. Critical actions are those actions for which even a slight chance of flooding is too great and would be protected to a higher level under the FFRMS.

FEMA explained above the applicability of the FFRMS and the 8-step process generally to facilities. As noted above, part 9 only applies to FEMA actions. Where FEMA may provide funding, FEMA's FFRMS policy provides details on how FEMA will apply the appropriate FFRMS approach to improve resilience to facilities against both current and future flood risks.

SLTTs can provide input into the determination. Pursuant to 44 CFR 9.11(d)(6) , a more restrictive Federal, State, or local standard will be used in lieu of the FFRMS. FEMA values additional input from SLTT partners and the public in the 8-step process. FEMA notes, where the agency provides funding, any increased costs are generally eligible for funding under FEMA's assistance programs subject to cost share requirements.

Regarding the commenter's concerns about replacing a facility or structure several times over a period of time, FEMA's preferred approach (CISA) incorporates service life as part of determining the FFRMS floodplain. FEMA understands the commenter's concerns and will determine the appropriate service life on a case-by-case basis for each action. The FFRMS Job Aid provides additional information on service life and how FEMA will make those individual determinations. [ 138 ]

Comment: The same commenter also wrote by raising the base flood elevation, the FFRMS would make the floodway obsolete and asked if FEMA would stop using floodways to regulate construction, and let local governments decide how much development was acceptable while adhering to the FFRMS. The commenter further recommended “temporary encroachments,” such as temporary structures required for bridge construction, be explicitly exempted from the FFRMS.

FEMA Response: FEMA assumes the commenter's reference to the base flood elevation is the base flood elevation established and applicable under the NFIP. This final rule does not raise the base flood elevation under the NFIP. The NFIP is a program through which property owners in participating communities can purchase Federal flood insurance as a protection against flood losses. [ 139 ] As a condition of eligibility, a community must adopt and enforce floodplain management regulations that incorporate NFIP minimum floodplain management criteria developed by the Administrator. [ 140 ] Further information regarding FEMA's minimum floodplain management standards for the NFIP can be found at 44 CFR part 59 et seq. Any update to those standards would require a rulemaking to revise the appropriate regulatory sections of the CFR. By contrast, the FFRMS as implemented by this rulemaking, only applies to actions where FEMA funds are used for new construction, substantial improvement, or repairs to address substantial damage to structures and facilities. [ 141 ]

As explained above, § 9.4 defines both “floodway” and “regulatory floodway.” The definition of “floodway” was not changed with this final rule and the definition of “regulatory floodway” was further clarified by eliminating the reference to a specific amount set by the NFIP and instead defining the term to mean the area regulated by Federal, State, or local requirements to provide for the discharge of the base flood so that the cumulative rise in water surface is no more than a designated amount above the base flood elevation. These edits more accurately encompass situations where communities have adopted more restrictive floodway definitions than the minimum specified by the NFIP. The changes are intended to help stakeholders better understand what a regulatory floodway is and how it is determined without tying the term to a specific amount that can change under the NFIP.

Regarding temporary encroachments, § 9.5(c)(1) exempts actions under PA category B pursuant to section 403 of the Stafford Act. Those actions may include temporary repairs to structures and facilities. Any temporary work associated with permanent work, however, is generally included in the 8-step analysis for the permanent action.

Comment: A commenter stated the RIA was limited and inadequate and cited several examples of where FEMA should improve the RIA. Specifically, the commenter stated that FEMA attempted to isolate a population of actions where the standards would be applied, limiting the analysis to structures that will be paid for with Federal funds and did not capture the costs and benefits of the regulatory alternatives that would be associated with applying the FFRMS to Federal licenses and permits. The commenter also stated that FEMA did not consider the impacts of the new standards on the floodplain regulations mandated for communities that participate in the NFIP and the economic impacts of applying the new standards to NFIP floodplain mapping and the accreditation of levees under the NFIP. The commenter further stated accreditation was mapping and the scope of 44 CFR part 9 included application of the 8-step process to NFIP mapping.

FEMA Response: FEMA appreciates the commenter's suggestions regarding the RIA but believes the commenter's requests go beyond the scope of this rulemaking. FEMA disagrees with the commenter that the RIA should capture costs and benefits associated with Federal licenses and permits. The changes made to part 9 to implement FFRMS only apply to actions subject to the FFRMS. FEMA defines “action subject to the FFRMS” as “any action where FEMA funds are used for new construction, substantial improvement, Start Printed Page 56956 or to address substantial damage to a structure or facility,” consistent with Executive Order 11988 , as amended, and the Revised Guidelines. The FFRMS applies to grants for projects funding the new construction, substantial improvement, or repair of substantial damage under FEMA programs such as IA, PA, and HMA programs, and grants processed by FEMA's GPD. Accordingly, the scope of FEMA's regulatory impact analysis is limited to the FEMA projects where the FFRMS standards would be applied.

FEMA further does not believe the agency is required to consider the impacts of the new standards on the floodplain regulations mandated for communities that participate in the NFIP and the economic impacts of applying the new standards to NFIP floodplain mapping and the accreditation of levees under the NFIP. As explained above, the NFIP is a program through which property owners in participating communities can purchase Federal flood insurance as a protection against flood losses. As a condition of eligibility, a community must adopt and enforce floodplain management regulations that incorporate NFIP minimum floodplain management criteria developed by the Administrator. Further information regarding FEMA's minimum floodplain management standards for the NFIP can be found at 44 CFR part 59 et seq. By contrast, the FFRMS as implemented by this rulemaking, only applies to actions where FEMA funds are used for new construction, substantial improvement, or repairs to address substantial damage to structures and facilities.

Several commenters expressed support for the use of the CISA but sought additional clarification on implementation of the approach. A few commenters raised concerns with the use of the CISA.

Comment: A commenter stated utilizing the CISA to determine the FFRMS floodplain where possible was of critical importance as CISA offered a forward-thinking approach to improve resilient development considering both current and future flood risk. The commenter noted the necessary data and modeling capabilities underpinning CISA have continued to expand in recent years, making CISA an increasingly practicable methodology for more accurately determining the extent of the FFRMS floodplain.

FEMA Response: FEMA agrees with the commenter that since the introduction of the CISA in 2015, additional data has become available to better inform CISA. [ 142 ] FEMA believes data availability and actionability will continue to advance for CISA in the future. Specifically, FEMA expects more data will be developed, supporting broader-based application of CISA as agencies implement the FFRMS, and this data will be considered and incorporated into future updates of the FFRMS and FEMA's implementation thereof. FEMA's policy approach is to use CISA where available, recognizing the data is still not available in every location.

Comment: Two commenters wrote the CISA did not promote predictability or reduce uncertainty as required by Executive Orders 12866 and 13563 and instead left the public to guess a standard from a range of possible climate scenarios. The commenters stated questions regarding the flood hazard area and elevation remain unanswered within the CISA and the approach lacked specific criteria for making those determinations. The commenters noted FEMA did not propose to require the use of CISA in the agency's 2016 NPRM because of the lack of available CISA data and stated those concerns still exist. The commenters further stated that the lack of coherent decision criteria within the CISA raised concerns about the clarity of Congressional authority guiding the standard.

FEMA Response: FEMA disagrees with the commenters that the CISA results in uncertainty for the public as the agency provided information on the CISA with the NPRM. Appendix H of the Revised Guidelines  [ 143 ] provides an overview of the available and actionable data for CISA, which is the basis for interagency supporting tools to implement the FFRMS. As explained above, the Science Subgroup convened by the Flood Resilience Interagency Working Group (IWG) of the National Climate Task Force published the FFRMS CISA State of the Science Report. [ 144 ] The FFRMS CISA State of the Science Report refines the initial framework from Appendix H and specifically identifies the latest sea level rise projections from the National Climate Assessment as actionable, stating that each agency should factor projected regional/local sea level change into Federal investment decisions located as far inland as the extent of estimated tidal influence, now and in the future, using the most appropriate methods for the scale and consequence of the decision. [ 145 ] This report is the basis of the interagency implementation and supporting tools such as the FFRMS Job Aid. [ 146 ] FEMA is relying on these interagency processes to select and evaluate the data and methods used. FEMA published the FFRMS Job Aid and the FFRMS CISA State of the Science Report in the public docket associated with this rulemaking. [ 147 ] FEMA also posted the FFRMS Job Aid on its website  [ 148 ] and currently plans to use the methodology found in the FFRMS Job Aid to determine the FFRMS floodplain as explained above.

FEMA believes the policy approach detailed in the agency's FFRMS Policy is sufficiently certain for FFRMS implementation. As detailed in the FFRMS Policy, FEMA will use the CISA when such data is available and actionable as further explained in Appendix H of the Revised Guidelines  [ 149 ] and refined in the FFRMS CISA State of the Science Report. [ 150 ] Where the CISA data is not available and/or actionable, the agency will use either the FVA or 0.2PFA depending on the criticality of the action and data availability. Consistent with the Start Printed Page 56957 information in the FFRMS CISA State of the Science Report regarding data availability/actionability, [ 151 ] FEMA will initially rely on the methodology from the FFRMS Job Aid  [ 152 ] to make the CISA, FVA, and 0.2PFA determinations.

FEMA understands data availability and actionability is a key factor in completing this analysis in a consistent, equitable manner. As stated above, since the introduction of the CISA in 2015, additional data has become available to better inform CISA. [ 153 ] FEMA believes data availability and actionability will continue to advance for CISA in the future. However, as actionable climate data are currently only available along low-lying coastal shorelines on the Atlantic and Gulf Coasts not subject to runup or overtopping pursuant to the FFRMS CISA State of the Science Report, [ 154 ] FEMA is proposing the FVA and 0.2PFA alternatives in the absence of actionable CISA data. FEMA notes, consistent with current practice, the agency will continue make the floodplain determinations as part of the action taken, reducing the burden on applicants in the process. FEMA estimated the cost for determining the appropriate FFRMS floodplain in the Administrative Cost section within the RIA.

Commenters inquired as to how FEMA would implement CISA as part of the agency's FFRMS implementation.

Comment: A commenter requested FEMA amend § 9.7(c)(i)(A) to require an assumption that “climate impacts would be more rather than less severe under conditions of uncertainty.”

FEMA Response: FEMA is not codifying the specific climate scenarios to be used as part of the CISA analysis. As previously explained, FEMA is relying on interagency tools to determine CISA flood elevations and corresponding horizontal floodplains. FEMA will initially implement this final rule using the FFRMS Job Aid that was published in the public docket associated with this rulemaking along with the proposed rule. The FFRMS Job Aid is also on FEMA's website. [ 155 ]

Comments: One commenter characterized CISA as a framework built upon continually evolving models, projections, and assumptions regarding climate change and anticipated future conditions. The commenter stated the decision criteria under the CISA approach was not adequately defined in the rule and the information provided about CISA in the rule regarding the best available information remained unspecified, raising concerns about project implementation and general uncertainty. Another commenter recommended that FEMA make clear its ability to update how it implements the FFRMS approaches as necessary according to the latest climate science, rather than going through a rulemaking process for each successive update. The commenter stated that the CISA State of the Science Report provided robust information on CISA implementation but because of its length was not necessarily an easily accessible reference document. The commenter recommended providing succinct and practical guidance on CISA to facilitate implementation of the approach. The comment suggested that such guidance could including a representative list of acceptable data sources and guidance on how to interpret and apply these sources (for instance, how to choose an appropriate timeline or planning scenario).

FEMA Response: FEMA's explanation of the CISA is consistent with Executive Order 11988 , as amended, and the Revised Guidelines. FEMA has not provided specific definitions of each approach under FFRMS but rather describes each in § 9.7 and also in the FFRMS policy. FEMA believes these explanations are sufficiently clear and will not result in ambiguity or misunderstanding because they are consistent with the Executive Order and Revised Guidelines.

FEMA further believes the information provided is consistent with Executive Order 11988 , as amended; the Revised Guidelines; and the CISA State of the Science report. The information is also sufficient to implement FFRMS and CISA. FEMA will rely on 44 CFR 9.7 , FEMA Policy 104-008-2: Guidance on the Use of Available Flood Hazard Information, [ 156 ] the Revised Guidelines, and the FFRMS CISA State of the Science Report in determining whether CISA and flood hazard data is available and actionable. The FFRMS CISA State of the Science Report  [ 157 ] is the basis of the interagency implementation and supporting tools such as the FFRMS Job Aid. [ 158 ] FEMA published the FFRMS Job Aid and the FFRMS CISA State of the Science Report in the public docket associated with this rulemaking. [ 159 ] FEMA also posted the FFRMS Job Aid on its website. [ 160 ]

FEMA intends to leverage the FFRMS Job Aid when implementing FFRMS. FEMA will initially rely on the methodology found in the FFRMS Job Aid for determining the FFRMS floodplain and, as explained elsewhere in our responses, will accept higher standards provided by other Federal, State, or local entities in accordance with 44 CFR 9.11(d)(6) so long as it is as least as restrictive as FEMA's FFRMS floodplain determination and adopted by the community for use, including where communities have adopted local CISA. FEMA will continue to collaborate across the Federal government to develop tools to facilitate the implementation of CISA and the FFRMS. The IWG recently released a beta version of the Federal Flood Standard Support Tool (FFSST), a novel interactive, map-based tool that incorporates new data to help users identify if a Federally funded project is in the FFRMS floodplain, for comment. [ 161 ] FEMA intends to provide additional resources to assist stakeholders as FFRMS is implemented.

Consistent with Executive Order 11988 , as amended, and the Revised Guidelines, CISA requirements will change as the available and actionable data change. The MitFLG in consultation with the Federal Interagency Floodplain Management Task Force (FIFM-TF) will reassess FFRMS annually, after seeking stakeholder input, and provide recommendations to the WRC to update FFRMS, including the FVA, if warranted based on accurate and actionable science that takes into account changes to climate and other changes in flood risk. The WRC shall issue an update to FFRMS at least every 5 years. [ 162 ]

Comments: Three commenters requested that FEMA clarify how it will determine that CISA data are available and actionable when determining the FFRMS floodplain. One of the commenters asked whether CISA data availability was dependent on FEMA mapping using CISA data. Another commenter requested clarity on how CISA would be assessed. The commenter noted the CISA data must be “existing” and both “available” and “actionable,” and stated this implied that entities proposing a project were only obligated to rely on information that was already existing, available, and actionable, which was inconsistent with the rest of the rule that focused on creating project-specific assessments.

FEMA Response: Data availability is not dependent on the development of FEMA regulatory mapping products (such as effective Flood Insurance Rate Maps [FIRMs]) utilizing CISA data. The Revised Guidelines require agencies to utilize the “best available and actionable science.” The Revised Guidelines state that in this context, “best-available” generally refers to science, data or information that is:

  • Transparent—clearly outlines assumptions, applications, and limitations;
  • Technically credible—transparent subject matter or more formal external peer review, as appropriate, of processes and source data;
  • Usable—relevance and accessibility of the information to its intended users;
  • Legitimate—perceived by stakeholders to conform to recognized principles, rules, or standards. Legitimacy might be achieved by existing government planning processes with the opportunity for public comment and engagement. [ 163 ]

The Revised Guidelines further state that actionable science includes theories, data, analyses, models, projections, scenarios and tools that are:

  • Relevant to the decision under consideration;
  • Reliable in terms of its scientific or engineering basis and appropriate level of peer review;
  • Understandable to those making the decision;
  • Supportive of decisions across wide spatial, temporal, and organizational ranges, including those of time-sensitive operational and capital investment decision-making;
  • Co-produced by scientists, practitioners, and decision-makers, and meet the needs of and are readily accessible by stakeholders.

These concepts of best-available and actionable science are further described in Part II, Step 1 of the Revised Guidelines, in the context of the various approaches for determining a floodplain and in Appendix H of the Revised Guidelines specifically as it relates to the CISA. [ 164 ]

As previously explained, the FFRMS CISA State of the Science Report  [ 165 ] contains an up-to-date review and update of the best-available, actionable science that can support application of the CISA, and is the basis of the interagency implementation and supporting tools such as the FFRMS Job Aid. [ 166 ] FEMA will initially rely on the methodology in the FFRMS Job Aid to determine the FFRMS floodplain when implementing this final rule.

FEMA disagrees with the commenter that requiring CISA data be available and actionable is inconsistent with the rest of the rule. The 8-step process is action-specific, and the floodplain determination is made based on the location of the action, but the data to determine the floodplain at that location must be available and actionable for CISA to be utilized. FEMA's FFRMS policy further defines where CISA is applicable.

Comments: FEMA received comments regarding the service life of proposed actions and how the agency would calculate the service life of actions. One commenter suggested FEMA provide guidelines on how to determine an appropriate period. Another commenter noted FEMA used a default 50-year lifecycle analysis that would not be appropriate for all actions and requested FEMA provide information on how the 50-year lifecycle timeline was determined, as well as guidelines on how to determine the appropriate lifecycle on a case-by-case basis.

FEMA Response: FEMA's analysis of the rule's benefits relied upon a report defaulting to a 25-year and 50-year lifecycle for all actions. However, when making floodplain determinations, FEMA intends to determine the appropriate service life on a case-by-case basis for each action. This will ensure that FEMA evaluates floodplain hazards over the appropriate lifecycle for each action. The FFRMS Job Aid provides additional information on service life and how FEMA will make those individual determinations. [ 167 ]

FEMA's RIA used the 2022 report titled “A Benefits Analysis of Increased Freeboard for Public and Nonresidential Buildings in Riverine and Coastal Floodplains,” (“2022 report”) in its analysis of benefits. The 2022 report calculated benefits for increased freeboard over 25-year and 50-year useful lives under a variety of climate change scenarios. [ 168 ] FEMA's analysis considered the benefits of the rule assuming a 50-year useful life.

Comment: A commenter stated some states, such as California, had guidelines on sea level rise and those guidelines were inconsistent with the CISA +5 feet option discussed in the rule's regulatory impact analysis. The commenter stated such an elevation requirement would be overbuilt per those State guidelines. The commenter stated that CISA would be overly conservative for many locations, because of what the commenter characterized as CISA's one-size-fits-all approach.

FEMA Response: FEMA's regulatory impact analysis utilizes an assumption of +5 feet for CISA as an analysis point. The +5 feet is an assumption because FEMA does not currently have detailed enough data to estimate the average CISA level within the United States based on currently available CISA data and the additional CISA data that will Start Printed Page 56959 continue to become available over time. However, CISA is not a one-size-fits-all approach. FEMA notes the FFRMS Floodplain Determination Job Aid indicates the CISA method is recommended for actions along low-lying coastal shorelines on the Atlantic and Gulf Coasts. For Pacific coasts and other coasts with bluffs, FEMA may initially use the FVA approach.

SLTTs can provide input into the determination. Pursuant to 44 CFR 9.11(d)(6) , a more restrictive Federal, State, or local standard will be used, including local CISA data and methods that have been adopted by a community for use in floodplain management, as long as such data result in a more restrictive standard.

FEMA's FFRMS policy is not a one-size-fits-all approach; rather, the agency's policy approach is flexible to address criticality of the action being taken, data availability based on the location of the action, and equity concerns. FEMA is not codifying the specific climate scenarios to be used as part of the CISA analysis. As previously explained, FEMA is relying on interagency tools to determine CISA flood elevations and corresponding horizontal floodplains. FEMA will initially implement this final rule using the FFRMS Job Aid that published in the public docket associated with this rulemaking along with the proposed rule. The FFRMS Job Aid is also on FEMA's website. [ 169 ]

Comment: The same commenter stated that when designing bridges and embankments, the CISA approach considers impacts from projected land cover/land use changes, long-term erosion, and other processes that may alter flood hazards over the lifecycle of the Federal investment. The commenter asked how the estimates for long-term erosion and scour would be determined. This commenter further stated the outcomes from these estimates were subject to uncertainty, resulting in overdesign and greatly reducing the likelihood of the CISA data actually occurring.

FEMA Response: FEMA's FFRMS policy provides details on how FEMA will implement FFRMS for facilities. This analysis is completed on a case-by-case basis and may require the services of a professional engineer, as appropriate, consistent with FEMA program requirements. More information on consideration of flood characteristics such as erosion and scour can be found in the Revised Guidelines. [ 170 ]

Whether CISA data are available and/or actionable will depend in part upon the location of the action being taken. FEMA believes the policy approach detailed in the agency's FFRMS policy is sufficiently certain for FFRMS implementation. As detailed in the FFRMS policy, FEMA will use the CISA where such data is available and actionable. FEMA is relying on interagency tools to determine CISA flood elevations and corresponding horizontal floodplains. Where the CISA data are not available and actionable, the agency will leverage either the FVA or 0.2PFA depending on the criticality of the action and data availability. Where the CISA data are available and actionable, the CISA floodplain must be at least as restrictive as the 1 percent annual chance flood elevation or 0.2PFA, again depending on the criticality of the action. In this way, FEMA has addressed equity concerns in the policy approach, specifically to mitigate the likelihood of over- and under-building. FEMA believes that allowing for a lower standard for non-critical actions helps address concerns related to overbuilding. Selecting the lower approach for non-critical actions will still result in a higher level of resilience than the current requirements under part 9 while also taking equity and cost-effectiveness considerations into account.

Comment: A commenter requested FEMA apply the CISA to all of the agency's mapping and map revision processes. The commentor wrote that letters of map amendment (LOMAs) and letters of map revision-based on fill (LOMR-Fs) essentially allowed FEMA to piecemeal exempt properties and stated the combination of Executive Orders and statutes required FEMA to build a robust and well-informed mapping program to guide development away from floodplains. The commenter stated the exclusion of LOMAs and LOMR-Fs from FFRMS created an exception that would swallow the rule.

FEMA Response: FEMA appreciates the commenter's support of the CISA and understands the commenter's concerns regarding LOMAs and LOMR-Fs. FEMA is not making changes to the agency's NFIP mapping process with this rulemaking or accompany FFRMS policy. The NFIP's regulations on mapping and changes to FEMA maps are found at 44 CFR part 70 et seq. Further, the proposed changes to part 9 do not affect implementation of the NFIP's floodplain management regulations. Those regulations are found at 44 CFR part 59 et seq. The framework that FEMA uses in part 9, including the revised definition of floodplain applicable to actions subject to the FFRMS under this rule, is distinct from NFIP mapping. FEMA believes that the flexibility outlined in 44 CFR 9.7 and the practice of best available information will allow the application of part 9 to adjust to any future change made in the NFIP mapping process.

Comment: A commenter requested FEMA consider inequities in access to the best available climate science as some communities may not have access to the CISA data. The commenter acknowledged FEMA's proposed alternatives to the CISA but requested the agency consider how this rule would unintentionally exacerbate inequities in flood preparedness and safety across the country and how FEMA would distribute Federal funding and other financial assistance to address these discrepancies.

FEMA Response: FEMA's revisions to part 9 reflect consideration of the type and criticality of the action involved, the availability and actionability of the data, and equity concerns in the implementation of Executive Order 11988 , as amended. FEMA also has an agency-wide initiative focused on reducing barriers and increasing opportunities so all people, including those from vulnerable and underserved communities, can get help when they need it. [ 171 ] FEMA notes any increased costs are generally eligible for funding under FEMA's assistance programs subject to cost share requirements.

As part of the implementation cost, FEMA will publicize the FFRMS to public and SLTT partners, identifying what the FFRMS is and how the agency will implement the Executive Order as amended and part 9. These resources will help applicants applying for FEMA-funded assistance programs. FEMA's regional offices will also provide technical assistance in support of FFRMS implementation.

As climate science data continues to be advanced, FEMA will continue to rely on 44 CFR 9.7 , FEMA Policy 104-008-2: Guidance on the Use of Start Printed Page 56960 Available Flood Hazard Information, [ 172 ] and the Revised Guidelines in determining whether CISA and flood hazard data is available and actionable. Appendix H of the Revised Guidelines and the CISA FFRMS State of the Science Report provide an overview of the available and actionable data for CISA, which is the basis for these interagency supporting tools. The Revised Guidelines also provide an explanation of how the FFRMS will be updated in the future. Additionally, where a community does have access to CISA data and has adopted its use for floodplain management, that data will be used pursuant to 44 CFR 9.11(d)(6) , as long as it results in a more restrictive standard. In this way the unique considerations of a particular community are also taken into account.

Comment: A commenter stated FEMA should be prepared to reassess the use of 2 and 3 feet of freeboard in the FVA according to the latest climate science. The commenter requested the FFRMS should explicitly allow this type of reassessment to take place without rulemaking.

FEMA Response: The FVA is an alternative approach to the CISA under the FFRMS. FEMA cannot independently revise the FFRMS. The MitFLG in consultation with the FIFM-TF will reassess the FFRMS annually, after seeking stakeholder input, and provide recommendations to the WRC to update the FFRMS, including the FVA, if warranted based on accurate and actionable science that takes into account changes to climate and other changes in flood risk. The WRC shall issue an update to the FFRMS at least every 5 years. [ 173 ]

FEMA appreciates the intent behind the comment, namely that the agency should implement the FFRMS in a way that allows for reassessments that account for changes in climate science. FEMA has ensured that its implementation of the FFRMS will allow for such updates. Specifically, in this final rule, FEMA will implement the FFRMS by adopting the flexible framework identified in Executive Order 11988 , as amended by Executive Order 13690 , in its entirety, instead of mandating a particular approach in its regulations and will provide additional guidance (more readily capable of revisions and updates) that addresses which approach FEMA would generally use for different types of actions. Consistent with Executive Order 11988 , as amended, and the Revised Guidelines, the CISA requirements will change as the available and actionable data change and FEMA will similarly update its guidance, as appropriate, to account for such changes.

Comments: Commenters asked questions about the 0.2PFA and how FEMA would implement the approach. A commenter expressed support for the use of the 0.2PFA as an effective alternative to the CISA while technology and capabilities to implement CISA are scaling to a nationwide level. At the same time, the commenter recommended that FEMA allow for the flexibility to use the most protective and up-to-date science in coastal regions or where higher quality data and analytics are available. The same commenter wrote that FEMA should continue educating the public regarding flood risk from flood events that could affect areas beyond the 0.2 percent annual chance floodplains. The commenter stated that during the past two decades, many storm events of a magnitude greater than a 0.2PFA event have occurred, such as the 2010 Nashville flood and the 2017 inland flood induced by Hurricane Harvey. The commenter stated that while reliance on the 0.2PFA would significantly reduce flood risk in comparison to reliance upon the 1 percent annual chance floodplain, FEMA should not be satisfied that this would be sufficient. The commenter also requested FEMA include land surface flooding. The commenter also recommended the flood mitigation standard for critical infrastructure (such as subway systems, metropolitan wastewater treatment facilities, and others) be different and higher than those for non-critical. Another commenter requested FEMA account for the area of elevation that was above or below sea level to plan for implementation of the 0.2PFA.

FEMA Response: FEMA's policy approach provides flexibility. As explained in the FFRMS policy, FEMA will use the CISA to determine the floodplain where that data is available and actionable. Where the CISA data is not available or actionable, FEMA will utilize either the FVA or 0.2PFA depending on the criticality of the action and data availability. FEMA notes there is no requirement in the FFRMS or the Revised Guidelines to select the higher approach when not using the CISA, as FFRMS is a resilience standard. “When an agency is not using the Climate-informed Science Approach in riverine flood hazard areas, the agency may select either the Freeboard Value Approach or the 0.2-percent-annual chance elevation, as appropriate, and is not required to use the higher of the two.”  [ 174 ]

FEMA will continue to rely on 44 CFR 9.7 , FEMA Policy 104-008-2: Guidance on the Use of Available Flood Hazard Information, [ 175 ] and the Revised Guidelines in determining whether CISA and flood hazard data is available and actionable. FEMA will use the best available information in making the floodplain determination under part 9, and the best available information may include information that is non-regulatory or FEMA preliminary flood hazard data. To be designated as the best available information, it must be at least as restrictive as information provided by effective FIRMs. Pursuant to 44 CFR 9.11(d)(6) , a more restrictive Federal, State, or local standard will be used and this includes the use of local CISA data and methods that have been adopted by a community for use in floodplain management, as long as such data results in a more restrictive standard.

To clarify, FEMA is not relying on the 1 percent annual chance floodplain in the FFRMS approaches. Rather, FEMA is relying on the CISA, FVA, or 0.2PFA. FEMA's FFRMS policy clarifies the agency will use the higher of the FVA or 0.2PFA for critical actions when CISA data is not available or actionable. FEMA will continue to utilize the 1 percent annual chance floodplain under part 9 only for those actions that are not subject to the FFRMS and are considered non-critical actions.

FEMA has considered and will continue to consider flooding characteristics such as land surface flooding consistent with § 9.7. FEMA's FFRMS policy also emphasizes whether the action is a critical action as one of the factors to consider when conducting the analysis as to the approach to utilize when CISA data is not available or actionable.

Regarding the commenter's concerns about elevation, the interagency tools FEMA will use to determine the 0.2PFA, as well as CISA and FVA, will account for ground elevation.

Comment: One commenter wrote only 20 percent of the country had detailed horizontal floodplain boundaries of the 0.2 percent annual chance floodplain Start Printed Page 56961 and that the elevation determination was also important given that some flood depths could be lower in the 0.2 annual chance floodplain than in the 1 percent annual chance floodplain. A commenter stated the lack of comprehensive elevation information for the 0.2PFA would cause confusion among stakeholders and applying FFRMS without accounting for distinct elevation profiles undermined the practicality and success of the policy. Another commenter supported utilizing the 0.2PFA and FVA when the CISA data was not available and not actionable. The commenter noted wave modeling should be included when applying the 0.2PFA and FEMA had not regularly produced maps that incorporate wave modeling. The commenter requested FEMA regularly include wave modeling in its 0.2 percent annual chance flood maps.

FEMA Response: As explained above, FEMA's FFRMS policy identifies data availability as a factor in determining the FFRMS approach to be used for a specific action. FEMA recognizes data availability of the 0.2 percent annual chance floodplain, as well as technical considerations relating to how wave action may be incorporated, can be challenges in implementing the 0.2PFA. In coastal areas, the Revised Guidelines note Federal agencies should use the FVA as the minimum elevation when not using the CISA if the 0.2 percent annual chance flood information depicted on FEMA's regulatory products considers storm-surge hazards but not wave action, and wave action data cannot be obtained from other sources.

As the commenter notes, when the CISA is not available and the 0.2PFA is used in coastal areas, the 0.2PFA should consider wave action. As the Revised Guidelines state, before using the 0.2PFA in that situation, an analysis should be conducted of coastal flood hazards at the site that incorporates the local effects of wave action, scour and erosion, wave run-up, and overtopping. [ 176 ] In some instances, the FEMA 0.2 percent annual chance flood elevation, which does not consider wave action, will be lower than the current BFE or the FVA. As noted in the Executive Summary of this preamble, FEMA edited the agency's proposed FFRMS policy to clarify that FIRMs and Federal Insurance Studies (FIS) provide 1 percent annual chance flood elevations including wave action in coastal areas; however, the 0.2 percent annual chance flood elevations generally are stillwater elevations that do not account for the effects of wave action. To emphasize the importance of this for non-critical actions in particular, the FFRMS policy wording has been clarified and relocated to Section C.3.a, stating that when the lower of the 0.2PFA or FVA is used, the FVA flood elevation must be used in those instances where the 0.2-percent-annual-chance flood elevation does not account for the effects of wave action. [ 177 ] For critical actions, the policy approach is to use the higher of the FVA or 0.2PFA, which would avoid relying on 0.2PFA in situations where the 0.2PFA elevations would be lower.

Comment: A commenter stated the fourth approach listed in the rule was a “hedge” and resulted in inexcusable operational uncertainty to the FFRMS. The commenter stated the public would struggle to understand the appropriate standard on an annual basis given this approach. Another commenter stated the fourth approach was a “safety net” and consistent with the other commenter, stated the approach amplified operational uncertainty within FFRMS rather than addressing it.

FEMA Response: FEMA disagrees that the fourth approach in the regulation provides additional uncertainty for the public. This approach is provided in the Revised Guidelines, and FEMA would provide notice to the public of any such approach and the adoption of that approach consistent with Executive Order 11988 , as amended.

Comment: One commenter suggested that cost-benefit analysis could serve as an alternative to using the FFRMS approaches. The commenter stated cost-benefit analysis informed by risk could be scaled to the circumstances of decisions and would achieve better results than applying error-prone arbitrary standards. The commenter stated that benefits and costs can be broadly conceived to include more than values reflected in market transactions. The commenter wrote that FEMA applied cost-benefit analysis in a partial way to its hazard mitigation program only and asked how not leveraging a cost-benefit analysis but instead applying the FFRMS approaches would result in net Federal resource savings.

FEMA Response: As an initial matter, FEMA notes that establishing the floodplain for each project on the basis of individualized cost-benefit assessments would potentially be inconsistent with the commenter's stated preference for predictability and reduced uncertainty (as reflected in the commenter's objection to the CISA standard). For instance, the commenter's proposal could require individualized flood risk assessments that would make it challenging for private parties to predict the applicable floodplain prior to engaging with FEMA. In addition, in at least some cases, the commenter's proposed approach would call for consideration of relevant data and science in order to understand the potential costs and benefits of building to different levels of resilience. Although as reflected throughout this response and preamble, FEMA shares the commenter's sensitivity to cost and preference to limit unnecessary expenditures to the extent possible, FEMA does not believe that the approach suggested by the commenter is necessarily more likely to be predictable or administrable, or to maximize net benefits.

While not all of FEMA's programs are statutorily required to be cost-effective, FEMA has consistently leveraged cost-benefit analysis and will continue to do so along with minimum standards for floodplain management across the agency's programs to provide for Federally funded projects that are both cost-effective and result in more resilient communities.

In its NPRM and proposed policy, FEMA explained how the agency considered cost along with data availability, criticality of the action, and equity in establishing a flexible framework for FFRMS implementation. Consistent with the Revised Guidelines, FEMA's preferred approach is the CISA, but the FFRMS policy explains the CISA must be available and actionable and where it is not, the FVA or 0.2PFA will be utilized depending on the criticality of the action and availability of data.

FEMA believes the benefits of preventing property damage and potentially saving lives justify the costs of the rule. These benefits are a result of the improved protection of structures due to increased elevation and floodproofing standards in FEMA's implementation of the FFRMS. This rule will help to ensure that Federal investments are better protected from flood damage, and the natural values of floodplains are preserved. If, in the future, the commenter were to identify a specific cost-benefit methodology that warranted adoption via the process outlined in the Executive Order, FEMA could in principle pursue such an option.

Comments: Some commenters recommended FEMA adopt specific building codes and design standards as part of this rulemaking. One commenter Start Printed Page 56962 stated FEMA's rule was consistent with ASCE Policy Statement 421. The commenter recommended FEMA adopt both the current 2022 edition of ASCE 7 as well as Supplement #1 and Supplement #2 for the Flood Chapter, and the upcoming revision to ASCE 24. Another commenter recommended FEMA require up-to-date editions of the International Residential Code (IRC) and International Building Code (IBC) to ensure the FFRMS incorporates the most stringent flood provisions for Federally assisted construction in flood zones. Another commenter also recommended FEMA specifically adopt a reference to the ANSI/FM Approvals 2510 standard for floodproofing/flood mitigation products, similar to the U.S. Department of Housing and Urban Development (HUD)'s proposal to allow floodproofing of non-residential areas below the FFRMS floodplain elevation in their NPRM.

FEMA Response: FEMA appreciates the commenter's concerns and notes the agency does implement specific codes and standards through grant program policies and requirements. [ 178 ] However, the scope of this rule is limited to implementation of FFRMS consistent with Executive Order 11988 , as amended, and the Revised Guidelines; FEMA did not propose to adopt specific building codes and standards in the NPRM. FEMA may, however, clarify the use of such standards through additional guidance.

FEMA adopted a Building Codes Strategy  [ 179 ] in March 2022 that focuses on leveraging partnerships to promote current hazard resistant building codes; understanding stakeholder needs to identify opportunities that advance building code adoption and enforcement; amplifying climate science messaging to increase public demand for building codes and standards; and targeting building code adoption outreach to the most vulnerable communities to achieve a more resilient nation. FEMA believes the changes made in this final rule and the FFRMS policy will further this strategy without mandating specific codes and standards in the regulatory text. FEMA will continue to review and update the agency's policies and guidance regarding codes and standards to ensure the agency is promoting use of the standards consistent with FEMA program requirements.

FEMA appreciates the commenter's request that the agency mirror HUD's proposal to allow floodproofing of non-residential structures below the FFRMS flood elevation. FEMA already allows for floodproofing of non-residential structures below the floodplain in 44 CFR 9.11(d)(3) and will continue to allow floodproofing below the FFRMS flood elevation. No changes to the regulatory text are required to achieve this result.

Comments: Commenters offered support for the edits proposed to § 9.7 and the accompanying proposed FFRMS policy document to implement FFRMS. Commenters also stated specific support for FEMA's policy decision to prioritize the use of CISA when determining the FFRMS floodplain for actions subject to the FFRMS. Commenters were also generally supportive of FEMA's approach to utilize either the FVA or 0.2PFA where CISA data was not available or not actionable.

FEMA Response: FEMA appreciates the commenter's agreement with the general policy approach detailed in FEMA's FFRMS policy and the agency is finalizing that policy approach with the publication of this final rule. FEMA notes the revisions made to part 9 apply only to FEMA projects and not all Federally funded projects as some commenters suggested. All Federal agencies will utilize the Revised Guidelines for their own FFRMS implementation.

Comment: One commenter wrote in support of the revisions to § 9.7. The commenter stated that a recent TMAC report indicated that existing 1 percent and 0.2 percent annual chance floodplains were insufficient for informing land use practices and stated the use of CISA aligned with TMAC's principle to use a climate-informed map for floodplain management, separate from the 1 percent annual chance map used for NFIP mandatory purchase and other regulatory requirements.

FEMA Response: FEMA appreciates the commenter's support of the agency's preferred approach and the clarifications made in § 9.7 as part of this final rule. Executive Order 11988 , as amended, and the FFRMS reinforce the importance of avoiding adverse impacts associated with actions in or affecting a floodplain and minimizing potential harm if an action must be located in a floodplain. As amended, Executive Order 11988 directs agencies to use a higher vertical flood elevation and corresponding horizontal floodplain than that of the base flood for Federally funded projects to address current and future flood risk and help ensure that projects last as long as intended. FEMA appreciates the commenter's reference to the recent TMAC recommendations, but notes TMAC recommendations are not binding on FEMA and relate directly to the NFIP, not necessarily to part 9 and this final rule.

Comment: One commenter was not supportive of FFRMS, stating that a national “one-size-fits-all” approach that lacked flexibility to address specific regional and local circumstances and needs and a uniform strategy would not adequately address the nuanced and varied nature of flood dynamics. The commenter wrote that without tailored considerations for regional variations, FFRMS overlooked critical factors, risking inconsistency and inefficiency in flood management efforts.

FEMA Response: The FFRMS is a resilience standard with flexibility in the approach selected to meet the standard. FEMA's FFRMS policy explains how the agency selects the FFRMS approach to use for each project and is not a “one-size-fits-all” policy. The FFRMS policy is flexible to address data availability based on the location of the action, criticality of the action being taken, and equity concerns and allows consideration of regional variations and community concerns.

SLTTs can provide input into the floodplain determination. Pursuant to 44 CFR 9.11(d)(6) , a more restrictive Federal, State, or local standard will be used. This includes the use of local CISA data and methods that have been adopted by a community for use in floodplain management, as long as such data result in a more restrictive standard. FEMA values additional input from SLTT partners and the public throughout the 8-step process.

Comment: Another commenter also opposed FFRMS, stating that the approaches based on elevation and areal extent determined by flood elevations across the watershed were subject to availability heuristic bias. The commenter stated that higher is not always better and that FFRMS did not consider whether the standard was prone to error and therefore introduced Start Printed Page 56963 new risks, including the risk that FFRMS would impose more costs than it achieves in benefits. The commenter stated FEMA acknowledged the proposed standard would make errors and, in some cases, imposed costs greater than anything it prevented or saved. The commenter recommended that FEMA test its new standard in proposed use cases to determine where the standard would make errors. The commenter recommended that where the probability and consequences of errors from using the standard were significant, the agency should resort to detailed cost-benefit analysis. The commenter recommended that the FFRMS be formulated with reference to alternatives and cost-benefit analysis, stating the public deserves some clarity about when FFRMS applies and when it did not.

FEMA Response: FEMA disagrees with the commenter that the agency is assuming higher is universally better. There is no requirement in the FFRMS or the Revised Guidelines to select the most restrictive standard, as FFRMS is a resilience standard. The Revised Guidelines state “[w]hen an agency is not using the Climate-informed Science Approach in riverine flood hazard areas, the agency may select either the Freeboard Value Approach or the 0.2-percent-annual chance elevation, as appropriate, and is not required to use the higher of the two.”  [ 180 ] In some instances, building to a higher elevation may lead to overbuilding and thus not be the most cost-effective, equitable approach particularly for non-critical actions. FEMA believes its proposed approach to use the CISA, and to utilize the lower of the FVA or 0.2PFA where the CISA is not available and actionable, reflects appropriate sensitivity to cost and risk.

Further, the revisions to part 9 do not change FEMA's long-standing requirement as part of implementing Executive Order 11988 , as amended, to only perform or fund actions within or affecting floodplains if those actions are the only practicable alternative. Through the 8-step process, FEMA will consider alternative locations, alternative actions, nature-based solutions, and the no action alternative under the practicability analysis. If there is no practicable alternative, FEMA will perform or fund the action and will minimize any adverse impacts when doing so.

Regarding clarity on the application of FFRMS, FEMA defines “action subject to the FFRMS” as “any action where FEMA funds are used for new construction, substantial improvement, or to address substantial damage to a structure or facility.” The FFRMS applies to grants for projects funding the new construction, substantial improvement, or repair of substantial damage under FEMA programs such as IA, PA, and HMA programs, and grants processed by FEMA's GPD. FFRMS applies only to Federal actions and this rule only applies to those actions FEMA takes using Federal funding. This rulemaking is generally not expected to negatively impact individuals and their ability to pay. Where applicable, any increased costs associated with this rulemaking would be subject to cost share requirements for FEMA's programs.

FEMA also disagrees with the commenter that the agency acknowledged the FFRMS would create errors and would impose costs greater than anything the standard would prevent or save. FEMA believes the benefits of preventing property damage and potentially saving lives justify the costs of the rule. These benefits are a result of the improved protection of structures and facilities due to increased elevation and floodproofing standards in FEMA's implementation of the FFRMS. This rule will improve the resilience of Federal investments to be better protected from flood damage and promote preservation of the natural and beneficial values of floodplains.

FEMA believes the regulatory impact analysis was sufficiently detailed to analyze the FFRMS approaches in general, as the RIA itself was not intended to analyze the costs and benefits of applying the FFRMS standards to specific use cases. FEMA conducted an analysis to create a range of the potential impacts. FEMA does not know how many projects will be subject to the FVA, 0.2PFA, or CISA requirements over the 10-year period as FEMA anticipates it to continually change. Therefore, FEMA has analyzed the impact of FVA, 0.2PFA and CISA for each of the programs, PA, IA, and HMA as if each were the only FFRMS expansion option. Evaluation of the practicability of certain FFRMS standards in the context of specific use cases occurs as part of the 8-step process, and to the extent that FEMA finds certain approaches to be incompatible with practicable implementation in certain cases, FEMA may issue further guidance on the topic. In general, however, commenters did not identify categories of actions for which application the FFRMS approaches appears likely to be particularly problematic.

While FEMA could not quantify the costs and benefits of several aspects of this rule, FEMA was able to quantify the number of structures and facilities that would be impacted by the rule. FEMA was transparent about its inability to quantify the costs and benefits of several aspects of the rule. FEMA provided a literature review of relevant benefits that could be realized from flood mitigation, an analysis of benefits quantified for the rule, and a qualitative description of additional benefits that could be realized from the rule. FEMA conducted a quantitative cost-benefit analysis based on the data available.

Comments: Commenters were generally supportive of FEMA's policy approach to utilize the higher of the FVA or 0.2PFA for critical actions where CISA data was not available and/or actionable. Some of these commenters, however, expressed concerns with utilizing the lower of the FVA or 0.2PFA for non-critical actions where CISA data was not available and not actionable. Several of these commenters inaccurately stated policy positions on the FFRMS approaches selected by other Federal agencies for non-critical actions.

Commenters requested that FEMA adopt the higher of the FVA or 0.2PFA for non-critical actions where CISA data was not available and not actionable. Commenters stated that FEMA's policy decision to utilize the lower standard would undermine the urgent need to design development proposals to a more resilient standard and minimize overall impacts to the floodplain. In response to FEMA's statements in the NPRM regarding concerns with overbuilding and inequitable outcomes that may not be cost-effective, a commenter noted that FEMA has consistently advocated for states and localities to embrace stricter standards such as updated building codes that can have similar cost implications. Commenters also wrote that upfront investments in resilient development produced significant cost savings to communities in the long run and stated that the cost of construction was not the only consideration for costs, particularly for housing. These commenters requested FEMA consider the higher standard for non-critical actions, stating that the long-term benefits would outweigh the costs.

FEMA Response: As explained above, there is no requirement in the FFRMS or the Revised Guidelines to select the most restrictive standard, as FFRMS is Start Printed Page 56964 a resilience standard. The Revised Guidelines state “[w]hen an agency is not using the Climate-informed Science Approach in riverine flood hazard areas, the agency may select either the Freeboard Value Approach or the 0.2-percent-annual chance elevation, as appropriate, and is not required to use the higher of the two.”  [ 181 ] While the approach the commenters suggested would ensure that applicants were building all actions to the most protective level where CISA data is not available, this approach may lead to overbuilding and thus not be the most cost-effective, equitable approach particularly for non-critical actions. FEMA believes the agency's approach is sufficiently protective of all actions and would be less expensive and complex to administer and implement than the commenters' approach.

FEMA did consider the long-term costs and benefits of the rulemaking and policy and does not agree with the commenters that FEMA's policy approach would result in inequities. Rather, FEMA believes the policy approach is appropriate as it will help ensure communities can rebound quickly and effectively from a disaster.

Comments: Other commenters requested FEMA require the use of the more protective standard for non-critical actions to better align with HUD's proposed rule to implement the FFRMS. Several of those commenters stated that aligning with HUD's approach would reduce conflicts and delays. One commenter stated that FEMA's approach to use a lower elevation for non-critical projects facilitated a beneficial benefit/cost ratio. That commenter stated the higher standard should not be overly burdensome and consistent with another commenter noted the cost of construction was not the only consideration for costs, particularly for housing.

FEMA Response: As explained above, there is no requirement in the FFRMS or the Revised Guidelines to select the most restrictive standard, as FFRMS is a resilience standard. While the approach the commenter suggested would ensure applicants were building all actions to the most protective level where CISA data is not available, this approach may lead to overbuilding and thus not be the most cost-effective, equitable approach, particularly for non-critical actions. FEMA believes the agency's approach is sufficiently protective of all actions and would be less expensive and complex to administer and implement than the commenter's approach.

While HUD's rule would require all proposed actions that require an Environmental Impact Statement (EIS) under NEPA to define the FFRMS floodplain using CISA, FEMA does not believe it is appropriate to require CISA in every instance where an EIS is required. FEMA cannot utilize CISA if CISA data is not available and actionable even if an action requires an EIS. Where CISA data is both available and actionable, FEMA will require CISA, including for those proposed actions that require an EIS.

HUD proposed to use the CISA to determine the FFRMS floodplain where the data is available and actionable. For non-critical actions where CISA is unavailable, HUD will use the 0.2PFA. Where the 0.2PFA is also unavailable for non-critical actions, HUD will use the FVA. For critical actions where CISA is unavailable, HUD will use either the 0.2PFA or the FVA to determine the FFRMS floodplain, whichever results in the larger floodplain and higher elevation. The only significant difference between HUD's policy approach and FEMA's is that HUD will first use the 0.2PFA for non-critical actions where it is available, but the CISA is not, and FEMA will use the lower of the 0.2PFA and the FVA for non-critical actions where CISA is not available.

FEMA considered requiring the use of the 0.2PFA when CISA is not available for non-critical actions rather than the lower of the 0.2PFA or FVA. While application of the 0.2PFA may provide a more consistent reduction of flood risk as it is probability based, the relationship to the FVA varies depending on topography ( i.e., in some instances the 0.2PFA may result in a lower flood elevation than the FVA). Application of only the 0.2PFA without a comparison to the FVA may result in building to a higher resilience standard than is necessary. There could also be equity concerns related to underbuilding or overbuilding to this standard, as communities seek to rebound quickly and effectively from a disaster. Data availability of the 0.2 percent annual chance floodplain can also be a challenge in implementing the 0.2PFA, as well as technical considerations relating to how wave action may be incorporated. In coastal areas, the Revised Guidelines note Federal agencies should use the FVA as the minimum elevation when not using the CISA if the 0.2 percent annual chance flood information depicted on FEMA's regulatory products considers storm-surge hazards but not wave action and wave action data cannot be obtained from other sources. Only some of those coastal areas have included wave action in the computation of the 0.2 percent annual chance floodplain.

FEMA's FFRMS policy provides details on how FEMA will coordinate with other agencies when implementing actions in the same area as another Federal agency. See Section H, page 9. FEMA's interagency consultative role in the broader implementation of the FFRMS across the Federal government, through the agency's participation in the Interagency Working Groups and the FIFM-TF helps ensure consistent and effective implementation.

FEMA agrees with the commenter that equity is an important consideration and FEMA incorporated equity into the agency's policy approach as explained above. Equity was a primary consideration for FEMA's policy approach, not a desire to achieve a better benefit-cost ratio for non-critical actions as the commenter suggests. FEMA did consider the long-term costs and benefits of the rulemaking and policy and does not agree with the commenters that the policy approach would result in inequities. Rather, FEMA believes the policy approach is appropriate as it will help ensure communities seeking to rebound quickly and effectively from a disaster may do so.

Comment: One commenter also stated using the less restrictive standard could result in greater impacts on floodplains, ESA-listed species, Tribal treaty rights, and realized costs to vulnerable communities. The commenter stated using the higher standard between FVA or 0.2PFA when CISA data was not available and not actionable would not only prevent impacts on floodplains but would also avoid a similar situation that required expensive infrastructure upgrades and government liability after poorly located initial development within floodplains.

FEMA Response: As explained above, there is no requirement in the FFRMS or the Revised Guidelines to select the most restrictive standard, as FFRMS is a resilience standard. While the approach the commenter suggested would ensure applicants were building all actions to the most protective level where CISA data is not available, this approach may lead to overbuilding and thus not be the most cost-effective, equitable approach particularly for non-critical actions. FEMA believes the agency's approach is sufficiently protective of all actions and would be less expensive and complex to administer and implement than the commenter's approach.

A more restrictive application of the FVA or 0.2PFA would not necessarily Start Printed Page 56965 determine whether an action will impact a protected species or critical habitat or impact Tribal treaty rights. In step 4 of the 8-step process, FEMA determines impacts to the floodplain which include changes to the hydraulics and hydrology of the floodplain which informs on potential impacts to protected species and their critical habitats. FEMA will also perform Section 7 consultation under the Endangered Species Act where appropriate.

Comments: Two commenters provided feedback on FEMA's specific request for comment on requiring the highest elevation for all actions regardless of criticality. One commenter noted FEMA's policy approach was flexible and acknowledged the need to be flexible and design an approach that would not unduly burden communities. The commenter recommended that FEMA continue to evaluate these approaches and consider revising and strengthening the standards if the standards become insufficiently protective. The other commenter stated that completing the required floodplain analysis for any one of the approaches would be challenging on its own and to require the analysis and consideration of all three would be costly and might not yield results materially different from the CISA. The commenter stated that because CISA would result in a determination of the appropriate level of resilience to design minimization measures, it would be unnecessary to require the use of the highest standard for all actions. The commenter stated that such an approach would be costly and, in some instances, would result in projects being built to higher resilience levels than required. This commenter supported FEMA's policy approach for critical actions as separate and apart from other actions, stating by separating critical actions from others, FEMA would be able to properly balance different levels of protection with minimization and mitigation measures and cost considerations.

FEMA Response: FEMA appreciates the commenters' consideration of the alternatives and understanding of the need for a flexible approach balancing cost and equity considerations. FEMA agrees with the commenter that the use of the highest standard for all actions is not always appropriate and the FFRMS policy reflects the decision to use the lower standard for non-critical actions. FEMA intends to continue to evaluate the policy approach as FFRMS is implemented and will consider future revisions as appropriate. While FEMA understands the commenter's concern that completing the analysis for all of the approaches for every action could be an administrative burden on the agency, the agency does not believe that completing the analysis for any one of the approaches is on its own too challenging. As explained above, FEMA will use the FFRMS Job Aid to determine the FFRMS floodplain for actions, and that tool provides the agency and stakeholders with a methodology and process for completing the analysis.

Comment: Two commenters wrote that FEMA artificially constrained the agency's consideration of alternatives to just the three disclosed regulatory approaches in the proposal and did not consider no regulatory action as an alternative. One of the commenters added that FEMA did not assess how private and non-Federal interests would adapt to flooding without regulation and the no regulation alternative likely understated flood adaptation, which resulted in the cost-benefit analysis overstating the benefits of the three regulatory alternatives. The commenter also wrote the true value of cost-benefit analysis is nearly always realized when alternatives are identified that achieve substantial benefits and at much less cost than much higher levels of regulation. The commenter stated that FEMA could have analyzed other alternatives, such as strategic choices of use-case subsets for application of the various FEMA standards rather than all use-cases being subject to CISA. The commenter further stated that the FVA or 0.2PFA entail much lower analysis costs and are probably better suited to decisions where the costs of the structures or costs of adaptation were lower. The commenter stated avoiding the CISA in those situations might result in substantial cost savings.

FEMA Response: FEMA's policy approach detailed in the NPRM preamble explains how the agency balanced consideration of costs with data availability, criticality of the action, and equity in establishing a flexible framework for FFRMS implementation. Consistent with the Revised Guidelines, FEMA's preferred approach is the CISA, but the FFRMS policy explains the CISA must be available and actionable and where it is not, the FVA or 0.2PFA will be utilized depending on the criticality of the action and availability of data. The CISA is FEMA's preferred approach, as FEMA believes it has the potential to be the best and most well-informed approach to building resilience in an equitable manner and ensuring a reduction in disaster-related suffering. CISA is designed to meet current and future estimates of flood risks unique to the location and thus provide the best overall resilience, cost effectiveness, and equity. FEMA understands the availability and actionability of data are key factors in completing the RIA in a consistent, equitable manner and believes data availability and actionability will continue to advance for the CISA. In response to the commenter's concerns that FEMA did not assess how private and non-Federal interests would adapt to flooding without regulation, FEMA notes that this regulation would not regulate purely privately funded activity in the floodplain. To the extent that private incentives exist to plan for increased flood risk, those incentives are substantially diluted by the use of FEMA assistance to support projects. FEMA thus did not understate private incentives to plan for flood risk and did not overstate the benefits of the regulatory alternatives.

FEMA's policy approach includes consideration of the alternatives as part of the framework explained above. FEMA intends to continue to evaluate the policy approach as FFRMS is implemented and will consider future revisions as appropriate. Additionally, FEMA's RIA does analyze all three approaches, as well as the no action alternative the commenter references. Under the No Action alternative, although non-Federal jurisdictions or private entities may continue to adapt to the future risk of flooding over time, the current Federal standards would remain. To the extent that private incentives exist to plan for increased flood risk, those incentives are substantially diluted by the use of FEMA assistance to support projects. Accordingly, such adaptation is unlikely to occur as quickly or as fully as this rule, leaving Federal investments at a greater risk of flooding than under the final rule. Because of the greater risk to structures and facilities, there is also a greater risk to life. In addition, the natural value and function of the floodplains would be at a greater risk of loss under the No Action alternative. However, the No Action alternative would initially cost incrementally less than the FFRMS approach and would result in less administrative complexity as compared to implementing the FFRMS. Overall, based on the evaluation, the FFRMS was selected over the No Action alternative for the benefits that it provides to Federal investments and those who use them.

In response to the commenter's suggestion on how FEMA should have analyzed other alternatives, such as strategic choices of use-case subsets for Start Printed Page 56966 application of the various FEMA standards rather than all-use cases being subject to CISA, FEMA did complete an analysis of all three approaches. FEMA analyzed the impact of the FVA, 0.2PFA, and CISA for each of the programs (PA, IA, and HMA) as if each approach were the only FFRMS expansion option to create a range (see sections 7.4, 7.5, and 7.6 in the RIA). In reality, it is likely that with FFRMS, there will be a mix, with some projects falling under CISA, FVA, or 0.2PFA. Therefore, the actual cost will fall somewhere within the range. FEMA selected the CISA as the primary approach, as it is the preferred option. CISA is designed to meet current and future estimates of flood risks unique to the location and thus provide the best overall resilience, cost effectiveness, and equity. As noted above, FEMA intends to continue to evaluate the policy approach as FFRMS is implemented and will consider future revisions as appropriate. Such revisions could in principle include defaulting to the FVA or 0.2PFA for smaller investments, although FEMA believes that the administrative costs associated with implementing the CISA are likely to decline over time.

Further, FEMA did consider the long-term costs and benefits of the rulemaking and policy. Rather, FEMA believes the policy approach is appropriate, as it will help ensure communities can rebound quickly and effectively from a disaster.

Comment: A commenter requested FEMA revise the proposed principle B in the FFRMS policy (“Avoid, to the extent possible, the long- and short-term adverse impacts associated with occupancy and modification of floodplains and avoid direct or indirect support of floodplain development wherever there is a practicable alternative”) to include additional language for FEMA to restore and preserve the natural and beneficial functions and values of wetlands and floodplains. Another commenter requested FEMA add a principle to the FFRMS policy and final rule specific to the restoration and preservation of the natural and beneficial functions and values of floodplains, and use of natural systems, ecosystem processes, and nature-based approaches.

FEMA Response: FEMA believes the commenters' requested revisions are unnecessary. The principles laid out in the FFRMS policy are an abbreviated version of FEMA's policy statements found in § 9.2. As stated in new § 9.2(d), FEMA shall “[r]estore and preserve the natural and beneficial values served by floodplains” and “[p]reserve and enhance the natural values of wetlands.” FEMA's longstanding requirements in 44 CFR 9.11(e) outline the agency's requirements to restore and preserve the natural and beneficial values served by floodplains and wetlands. These current requirements meet the commenters' concerns and remain unchanged in this rulemaking process.

Comment: A commenter requested other specific edits to the policy document, including adding “dry” before floodproofing throughout the document and replacing “minimization standards” with “residential flood resistant design and construction requirements.” The commenter also suggested FEMA add emphasis that nature-based solutions complement the elevation requirements versus being alternative actions and implementing a nature-based solution would not exempt an applicant from the elevation requirements.

FEMA Response: FEMA believes the current language in the FFRMS policy is sufficiently clear. FEMA believes adding “dry” before floodproofing is not necessary as floodproofing is described in detail in new § 9.11(d)(3)(ii) and section G.1.c of the FFRMS policy. Further, FEMA's policy references the use of the agency's additional resources including FEMA's NFIP Technical Bulletins that address floodproofing. [ 182 ] Using the term “minimization requirements” is consistent with the minimization provisions and minimization standards in § 9.11. The term “flood risk minimization measures” is preferred by FEMA to avoid confusion with “hazard mitigation” actions funded by FEMA.

FEMA believes that natural features and nature-based solutions should be considered as project alternatives and used where possible. Where they are not practicable as an alternative on their own, natural features and nature-based solutions may be incorporated into actions as minimization measures. The FFRMS policy clarifies the FFRMS is a resilience standard and where elevation may not be feasible or appropriate, the FFRMS floodplain establishes the level to which a structure or facility must be resilient. Resilience measures include using structural or nonstructural methods to reduce or prevent damage; elevating a structure; or, where appropriate, designing it to adapt to, withstand and rapidly recover from a flood event.

Comment: The same commenter requested several clarifications. The commenter requested FEMA clarify the requirements provided in the policy were minimum requirements not maximums and that applicants could exceed those requirements. The commenter requested FEMA clarify the policy's requirements apply regardless of whether or not substantial improvement or substantial damage is triggered and also clarify whether a structure within an FFRMS floodplain must comply with the policy's requirements.

The commenter also requested clarifications on—

  • The application of FFRMS to FEMA's benefit-cost analysis tool used by some FEMA programs;
  • whether the FFRMS policy limited where certain projects could be done, citing an example of mitigation reconstruction projects being prohibited in V Zone; and
  • what constitutes a critical action and specifically whether or not certain specific actions would be considered critical, such as construction of new safe room and stand-alone generator projects if they are supporting a critical facility.

FEMA Response: The commenter is correct that FFRMS is a minimum requirement under part 9. In section C.4 of the policy, FEMA clarifies pursuant to 44 CFR 9.11(d)(6) , a more restrictive Federal, State, or local standard will be used. Actions may follow a higher standard so long as the action complies with FEMA's program requirements.

In section A.2 of FEMA's FFRMS policy, the agency clarifies applicability of the policy to specific actions, including actions involving substantial improvement and substantial damage. FEMA does not believe the policy requires additional revision given the language in section A.2 regarding applicability. Section C of the policy explains how FEMA determines the FFRMS floodplain. Specific actions listed in section A.2 that are within the FFRMS floodplain are subject to the requirements of the policy.

FEMA appreciates the commenter's interest in the application of the Benefit-Cost Analysis (BCA) tool to the FFRMS process for FEMA programs. FFRMS does consider current and future flood risks. Where CISA is available and Start Printed Page 56967 actionable, sea level rise is specifically incorporated into the determination of the FFRMS flood elevation. FEMA's FFRMS policy will generally not change BCA requirements for FEMA programs. For FEMA's HMA program, additional elevation above the BFE incorporated into the design of the project and attributed to current and future flood risk such as sea level rise would be allowable in the BCA. Currently, pre-calculated benefits that streamline the cost-effectiveness determination for structure elevation projects are limited to structures where some part of the structure is within the SFHA. For an elevation project where the entire structure footprint is outside the SFHA, a BCA will be required to show cost-effectiveness. For FEMA's PA program, cost-effectiveness requirements apply only to Hazard Mitigation measures on projects to restore disaster damaged structures and facilities. FFRMS elevation requirements are mandated by law and therefore are eligible for financial assistance without additional cost-effectiveness analysis. FEMA notes any increased costs are generally eligible for funding under FEMA's assistance programs subject to cost share requirements.

The requirements of § 9.11(d)(1) still apply and remain unchanged in this final rule. The commenter references V Zone mitigation reconstruction projects. For V Zone actions that are new construction, FEMA is prohibited from funding such actions unless the action is functionally dependent or facilitates open space use. The HMA Program and Policy Guide also states HMA mitigation reconstruction projects are prohibited in the V Zone and in floodways  [ 183 ] and this final rule and FFRMS policy will not change that requirement. HMA mitigation reconstruction actions that are within the FFRMS floodplain must either be relocated or elevated to the FFRMS requirements.

Regarding the commenter's request for clarification on whether or not specific actions were considered critical and subject to FFRMS, FEMA cannot provide a full adjudication of whether an action is a critical action without context. FEMA makes the determination of whether an action is a critical action as part of the 8-step process on a case-by-case basis with input from the applicant. FEMA's definition of “critical action” is consistent with Executive Order 11988 , as amended, through the Implementing Guidelines and further clarified in the Revised Guidelines. The Revised Guidelines provide further details on what constitutes a critical action. FEMA will leverage the information in the Revised Guidelines when providing additional guidance to stakeholders.

As explained throughout this final rule, FEMA will publish additional resources for the public and SLTT partners identifying what the FFRMS is, and how the agency will implement the Executive Orders to help applicants of FEMA-funded assistance programs. FEMA's regional offices will also provide technical assistance in support of FFRMS implementation.

Comment: The same commenter also had several other recommendations for FEMA's FFRMS policy. The commenter recommended FEMA add an emphasis on specific codes and standards that might be applicable to specific FEMA programs, limit the dry floodproofing design to 3 feet for any new construction as recommended by NFIP Technical Bulletin 3, and cap elevation costs at the current NFIP ceiling for building coverage or the current replacement value. The commenter also suggested FEMA add information related to relocation regarding nature-based solutions, stating that instead of elevating or reconstructing in place the preference should be to relocate an action.

FEMA Response: The FFRMS policy provides information on FEMA's Building Codes Strategy and refers to specific codes and standards the agency leverages through specific program policies. FEMA does not believe additional emphasis on specific codes and standards is required in the FFRMS policy, as these are detailed in each specific program's policies. FEMA will distribute additional resources for the public and SLTT partners identifying what the FFRMS is, and how the agency will implement the Executive Orders to assist applicants of FEMA-funded assistance programs. FEMA will also provide technical assistance through the agency's regional offices in support of FFRMS implementation.

FEMA's FFRMS policy states “[e]levation and floodproofing requirements must be consistent with NFIP criteria or any more restrictive local standard.”  [ 184 ] Rather than direct quotation of a specific requirement for floodproofing design as the commenter requested, section G.1.d of the FFRMS policy addresses the use of other FEMA publications, including NFIP Technical Bulletins to assist readers.

FEMA believes the commenter's suggested funding limitations to cap elevation costs are outside the scope of this rulemaking. Applicants seeking FEMA program funding will be required to comply with that program's eligibility requirements, which may consider cost effectiveness of the proposed action.

Regarding the commenter's request to add information regarding relocation, FEMA notes this policy does not change the current requirement of step 3 of the 8-step process: “If a practicable alternative exists outside of the floodplain or wetland FEMA must locate the action at the alternative site.”

Comment: Another commenter asked if Approach 2 was only for critical actions.

FEMA Response: Approach 2 (the FVA) may be used for both critical and non-critical actions where CISA is not available and actionable. FEMA's FFRMS policy requires FEMA to determine the FFRMS floodplain according to the CISA for all locations where the best-available, actionable hydrologic and hydraulic data methods that integrate current and future changes in flooding based on climate science exist. When CISA is not available for a critical action, the FFRMS policy requires FEMA to determine the FFRMS floodplain as the area that would be inundated by the higher of the 0.2 percent annual chance flood and 3 feet of freeboard above the BFE for that location (the Freeboard Value Approach or FVA). When CISA is not available for a non-critical action, the FFRMS policy requires FEMA to determine the FFRMS floodplain as the area that would be inundated by the lower of the 0.2 percent annual chance flood and 2 feet of freeboard above the BFE for that location (the FVA). In coastal areas where CISA is unavailable, the FFRMS policy requires the FVA be used if the available 0.2 percent annual chance flood elevation does not account for wave action.

Comment: One commenter stated several links in the policy document did not appear to be active.

FEMA Response: FEMA appreciates the commenter's review of the policy document links and has confirmed the links are updated and active in the attached FFRMS policy.

Comments: Four commenters discussed the availability of the CISA data to implement the FFRMS and some of the commenters requested maps or other resources depicting the FFRMS Start Printed Page 56968 floodplain. A commenter stated there were no consistently accurate resources depicting the floodplain, floodway, the 100-year floodplain, the 500-year floodplain, or the FFRMS floodplain. The commenter stated that the floodplain determination triggered whether a proposed action was required to complete the 8-step decision-making process and the lack of FFRMS floodplain maps would create difficulty for stakeholders seeking Federal funding from FEMA for projects. The commenter stated that FEMA's work with other agencies to develop FFRMS tools and resources would help situations involving existing development but would not deter new development because the FFRMS floodplain determination would come only after the initial investments were made. The commenter added that FEMA's regulatory maps for the NFIP help stakeholders determine whether a property is located in a regulated floodplain within a short period of time and with a high degree of certainty and that the FFRMS establishes a moving, undocumented, and unmapped target that would be used haphazardly to determine the floodplain status of any given property.

Further, the commenter stated FEMA had not provided enough information on how FEMA would implement the preferred CISA approach and had not defined when data might be considered to be “available” or “actionable.” The commenter stated the regulatory text lacked information on the CISA data and FEMA's request for comment on how the CISA could be implemented using a publicly accessible, standardized, predictable, flexible, and cost-effective methodology indicated the agency was uncertain of how to apply the CISA to any given project. The commenter stated the lack of maps and other resources depicting the FFRMS floodplain made the floodplain determination susceptible to confusion, error, and potential abuse. The commenter stated FEMA rejected the use of the 0.2PFA based on data availability, costs, and certainty for stakeholders and stated concern with FEMA moving forward with the CISA, stating that approach was supported by even less data.

Conversely, a second commenter stated the necessary data and modeling capabilities underpinning CISA have continued to expand in recent years, making CISA an increasingly practicable methodology for more accurately determining the extent of the FFRMS floodplain. The commenter wrote that FEMA should emphasize developing and deploying the necessary data to support the use of the CISA more broadly and specifically consider and address how regional data limitations could result in inequitable outcomes if the CISA is routinely unavailable in low income, rural, Tribal, or otherwise underserved communities.

Two other commenters requested that FEMA provide mapping depicting the FFRMS floodplain. One commenter specifically requested mapping reflecting the CISA. One of the commenters noted the importance of mapping to identify all 3.5 million miles of floodplains associated with streams, rivers, and coastlines. This commenter recommended FEMA create maps with as much coverage as possible by considering incorporating data from areas with Base Level Engineering (BLE) in additional areas with detailed flood studies, when possible. The commenter stated this was the best way to ensure consistent, accurate CISA use.

FEMA Response: FEMA disagrees with the commenter that there are not sufficient resources depicting the floodplain, floodway, the 1 percent annual chance floodplain, or the 0.2 percent annual chance floodplain for all regions of the country. The commenter acknowledges further in their own comment that such resources currently exist for the 1 percent annual chance floodplain when stating the wide availability and certainty of FEMA's FIRMs. While regulatory mapping products may not exist depicting all of the areas referenced by the commenter, floodplain determinations under part 9 are not solely predicated on existing FIRMs. Rather, FEMA will use best available information, which may include information that is non-regulatory or FEMA preliminary flood hazard data. To be designated as the best available information, the information must be at least as restrictive as information provided by effective FIRMs per FEMA's best available information policy. [ 185 ] Given this policy, the agency will be continuously improving the data associated with the floodplain determination. FEMA's regulatory mapping products are a starting point for the floodplain determination under part 9 and any other flood information used should be at least as restrictive as those regulatory products.

Further, while there are no regulatory mapping products depicting the FFRMS floodplain, FEMA believes the information provided in the public docket with this rulemaking is sufficient to establish the FFRMS floodplain. Specifically, the FFRMS CISA State of the Science Report and the FFRMS Job Aid are resources to determine the FFRMS floodplain. Using the FFRMS Job Aid, FEMA can determine the FFRMS floodplain relevant to a particular location within approximately 23 minutes.

While FEMA appreciates that the commenter seeks to make the floodplain determinations, the agency has historically made and will continue to make floodplain determinations under part 9 by partnering with applicants in the 8-step decision-making process. FEMA will make the floodplain determination leveraging the FFRMS Job Aid published on the agency's website and in the public docket of this rulemaking. The FFRMS Job Aid is a resource for FEMA and applicants that details the methodology and process by which the FFRMS floodplain can be determined for the CISA, FVA, and 0.2PFA. FEMA further notes that the commenter's concerns regarding the floodplain determination are only a part of the analysis at Step 1 of the 8-step process. The determination in Step 1 is not just whether or not an action is located within a floodplain or wetland but is also whether the action would impact the floodplain or wetland.

FEMA will continue to rely on 44 CFR 9.7 , FEMA Policy 104-008-2: Guidance on the Use of Available Flood Hazard Information, [ 186 ] and the Revised Guidelines in determining whether CISA and flood hazard data is available and actionable. The FFRMS CISA State of the Science Report is based on the Revised Guidelines and further refines the initial framework from Appendix H to define two specific workflows for applying CISA. The FFRMS CISA State of the Science Report identifies the latest sea level rise projections from the National Climate Assessment as available and actionable data for CISA. [ 187 ] FEMA understands the commenter's concerns in seeking a simplified resource that depicts the FFRMS floodplain and is coordinating across the federal government to develop additional tools beyond the FFRMS Job Aid to assist agencies and stakeholders in determining the appropriate vertical flood elevation and corresponding horizontal FFRMS floodplain. FEMA will continue to Start Printed Page 56969 collaborate across the Federal government to develop tools to facilitate the implementation of CISA and the FFRMS. The IWG recently released a beta version of the Federal Flood Standard Support Tool (FFSST), a novel, interactive, map-based tool that incorporates new data to help users identify if a Federally funded project is in the FFRMS floodplain, for comment. [ 188 ] However, FEMA will initially rely on the FFRMS Job Aid methodology to determine the FFRMS floodplain.

The commenter incorrectly characterizes FEMA's request for comment as an indication that the agency is unable to apply the CISA. As explained above and throughout this final rule, FEMA is leveraging the resources provided in the public docket of this rulemaking to implement the FFRMS. As part of the NPRM, FEMA sought public comment to gauge the public's understanding of CISA and implementation of the FFRMS using the CISA, including locally available CISA data and methods. FEMA is collaborating across the Federal government to develop resources to further assist with FFRMS implementation beyond the FFRMS Job Aid provided in the rulemaking docket, the public comments requested will help the agency through work with the IWG to enhance the Job Aid and other interagency resources. Additionally, FEMA sought public comment to engage more dialogue on data availability and actionability beyond Federal interagency resources for FFRMS implementation.

FEMA further disagrees with the first commenter that the CISA is supported by even less data than the 0.2PFA. FEMA's policy addresses concerns regarding the availability and actionability of CISA data by offering a flexible approach to implement either the FVA or 0.2PFA where CISA data is not available and/or actionable. Further, as the policy explains, the use of both CISA and 0.2PFA are subject to data availability. While CISA is preferred, where CISA data is not available and/or actionable, the agency will rely on the alternative approaches as detailed in the FFRMS policy.

FEMA agrees with the second commenter that since the introduction of the CISA in 2015, additional data has become available to better inform the CISA. [ 189 ] FEMA believes data availability and actionability will continue to advance for the CISA in the future. Specifically, FEMA expects more data will be developed supporting broader-based application of the CISA as agencies implement the FFRMS, and this data will be considered and incorporated into future updates of the FFRMS and FEMA's implementation thereof. FEMA's policy approach is to use the CISA where available and actionable, recognizing that the data is still not available and not actionable in every location. FEMA also recognized equity concerns in the policy approach, specifically considering over- and under-building concerns for locations where the CISA may be unavailable as explained in the NPRM preamble. The Revised Guidelines recognize the importance of consideration of impacts to vulnerable populations, including those at risk to impacts of flooding due to their location or because they are overburdened, lack resources, or have less access to resources. [ 190 ] Consistent with these concerns, FEMA's FFRMS policy would require the lower of the FVA floodplain or the 0.2PFA floodplain for non-critical actions. FEMA believes the lower approach would help reduce the burden on communities by addressing concerns related to overbuilding, particularly in underserved communities seeking to rebound quickly and effectively from a disaster. Selecting the lower approach for non-critical actions will still result in a higher level of resilience than the current requirements under part 9, while also taking equity and cost-effectiveness considerations into account.

FEMA appreciates the concerns of the remaining commenters requesting maps that depict the FFRMS floodplain and the importance of providing maps with as much coverage as possible. FEMA understands the commenter's concerns in seeking a simplified resource such as a map depicting the FFRMS floodplain and is coordinating across the federal government to develop additional tools beyond the FFRMS Job Aid to assist agencies and stakeholders in determining the appropriate vertical flood elevation and corresponding horizontal FFRMS floodplain. The IWG recently released a beta version of the Federal Flood Standard Support Tool (FFSST), a novel, interactive, map-based tool that incorporates new data to help users identify if a Federally funded project is in the FFRMS floodplain, for comment. [ 191 ] However, FEMA will initially rely on the FFRMS Job Aid methodology to determine the FFRMS floodplain.

Comments: FEMA received questions regarding the CISA floodplain determination methodology. Commenters stated the NPRM did not specify how FEMA would determine the best-available, actionable climate science data and methods for the CISA, stating the agency also did not explain how it would select, evaluate, and update the data and methods that inform the CISA. One commenter asked what sources of data and methods FEMA would use; how FEMA would account for uncertainty and variability in climate projections; and how often FEMA would update the data and methods to reflect new scientific findings. One commenter requested information on the methods FEMA would use prior to selecting data and asked whether state agencies, floodplain managers, and other stakeholders would have an opportunity to inform what best aligned with on-the-ground realities. Both of these commenters asked how FEMA would communicate the data and methods to stakeholders and the public.

One commenter raised concerns that the CISA was still emerging and stated the overall approach would be overly conservative. Similar to other comments described earlier in this summary, this commenter asked who would make the determination to accept the science used for CISA and which projections would be applicable for design life and risk aversion of the structure. This commenter noted the FFRMS did not mention how recent the local climate study needed to be for the CISA and stated that regulatory agencies choose to enforce the most extreme flood events. The commenter recommended FEMA provide guidance for how to use climate projection data for development of unsteady hydraulic models which would be required to determine rate of rise of floodwater and durations.

Another commenter provided several specific recommendations regarding actionable model criteria for the CISA including that the models be well-established in practice; not extrapolate results; display information on uncertainty; are well-calibrated; provide outputs that are understandable; and be Start Printed Page 56970 evaluated via peer-review. The commenter recommended that FEMA provide additional clarity as to what standard of peer review would be considered efficacious when producing future flood risk models, and that FEMA follow up with entities peer reviewing models to confirm that this standard has actually been met. This commenter encouraged the use of a consistent and accurate methodology for determining the FFRMS floodplain across the Federal government. The commenter stated that where CISA data was not available, utilizing the 1 percent annual chance floodplain and the 0.2 percent annual chance floodplain would be appropriate, as those are well understood and adopted for regulatory purposes under the NFIP, as well as the mortgage and insurance industries broadly.

Another commenter stated the lack of transparency in the FFRMS floodplain determination data raised concerns similar to concerns raised regarding proprietary tools used in the implementation of FEMA's Risk Rating 2.0. The same commenter stated proprietary tools would make it difficult to assess whether a CISA floodplain determination was appropriate for local conditions for a specific action and stated national-scale, one-size-fits-all tools would not be readily applicable to project sites in every location, including rural states. The commenter requested FEMA commit to bringing in State and local stakeholders to provide their perspectives.

FEMA Response: FEMA believes the information provided in the rulemaking docket addresses the commenters' concerns regarding how the agency will select, evaluate, and update the data and methods that inform the CISA and account for uncertainty and variability in climate projections. As explained above, the FFRMS CISA State of the Science Report and FFRMS Job Aid provide the public with information on the best available and actionable data for the CISA and the methodology the agency intends to initially use to determine the FFRMS floodplain using the CISA. The FFRMS CISA State of the Science Report and the Revised Guidelines provides details on how the agency will determine the availability and actionability of data for the CISA. The FFRMS Job Aid provides the methodology and process FEMA will use, based on those resources, to determine the FFRMS floodplain.

As explained above, FEMA makes the determination for Step 1 of the 8-step process, in coordination with applicants, and will work with State agencies, floodplain managers, and other stakeholders during this process to best understand the on-the-ground realities. Pursuant to 44 CFR 9.11(d)(6) , a more restrictive Federal, State, or local standard will be used in lieu of the FFRMS. This includes the use of local CISA data and methods that have been adopted by a community for use in floodplain management, as long as such data result in a more restrictive standard. FEMA notes that the agency did communicate information on the data and methodology to determine the FFRMS floodplain to stakeholders and the public with this rulemaking by providing the FFRMS CISA State of the Science Report and FFRMS Job Aid in the public docket. FEMA will provide additional resources to SLTTs and the public and will offer technical assistance regarding the FFRMS floodplain determination as part of the FFRMS implementation. FEMA disagrees with the commenter that agencies choose to enforce the most extreme flood events; the CISA is based on the best available and actionable data, not the most extreme scenarios.

With respect to the comment suggesting that FEMA support a consistent and accurate methodology for determining the FFRMS floodplain across the Federal government, FEMA supports the development of interagency tools because such tools enhance predictability and mitigate transaction costs associated with floodplain determinations. FEMA has prioritized the use of such tools in its policy approach and will initially implement the CISA using the FFRMS Job Aid. FEMA's interagency consultative role in the broader implementation of the FFRMS across the Federal government, through the agency's participation in the Flood Resilience IWG and the FIFM-TF, helps ensure consistent and effective implementation. FEMA's FFRMS policy further provides details on how FEMA will coordinate with other agencies when implementing actions in the same area as another Federal agency. See Section H, page 9. At the same time, there is no requirement in the FFRMS or the Revised Guidelines for all Federal agencies to select the same approach or to implement the CISA with the same tools; the FFRMS is a resilience standard and is meant to be flexible. [ 192 ] Regarding the commenter's question regarding which projections would be applicable for design life and risk aversion of the structure, the FFRMS Job Aid Section 2.4.1 discusses service life including in the context of critical actions. [ 193 ] This information should resolve the commenter's question. FEMA notes that the agency's proposed implementation of the CISA does not include incorporating climate projection data into hydraulic models (steady or unsteady).

FEMA appreciates the recommendations provided by another commenter on the actionable model criteria for the CISA. FEMA is not relying on models for the CISA implementation beyond the models already utilized to produce the agency's regulatory and non-regulatory products for the NFIP. Appendix H of the Revised Guidelines  [ 194 ] and the FFRMS CISA State of the Science Report  [ 195 ] provide an overall framework for assessment of data and models to determine available and actionable climate science.

FEMA agrees with this commenter that, where CISA data is not available and not actionable, the agency will rely on the alternative approaches as detailed in FEMA's FFRMS policy. Section C.3 of FEMA's FFRMS policy states that FEMA will determine the FFRMS elevation and the FFRMS floodplain depending on the criticality of the action. For non-critical actions, the FFRMS floodplain is the area that would be inundated by the lower of the 0.2 percent annual chance flood or 2 feet of freeboard above the BFE. For critical actions, the FFRMS floodplain is the area that would be inundated by the higher of the 0.2 percent annual chance flood or 3 feet of freeboard above the BFE. For locations where information about the elevation and/or extent of the 0.2 percent annual chance floodplain is not available, the FFRMS floodplain is 3 feet of freeboard above the BFE. To clarify, the FVA relies on the 1 percent annual chance floodplain but incorporates an additional measure of safety beyond the 1 percent annual chance floodplain. If available 0.2 percent annual chance floodplain data is not available, FEMA will utilize the appropriate FVA to determine the FFRMS floodplain and elevation.

Finally, FEMA believes the interagency tools used for FFRMS implementation have been transparent in nature. The tools FEMA will utilize to implement the FFRMS are not proprietary. FEMA, as a co-chair of the Flood Resilience IWG, under the National Climate Task Force, facilitated the publication of both the FFRMS Job Start Printed Page 56971 Aid  [ 196 ] and FFRMS CISA State of the Science Report. [ 197 ] The FFRMS Job Aid helps federal agencies and their non-federal partners (including potential federal financial aid recipients) conduct a screening to determine if a proposed federally funded action will be located within an FFRMS floodplain, based on any of the three approaches in accordance with Sec. 2(a)(1) of Executive Order 11988 , as amended. FEMA will initially utilize the FFRMS Job Aid to make these determinations, and this resource was posted in the public docket of this rulemaking for transparency to the public. As explained above, FEMA makes the determination for Step 1 of the 8-step process, in coordination with applicants, and will work with State and local communities during the 8-step process. FEMA will accept local CISA data and methods that have been adopted by a community for use in floodplain management, as long as such data result in a more restrictive standard and will help further ensure local needs are met.

Comment: One commenter requested FEMA specify which NOAA sea level rise (SLR) scenario the agency would consider as the minimum standard to apply the CISA to HMA grant project benefit-cost analysis (BCA) and designs. The commenter also requested FEMA specify under what conditions it would allow higher SLR scenarios to be used, stating the lack of clarity would result in slowdowns and inconsistency in application reviews across FEMA regions and projects. The commenter requested FEMA clarify whether the agency would defer to applicant or State policies that may incorporate higher projections and otherwise meet the criteria for the CISA.

FEMA Response: FEMA is not codifying the specific climate scenarios to be used as part of the CISA analysis. As explained above, FEMA is relying on interagency processes to select and evaluate the data and methods used to implement the FFRMS. In the proposed rule, FEMA referred readers to the FFRMS Job Aid and the FFRMS CISA State of the Science Report, which were posted to the public docket associated with this rulemaking. [ 198 ] FEMA has also posted the FFRMS Job Aid on its website  [ 199 ] and will leverage this tool when implementing the FFRMS. Consistent with the FFRMS Job Aid, FEMA will use the intermediate scenarios for non-critical actions and intermediate-high scenarios for critical actions using the SLR data from NOAA. [ 200 ]

In response to the commenter's concerns regarding the use of higher SLR scenarios and whether FEMA would accept higher standards, 44 CFR 9.11(d)(6) provides that a more restrictive Federal, State, or local standard will be used in lieu of the FFRMS. Thus, if a more restrictive State or local standard relied on a higher SLR scenario, that more restrictive standard would be used. FEMA notes the determination on the information the applicant is using under part 9 has always been made by the agency and thus, FEMA does not anticipate delays with projects as a result of the FFRMS implementation.

Comment: A commenter stated that FEMA's policy approach was not straightforward, as the boundaries and elevations for both the FVA and 0.2PFA must be identified for each project and then compared to establish the final floodplain but stated there was little information on how those boundaries and elevations would be determined. Similar to other commenters above, the commenter asked who would conduct the analysis, what data would be used, and what ground-truthing if any would be performed. The commenter stated this must be determined prior to FFRMS implementation. This commenter stated CISA's application was not understood nor was it likely to be consistent given the significant leeway provided to the Regional Administrators. The commenter requested FEMA explain how the agency would choose the FFRMS approach it would take, what data the agency would rely on, and provide publicly available maps depicting the regulated floodplain (whether that floodplain was determined based on the 1 percent annual chance floodplain, the 0.2 percent annual chance floodplain, or using the CISA, FVA, or any other methodology). The commenter stated the FFRMS was otherwise premature, and FEMA should cease implementation until these efforts were complete.

FEMA Response: FEMA understands the commenter's concern that both the FVA and 0.2PFA will be identified where the CISA is not available and/or actionable. However, FEMA does not believe this analysis will be overly burdensome to the agency or to applicants. FEMA has made, and will continue to make, floodplain determinations partnering with applicants in the 8-step decision-making process. The FFRMS Job Aid provides the methodology and process by which the FVA and 0.2PFA can be determined. This document is publicly available on FEMA's website and was posted to the public docket with this rulemaking. Using the FFRMS Job Aid, FEMA can determine the FFRMS floodplain relevant to a particular location within approximately 23 minutes.

FEMA disagrees with the commenter that the CISA's application is not understood nor likely to be consistent given the resources provided with this rulemaking as detailed above. The FFRMS CISA State of the Science Report and the FFRMS Job Aid help Federal agencies and the public better understand the CISA, the availability and actionability of the CISA data, and how to determine the FFRMS floodplain using the CISA, FVA, and the 0.2PFA. FEMA does not agree with the commenter that FFRMS implementation, including the CISA, will result in inconsistency. FEMA does not believe Regional Administrators are provided with a level of discretion to result in inconsistent FFRMS implementation. Regional Administrators have historically had the authority provided in 44 CFR 9.7 , and FEMA is not changing their authority with this rule.

FEMA notes that the agency explains how it will choose the FFRMS approach to be taken in the FFRMS policy. Section C.3 of the FFRMS policy states FEMA will determine the FFRMS elevation and the FFRMS floodplain depending on the criticality of the action. For non-critical actions, where the CISA is not available, the FFRMS floodplain is the area that would be inundated by the lower of the 0.2 percent annual chance flood or 2 feet of freeboard above the BFE. For critical actions, where the CISA is not available, the FFRMS floodplain is the area that would be inundated by the higher of the 0.2 percent annual chance flood or 3 feet of freeboard above the BFE. For locations where information about the Start Printed Page 56972 elevation and/or extent of the 0.2 percent annual chance floodplain is not available, the FFRMS floodplain is 3 feet of freeboard above the BFE. To clarify, the FVA relies on the 1 percent annual chance floodplain but incorporates an additional measure of safety beyond the 1 percent annual chance floodplain. If available 0.2 percent annual chance floodplain data is not available, FEMA will utilize the appropriate FVA to determine the FFRMS floodplain and elevation.

As explained above, FEMA will initially rely on the FFRMS CISA State of the Science Report and the FFRMS Job Aid to implement the FFRMS. FEMA appreciates the desire to have maps depicting the FFRMS floodplain and is coordinating across the Federal government to develop additional tools beyond the FFRMS Job Aid to assist agencies and stakeholders in determining the appropriate vertical flood elevation and corresponding horizontal FFRMS floodplain. However, FEMA will initially rely on the FFRMS Job Aid methodology to determine the FFRMS floodplain. Given the agency made resources publicly available on this rulemaking docket to determine the FFRMS floodplain, FEMA does not believe delaying the FFRMS implementation is needed. Flood risk is not static and will evolve over time due to changing conditions. Particularly in the context of Federal grantmaking, FEMA does not believe it would be appropriate to delay FFRMS implementation pending a comprehensive FFRMS floodplain mapping of the United States. The decision to proceed in this matter is also consistent with FEMA's historical practice of using best available information in the 8-step process, which also resulted in some degree of uncertainty as part of the project planning and application process.

Comment: A commenter noted the key language of “best available” and “actionable” in the definition of the CISA as determining the reliability, usability, and overall credibility of the final floodplain identification. The commenter noted FEMA's consistent use of the terminology and the definitions found in Appendix H of the Revised Guidelines. The commenter agreed with the terminology but recommended the inclusion of granularity, stating that climate-informed flood risk granular data is property-specific data. The commenter stated granular data has three significant characteristics: structure specific identifications, first floor height assessments, and high-resolution digital elevation model (DEM) data. To reliably assess future flood risk, the commenter stated FEMA must be able to both identify the property itself and the specific structure(s) on that property that require separate assessments. The commenter wrote that the identification requires geospatial data that can reliably assess the geographical boundaries of a property and its structure(s), and without this, risk assessments would not reflect the true risk to the structure. The commenter went on to explain how these assessments involved models based on underlying data inputs that reliably determine the first floor height elevation relative to sea level and ground level and require the use of DEM. The commenter stated the key to reliability is the use of high-resolution DEM, the level of granularity necessary to permit reliable assessment of first floor height elevation and related footprint data. The commenter recommended FEMA advocate for the addition of “granular” as a necessary characteristic for “best available, actionable science.”

The same commenter stated that FEMA's flexible approach would likely facilitate the uptake of critical forward-looking climate and flood assessment methodologies and where those techniques and solutions needed time to develop, still accurately account for flood risk through proven approaches. The commenter stated that while a forward looking, climate-informed approach would be the best framework for understanding flood and other natural hazard risk in the future, not every community, builder, or developer is currently equipped to understand and account for that risk. As building the knowledge base would take time, the commenter recommended use of the waterfall approach proposed by FEMA's policy allowing the FFRMS floodplain to be determined using the FVA or 0.2PFA. The commenter encouraged FEMA to depict the 0.2 percent annual chance floodplain on maps consistent with the requirements of the Biggert Waters Flood Insurance Reform Act of 2012 (BW-12).

FEMA Response: FEMA appreciates the commenter's emphasis on the importance of best available, actionable science to the CISA. FEMA agrees that a determination of the location of an action and site-specific details of the action that are needed for the floodplain determination and minimization of impacts requires a variety of granular data. However, all of the science and data used to define the floodplain does not necessarily need to be granular to be actionable. For example, regional sea level rise data is considered actionable best available science in the FFRMS CISA State of the Science Report but would not satisfy the definition of granular data provided by the commenter. FEMA will continue to use granular data, where appropriate, such as detailed digital elevation models to determine floodplain extents and first flood elevations for structures that are part of Federal actions. FEMA will further consider the commenter's request to incorporate granularity through the use of structure-specific identifications, first floor height assessments, and high-resolution digital elevation model (DEM) data as part of the agency's role in the IWG.

FEMA agrees with the commenter that, given that the best available data is not available and/or actionable in all locations, both FVA and 0.2PFA should be leveraged to determine the FFRMS floodplain. FEMA also agrees it is important to depict the 0.2 percent annual chance floodplain on community maps consistent with the requirements of BW-12.

Comment: A commenter asked whether the approaches in the FFRMS policy should be used to develop FIRMs or FIS. The commenter stated the methods listed to develop the floodplain should only apply to those actions listed in the Applicability section of the FFRMS policy.

FEMA Response: The approaches listed in section C of FEMA's FFRMS policy document for determining the FFRMS floodplain are not used to develop FIRMs or FIS. FIRMs and FIS are a starting point for the floodplain determination under the 8-step process. The approaches listed in section C of the policy are only applicable to the actions detailed in the applicability section of FEMA's FFRMS policy.

Comment: Two commenters stated that FEMA's 2016 proposed rule indicated the use of CISA was not appropriate and stated FEMA's current reliance on CISA was unsubstantiated. The commenters noted an article that expressed concerns with climate science  [ 201 ] and cited statements in the FFRMS CISA State of the Science Report as evidence that attempts to apply the CISA to set flood risk management standards would be subjective. Both commenters requested transparency and adherence to the principles of replicability and independent peer review if FEMA utilizes the CISA. One of the commenters stated FEMA must adhere to a specific set of criteria to clarify the Start Printed Page 56973 standard and that there must be metrics. The commenters stated that the other approaches provided numerical targets that define what success shall be. Both commenters stated that if FEMA could not provide decision criteria to be applied in the CISA approach, the agency should eliminate it as a standard.

FEMA Response: Since the introduction of the CISA in 2015, additional data has become available to better inform CISA. The FFRMS CISA State of the Science Report provides a recommendation on available and actionable CISA data. [ 202 ] Many of the concerns expressed by the commenters are further addressed in that report and explain why the CISA data is not actionable in all locations. FEMA disagrees with the commenters' suggestion that certain statements in the FFRMS CISA State of the Science Report regarding multiple scenarios and hybrid approaches that could be used to determine the CISA serve as evidence that the CISA is too subjective. The CISA guidance in Appendix H of the Revised Guidelines and the FFRMS CISA State of the Science Report provide broad guidance for where the CISA might be available and actionable with sufficient expertise, local data, and project-specific analysis. However, FEMA prioritized the type and criticality of the action involved, the availability and actionability of the data, and equity concerns, and determined that applying the CISA through complex expert project-specific modeling was not appropriate for FEMA given the agency's role in helping people recover from disasters in an expedited manner and to reduce the subjectivity concerns of the commenters stated above. FEMA instead decided to use consensus interagency approaches that were readily accessible and do not require project specific CISA modeling found in the FFRMS Job Aid.

The FFRMS Job Aid details the underlying methodology used to determine the FFRMS floodplain, including using the CISA, and FEMA believes that resource provides sufficient transparency and replicability to stakeholders and the public. FEMA will initially use the FFRMS Job Aid to make the FFRMS floodplain determination. FEMA is coordinating across the federal government to develop additional tools beyond the FFRMS Job Aid to assist agencies and stakeholders in determining the appropriate vertical flood elevation and corresponding horizontal FFRMS floodplain.

FEMA does not believe that the use of CISA results in uncertainty in the 8-step process. The FFRMS Job Aid details the underlying methodology used to determine the FFRMS floodplain, including using the CISA, and FEMA believes that resource provides sufficient transparency and replicability to stakeholders and the public. The FFRMS CISA State of the Science Report, upon which the FFRMS Job Aid is based, was reviewed by subject-matter experts across the members of the Flood Resilience IWG, including staff from NOAA's National Weather Service, the USGS's Water Resources Mission Area and Coastal/Marine Hazards and Resources Program, FEMA's National Flood Hazard Mapping Program, and other members of the FFRMS Science Subgroup. [ 203 ]

FEMA agrees with one of the commenters that the FVA and 0.2PFA provide some additional clarity to stakeholders because the 1 percent annual chance and 0.2 annual chance floodplains are more commonly used and depicted on FEMA regulatory and non-regulatory mapping products. FEMA's FFRMS policy provides for the use of these approaches where the CISA data is not available or not actionable. However, FEMA does not believe that the CISA must be eliminated simply because the FVA and 0.2PFA are more commonly understood. The FFRMS CISA State of the Science Report and the FFRMS Job Aid are resources the public can use to better understand the CISA and how FEMA will implement it. These resources provide the requisite decision criteria for how the CISA will be determined by FEMA in the initial FFRMS implementation. FEMA will provide additional resources and technical assistance to SLTTs and the public regarding the FFRMS floodplain determination as part of the FFRMS implementation to help further educate stakeholders.

Several commenters requested FEMA consider local CISA data in making the CISA floodplain determination.

Comments: Some commenters requested the use of specific State and/or local data. One commenter stated the use of locally available CISA data and methods would provide opportunities for underserved communities to provide critical local input. One commenter recommended FEMA develop a framework for evaluating whether local CISA data is technically credible and appropriate. One commenter stated if State, Tribal, territorial, or local data resulted in CISA-based elevation standards that met or exceeded standards developed using Federal data, then FEMA should apply the higher, locally available standards, if reasonable. The commenter stated Federal data should act as a floor for CISA calculation under the FFRMS.

Another commenter stated FEMA should accept local data where it is accurate and sufficiently protective to maximize the effectiveness of the rule. The same commenter requested FEMA consider the potential inequities in access to CISA. Another commenter recommended FEMA develop a framework for evaluating whether local CISA data is technically credible and appropriate.

In addition to requesting FEMA accept local CISA data, one commenter sought additional details on the FEMA FFRMS CISA data development to avoid developing duplicative or conflicting data. The commenter stated FEMA's Federal floodplain management tools ( i.e., FIS and FIRMs) are used for applications beyond their originally intended purpose, including comprehensive planning and resilience planning. The commenter encouraged FEMA to consider how its CISA FFRMS data and tools could be used for comprehensive flood risk planning at multiple levels of government when developing the products. The commenter also encouraged FEMA to coordinate with stakeholders when developing its CISA data and methods. Two commenters agreed that FEMA should further engage with stakeholders regarding CISA data and methods.

FEMA Response: FEMA agrees with the commenter that Federal data should act as a floor for the CISA calculations under the FFRMS. SLTTs can provide input into the determination. Pursuant to 44 CFR 9.11(d)(6) , a more restrictive Federal, State, or local standard will be Start Printed Page 56974 used. This includes the use of local CISA data and methods that have been adopted by a community for use in floodplain management, as long as such data results in a more restrictive standard.

FEMA notes the FFRMS Job Aid is a resource to help Federal agencies and their non-Federal partners (including potential federal financial aid recipients) conduct a screening to determine if a proposed federally funded action will be located within an FFRMS floodplain, based on the CISA, FVA, or 0.2PFA, in accordance with Sec. 2(a)(1) of Executive Order 11988 , as amended. FEMA will continue to collaborate across the Federal government to develop tools to facilitate the implementation of CISA.

Regarding the framework for accepting local CISA data, FEMA will continue to rely on 44 CFR 9.7 , FEMA Policy 104-008-2: Guidance on the Use of Available Flood Hazard Information, [ 204 ] and the Revised Guidelines in determining whether CISA and flood hazard data is available and actionable. FEMA is coordinating across the federal government to develop additional tools to assist agencies and stakeholders in determining the appropriate vertical flood elevation and corresponding horizontal FFRMS floodplain.

FEMA's policy approach considers situations where CISA data is not available. Specifically, the policy approach detailed in the FFRMS Policy provides for the use of the FVA or 0.2PFA depending on the criticality of the action and data availability. FEMA believes the agency's policy approach will reduce concerns with underbuilding or overbuilding and thus provide a more cost-effective, equitable approach.

As previously explained, FEMA is relying on interagency processes to select and evaluate the data and methods used. Appendix H of the Revised Guidelines  [ 205 ] provides an overview of the available and actionable data for CISA, which is the basis for these interagency supporting tools. The FFRMS CISA State of the Science Report  [ 206 ] provides a review and update of the best-available, actionable science that can support application of the Climate-Informed Science Approach (CISA), reflecting science and technology advancements made since Executive Order 13690 was issued in 2015. [ 207 ] FEMA will rely on these and future interagency publications for CISA data. The Revised Guidelines also provide an explanation of how the FFRMS will be updated in the future.

FEMA appreciates the importance of comprehensive flood risk planning and is developing additional resources for communities and the public to better understand their current and future flood risks. For example, FEMA's Future of Flood Risk Data (FFRD) initiative will provide a more comprehensive picture of the country's flood hazards and risks by leveraging new technologies to include more efficient, accurate, and consistent flood risk information across the nation. [ 208 ] These resources can be used by communities for planning purposes. FEMA will continue to engage with SLTTs and the public on the development and enhancement of flood risk resources, including FFRMS implementation resources for the CISA, FVA, and 0.2PFA.

Comment: One commenter requested FEMA provide training resources to help local communities, practitioners, and property owners understand the impact of the rule.

FEMA Response: FEMA values additional input from SLTT partners and the public in the 8-step process. FEMA will provide additional resources to SLTTs and the public as part of the FFRMS implementation, and FEMA's regional offices will provide technical assistance to applicants for FEMA programs.

Comment: One commenter stated concerns with the language in proposed § 9.7(b)(1), which stated that FEMA shall obtain enough information so that it can fulfill the requirements in part 9 to (i) avoid Federal action in floodplain and wetland locations unless they are the only practicable alternatives and (ii) Minimize harm to and within floodplains and wetlands). The commenter stated that the language was too vague to have any meaning, as “enough information” did not inform the agency or the public of the requirement. The commenter recommended some identifiable minimum standard be provided.

FEMA Response: FEMA disagrees that the proposed language is unduly vague. In context, paragraph (b) provides that FEMA will make the determination as part of the 8-step process and provides a list of the types of information FEMA will use to make this determination including the current and future flooding characteristics detailed in paragraph (b)(3). Not all of this information is required, as the information needed to make the floodplain or wetland determination is action-specific and subject to data availability.

Comment: One commenter stated costs would increase for engineering and planning around Federally funded projects when implementing FFRMS, particularly in areas where the 0.2 percent floodplain is not currently mapped.

FEMA Response: FEMA appreciates the commenter's concerns regarding costs but disagrees that engineering and planning costs will necessarily increase for actions subject to the FFRMS and particularly for those in areas where the 0.2 percent annual chance floodplain is not currently mapped. FEMA will initially implement the FFRMS using the FFRMS Job Aid to determine the FFRMS floodplain and stakeholders can also leverage this tool to determine the CISA, FVA, and 0.2PFA where such data is available. As FEMA's FFRMS policy states, where the CISA data is not actionable and not available and information about the elevation and/or extent of the 0.2 percent annual chance floodplain is also not available, the FFRMS floodplain is the FVA. By considering data availability in the FFRMS floodplain determination and providing resources to help stakeholders understand the FFRMS floodplain determination, FEMA believes the commenter's concerns are addressed.

Further, FEMA considered the costs and benefits associated with this rule, including the overall increased costs of FEMA projects, in the regulatory impact analysis provided on the docket. [ 209 ] FEMA believes that the benefits of preventing property damage, protecting Federal investments, and potentially saving lives justify the costs of the rule. These benefits are a result of the improved protection of structures and facilities due to increased elevation and floodproofing standards in FEMA's implementation of the FFRMS. This rule will help to ensure that Federal investments are better protected from Start Printed Page 56975 flood damage, and that the natural and beneficial values of floodplains are preserved. FEMA notes any increased costs are generally eligible for funding under FEMA's assistance programs subject to cost share requirements.

Comments: Some commenters requested clarification on the use of current FEMA regulatory products in the FFRMS floodplain determination. Commenters provided input asking FEMA to improve those maps for the FFRMS floodplain determination and other purposes. One commenter requested FEMA update the agency's floodplain mapping techniques and incorporate future risk into the mapping. The commenter recommended FEMA incorporate the recommendations by the TMAC for significant changes to FEMA's floodplain mapping techniques. The commenter requested all agencies collaborate and align around definitions for floodplain mapping and share expertise to develop CISA floodplain definition methods that are consistent with one another. Such consistency would be easier and assist applicants in adhering to agency regulations. The commenter further recommended the MitFLG work toward common definitions and delineation of floodplains to enable better interagency collaboration and coordination on issues related to flood risk reduction. The commenter also stated the need to improve and update FEMA's regulatory mapping products, indicating these products were essential for community-level planning, yielding enhanced resilience. The commenter stated flood maps were essential underpinning to drive wise land use decisions, including where not to develop and where to conserve lands that might aid in flood risk reduction.

Another commenter stated the FFRMS did not consider FIRM effective dates in communities where FIRMs are currently being updated and requested clarification for applying the CISA to those communities or applicable use of effective flood maps. One commenter noted FEMA's policy approach to leverage the 0.2PFA or FVA where CISA data is not available and not actionable and stated that approach was not without challenges given FEMA's regulatory and other mapping products used in the analysis of those approaches were outdated and likely to remain so for the foreseeable future.

A commenter recommended Federal agencies continue relying on FEMA flood risk data and tools for future implementation of a climate-informed floodplain. The commenter noted FEMA's investment on flood engineering studies and flood mapping over the past half century and that States and localities nationwide adopted FEMA flood map data for flood mitigation, community development, and many other purposes. The commenter stated that abandoning current Federal efforts on flood mapping and adopting an alternative flood map dataset would waste Federal investments on flood engineering studies and flood inundation mapping. Another commenter stated FEMA would have the primary responsibility to prepare the data to support the CISA through its existing mapping activities. The commenter noted other FEMA mapping priorities through the agency's RiskMAP program and encouraged FEMA to secure and allocate sufficient resources and fully utilize the Cooperating Technical Partners program to support the CISA and related mapping activities.

FEMA Response: FEMA appreciates the commenters' interest in the agency's flood risk mapping efforts. FEMA is considering the TMAC recommendations associated with future flood conditions mapping and intends to incorporate future flood conditions into mapping products as practicable. [ 210 ] FEMA's interagency consultative role in the broader implementation of the FFRMS across the Federal government, through the agency's participation in the IWG and the FIFM-TF helps ensure consistent and effective implementation. FEMA will continue to work in an interagency manner in conjunction with the Water Resources Council, the MitFLG, and the FIFM-TF to develop tools to facilitate the implementation of CISA. FEMA agrees that the agency's regulatory mapping products support community-level planning that enhances resilience and help drive wise land use decisions.

FEMA understand other commenters' concerns regarding FIRM effective dates and the age of FIRMs in some communities that may no longer reflect current flood risk. FEMA plans to continue updating regulatory mapping products to help address the commenter's concerns regarding stale maps. However, floodplain determinations under part 9 are not solely predicated on existing FIRMs and commenters' concerns about potential challenges with the FVA and 0.2PFA based on the age of existing FIRMs is thus unwarranted. As explained in the NPRM, FEMA will use best available information which may include information that is non-regulatory or FEMA preliminary flood hazard data. To be designated as the best available information, it must be at least as restrictive as information provided by effective FIRMs. Given the best available information policy FEMA adopted, [ 211 ] the agency will be continuously improving the data associated with the floodplain determination. FEMA notes pursuant to 44 CFR 9.11(d)(6) , a more restrictive Federal, State, or local standard will be used in lieu of the FFRMS. Communities can leverage their own data, including the use of local CISA data and methods that have been adopted by a community for use in floodplain management, as long as such data results in a more restrictive standard. FEMA believes these flexibilities address the second commenter's concerns to ensure the best available flood risk information is being considered in the 8-step analysis.

FEMA notes that, as explained above, the agency is not abandoning current efforts on flood mapping but rather is continuing to update regulatory maps. FEMA is not adopting an alternative flood map dataset as part of this rulemaking. Regulatory mapping products are part of the NFIP's regulatory process and not impacted by this rulemaking. The agency's investments in regulatory mapping products are not being wasted by this effort and will continue in support of the NFIP's regulatory process, as well as to inform the public on flood risk. FEMA further appreciates the commenter's concern regarding sufficient resources and will continue to utilize the Cooperating Technical Partners program to support the agency's mapping efforts.

Comment: A commenter wrote their support for modernizing the data and approaches used to understand and anticipate flood risks, stating the use of best available data, technology, and modeling would yield better baseline data to account for climate-induced increases in precipitation and inundation. The commenter noted that data from FIRMs in some areas can be 40 years old. The commenter noted that FEMA predicted more accurate maps would expand the floodplain but stated adjustments were needed to ensure the expanded mapping does not further hinder Federal, State, and local efforts Start Printed Page 56976 to restore natural and beneficial floodplain functions.

FEMA Response: FEMA does not anticipate that more accurate mapping of current flood risks will necessarily expand the floodplain. FEMA's experience when revising existing regulatory floodplains is that the overall floodplain area does not generally increase, as more accurate maps can also mean areas are no longer designated as being within the floodplain. While revised maps reflect updated data on inland hydrology, coastal storms, and sea levels, they focus on current conditions and do not include projections of future changes. FEMA does anticipate the FFRMS, when implemented, will generally expand the floodplain area for actions subject to the FFRMS under part 9. FEMA agrees with the commenter that leveraging the best available information in making the floodplain determination can assist in accounting for climate-induced increases in precipitation and inundation. As explained above, FEMA plans to continue updating regulatory mapping products to address the commenter's concerns with dated data; however, floodplain determinations under part 9 are not solely predicated on existing FIRMs. FEMA will use best available information which may include information that is non-regulatory or FEMA preliminary flood hazard data. To be designated as the best available information, it must be at least as restrictive as information provided by effective FIRMs. FEMA does not believe implementation of the FFRMS will hinder restoration of natural and beneficial floodplain functions. Rather, it is also the policy of FEMA to restore and preserve the natural and beneficial values served by floodplains in part 9.

Comment: One commenter requested clarification on how allowing the use of other data beyond the data found in FIRMs or FIS would affect the CLOMR, LOMR, No Adverse Effect, No Rise processes.

FEMA Response: This rulemaking does not have any impact on the current CLOMR, LOMR, or no rise processes. FEMA does not have a no adverse effect process.

Comments: Some commenters requested additional information regarding the interagency tools FEMA will utilize to depict the FFRMS floodplain. A commenter wrote in support of developing a decision support tool to facilitate the implementation of the FFRMS, requesting the tool be narrowly focused, integrating and avoiding duplication of existing Federal tools and data portals. The commenter also requested the tool incorporate local data wherever possible and that FEMA use the tool to highlight data gaps preventing the wider use of CISA to encourage development of such data in those areas. Another commenter wrote requesting FEMA work closely with NOAA, the White House Office of Science and Technology Policy, and other appropriate departments to ensure that States, communities, and the public can readily access information about what data sources meet the criteria for climate-informed science and are considered current and credible at a point in time. Two commenters noted appreciation for FEMA's work with the Flood Resilience IWG on developing an online mapping tool to assist in determining the FFRMS floodplain, including the CISA and requested prioritizing these efforts.

FEMA Response: FEMA appreciates the commenters' support of the agency's interagency collaboration and is continuing to work with IWG to support the FFRMS and CISA implementation. FEMA also appreciates the commenters' statements on developing additional tools to support the FFRMS implementation across the Federal government. FEMA agrees with the commenter that a tool to facilitate FFRMS implementation is an important component to the success of the FFRMS, and the agency published on the public docket with this rulemaking the FFRMS Job Aid as an initial resource. FEMA anticipates leveraging the FFRMS Job Aid for determining the FFRMS floodplain when the final rule is implemented. FEMA will continue to collaborate across the Federal government to develop tools to facilitate the implementation of CISA and the FFRMS. The IWG recently released a beta version of the Federal Flood Standard Support Tool (FFSST), a novel interactive, map-based tool that incorporates new data to help users identify if a Federally funded project is in the FFRMS floodplain, for comment. [ 212 ] FEMA will also continue to rely on 44 CFR 9.7 , FEMA Policy 104-008-2: Guidance on the Use of Available Flood Hazard Information, [ 213 ] and the Revised Guidelines in determining whether CISA and flood hazard data is available and actionable.

Comment: One commenter requested FEMA retain the requirement that Regional Administrators identify additional flooding characteristics in the locations of proposed actions. The commenter noted FEMA's changes in 44 CFR 9.7(b) (3) from “shall” to “may” identify such flooding characteristics, “as appropriate” and requested “shall” be retained, as the flooding characteristics identified included important factors to consider when minimizing harm to floodplains and wetlands. The commenter stated there was no adequate rationale for allowing the Regional Administrator to ignore any or all of the flooding characteristics. The commenter also requested FEMA include “evacuation and migration corridors for wildlife, including threatened and endangered wildlife” in the list of flooding characteristics.

FEMA Response: FEMA appreciates the commenter's concerns but does not believe this language change is a change impacting how FEMA will review the flooding characteristics. Rather, the edit from “shall” to “may” is a clarifying edit. As explained in the preamble to the NPRM, the term “shall” suggests a mandatory requirement for the Regional Administrator to identify all of the additional flooding characteristics listed, yet the current qualifying “as appropriate” language suggests the identification was not mandatory. FEMA's current practices do not mandate a review of each of the flooding characteristics but rather only those that are appropriate. FEMA updated this language to reflect the Regional Administrator's discretion in identifying the appropriate flooding characteristics consistent with current practices.

FEMA also appreciates the importance of wildlife and the commenter's concerns about their habitats and evacuation and migration corridors; however, wildlife concerns are currently part of the flooding characteristics considered when determining the floodplain. The definition of “natural and beneficial values of floodplains and wetlands” addresses wildlife considerations, and FEMA does not believe the additional language proposed by the commenter is required to ensure this analysis.

Comment: Another commenter requested FEMA give local communities a voice in the method used to determine the appropriate vertical flood elevation stating Federal agencies may not be familiar with the local conditions. The commenter gave an example of areas with flash floods requiring an appropriately short rainfall interval be Start Printed Page 56977 evaluated to avoid missing the storm peak.

FEMA Response: FEMA has and will continue to consider flooding characteristics such as those listed by the commenter consistent with § 9.7. FEMA notes that communities provide input into the floodplain determination for part 9 and the agency coordinates with applicants and State and local officials as appropriate throughout the 8-step process. As explained above, pursuant to 44 CFR 9.11(d)(6) , a more restrictive Federal, State, or local standard will be used. This includes the use of local CISA data and methods that have been adopted by a community for use in floodplain management, as long as such data results in a more restrictive standard. Projects subject to the FFRMS will continue to be designed to meet local needs as appropriate.

Comment: Four commenters requested FEMA recognize the value of Indigenous Knowledge and Tribal resources in the 8-step process. One commenter supported the proposed range of data sources to ensure FEMA relies on the best available information when determining flood risk but requested FEMA incorporate Indigenous Knowledge when considering best available information for determining flood risk. The commenter noted the Biden Administration's guidance to Federal agencies to increase reliance on Indigenous Knowledge to inform Federal decision-making and recommended FEMA incorporate the use of such information in the final rule. Specifically, the commenter requested FEMA revise § 9.7(c)(3)(ix) to read “State, Regional, and Tribal Agencies or governing bodies,” add a new § 9.7(c)(3)(xi) to identify Indigenous Knowledge as another source of high-quality information and seek opportunities for engagement and promotion of best practices to include Indigenous Knowledge in FEMA decision making. A second commenter provided similar feedback, supporting the expanded inclusion of diverse data sources and requesting FEMA integrate Indigenous Knowledge into the final rule while also continuing to collaborate with Tribal Nations and Indigenous Peoples to incorporate Indigenous Knowledge into FEMA policies. A third commenter supportive of incorporating Indigenous Knowledge into the 8-step process recommended the final rule direct FEMA to seek input from local Indigenous communities when developing alternatives to an action and assessing impacts. This commenter noted that these communities may have unique, proven methods for reducing flood risk and incorporating this knowledge would recognize Indigenous connections to the land and help produce better-informed decisions.

Another commenter requested FEMA align with States and Tribes on data practices. Consistent with other commenters above, this commenter requested FEMA consider State, Tribal, territorial, or local CISA-based elevation standards data that met or exceeded standards developed using Federal data. The commenter stated FEMA should apply the higher, locally-available standards if reasonable. The commenter provided an example of State SLR guidance using State data, requesting that FEMA allow us of this data so long as it met or exceeded the Federal data. The commenter stated that Federal data should act as a floor for CISA calculation under the FFRMS and that if reasonable, locally available data meets or exceeds the floor set by Federal data, then it should be accepted for implementation consistent with FEMA's proposed approach to leverage the best available data to inform flood risk. The commenter noted the incorporation of local data and methods can provide opportunities to achieve higher resolution data and in-depth understanding of contextual climate impacts. The commenter requested FEMA encourage intergovernmental and interstate collaboration to share and improve best practices for underlying local data collection, including agency guidance on expanding locally available data.

FEMA Response: As one commenter stated, President Biden issued Federal government-wide guidance on recognizing and including Indigenous Knowledge in Federal research, policy, and decision making. [ 214 ] FEMA agrees with the commenters on the importance of Indigenous Knowledge in the 8-step process. FEMA agrees with the commenter to ensure Tribes are specifically incorporated into § 9.7(c)(3)(ix) and is updating this final rule to state, “Agencies of State, Regional, and Indian Tribal Governments.” This edit will ensure consideration of Indian Tribal government data in the floodplain determination. FEMA believes the current language in § 9.7(c)(3)(x) regarding local sources covers those Tribes that are not considered to be an Indian Tribal government under 42 U.S.C. 5122(6) .

FEMA supports the inclusion of Tribal and Indigenous knowledge into the FFRMS process. As requested by the second commenter, FEMA is integrating Indigenous Knowledge into the FFRMS policy accompanying this rule. The agency will collaborate with Tribal Nations and Indigenous Peoples to incorporate Indigenous Knowledge into FEMA policies consistent with the guidance referenced above. FEMA further agrees with the third commenter that local Indigenous communities may have methods for reducing flood risk that recognize Indigenous connections to the land and help produce better-informed decisions. To ensure input from local communities, FEMA follows the process for early and final public notices in the 8-step process. See §§ 9.8(c)(4) and 9.12. The current regulatory text incorporates notice to Tribes when effects may occur on Tribal lands in the early public notice process. See § 9.8(c)(4)(ii). The final public notice includes notification to any entity that received early public notice. See § 9.12(a). These notifications give Tribal communities the ability to provide input on alternatives and impacts in the 8-step process. This ensures consideration of Tribal and Indigenous Peoples throughout the 8-step process.

Finally, FEMA agrees with the fourth commenter that Federal data should act as a floor for CISA calculations under the FFRMS. FEMA will apply higher, locally available standards consistent with § 9.11(d)(6) that requires a more restrictive Federal, State, or local standard be used. This includes the use of local CISA data and methods that have been adopted by a community for use in floodplain management, as long as such data results in a more restrictive standard. FEMA agrees with the commenter that locally available data can provide valuable input into the area's climate impacts and will leverage those higher standards adopted by communities. FEMA values additional input from SLTT partners and the public in the 8-step process and will continue to engage by providing additional resources and technical assistance as the FFRMS is implemented.

Comment: One commenter requested FEMA include examples of “other sources” in § 9.7(c)(iii).

FEMA Response: FEMA provides a list of other sources in § 9.7(c)(3)(i)-(x) of this final rule. As explained above, the agency will provide additional resources and technical assistance to Start Printed Page 56978 SLTTs and the public as part of the FFRMS implementation.

Comment: One commenter requested FEMA provide additional guidance on how to identify the appropriate lifecycle for a proposed action that uses CISA to determine the FFRMS floodplain. The commenter noted that FEMA used a default 50-year lifecycle analysis (in the regulatory impact analysis) and stated that would not be appropriate for all actions. The commenter requested FEMA provide information on how the 50-year lifecycle timeline was determined, as well as guidelines on how to determine the appropriate lifecycle on a case-by-case basis.

FEMA Response: FEMA's regulatory impact analysis was based on a report defaulting to a 50-year lifecycle, but FEMA intends to determine the appropriate service life on a case-by-case basis for each action. The FFRMS Job Aid provides additional information on service life and how FEMA will make those individual determinations. [ 215 ]

FEMA received several comments regarding implementation of the FFRMS. Commenters raised general process concerns with compliance with and enforcement of the FFRMS, and costs and delays with implementing the FFRMS. Commenters also inquired as to how FEMA would coordinate with other Federal agencies when implementing the FFRMS, how FEMA would effectively complete outreach to ensure effective implementation of the FFRMS, and how FEMA would resolve environmental justice concerns.

Comment: A commenter stated raising individual properties or a group of properties could not be done without considering potential for impounding water on neighboring properties and roadways. The commenter recommended a holistic approach with local land use agencies, municipalities, and DOTs that identify the best path forward for a roadway corridor.

FEMA Response: FEMA appreciates the commenter's concerns regarding the impact of elevation on neighboring properties and roadways. FEMA takes a holistic approach through the 8-step process as the agency considers the impacts within or affecting floodplains and wetlands. FEMA applicants propose actions based on their needs and planning efforts to protect life and property. Where FEMA provides funding for applicable actions, the FFRMS will help ensure resilience to structures and facilities against both current and future flood risks, including roadway corridors referenced by the commenter. Section G.2 of the FFRMS policy provides additional details on the application of the FFRMS resilience standard to facilities such as roadway corridors.

Comment: A commenter stated that FEMA's framework, while seeking to retain flexibility and be easily understood and consistently applied, would complicate understanding and implementation on the ground, as the framework created a confusing inundation of floodplain definitions—each of which could be used differently depending on the program and/or situation for which it is being used and/or applied.

This commenter noted the majority of structures and facilities impacted by the rulemaking were not residential in nature but stated concerns about implementation and difficulties of confusing and burdensome requirements. The commenter stated FEMA's proposed FFRMS floodplain definition and the vagueness of its depiction would generate countless unique floodplain definitions for programs. The commenter stated concern that once adopted and implemented for a very small number of Federally-funded residential projects, the Federal government would seek to expand the FFRMS applicability to all structures and that such a move would significantly impact housing affordability across the country.

The commenter noted the 1 percent annual exceedance probability (AEP) was set as the basis for the NFIP in the 1960s, and the 1 percent AEP was considered a fair balance between protecting the public and overly stringent regulation. The commenter stated that Executive Order 11988 has been historically and purposely tied to the 1 percent annual chance floodplain and that the Federal government had relied on the 1 percent annual chance floodplain when determining the extent of its authority and reach for most of its related programs, including the NFIP, FIRMs, and the mandatory flood insurance purchase requirements. The commenter stated this was no longer the case under the proposed rule.

The commenter stated that during the 1978 Guidelines drafting, concerns were raised about the need to provide a higher degree of protection for certain activities, and the 1978 Guidelines bifurcated the definition of floodplain for critical and non-critical actions. The commenter noted that FEMA was taking a similar approach for the FFRMS floodplain per the Revised Guidelines, separating the definition further depending on the type of action and data availability. The commenter stated that unlike the revision made in the 1978 Guidelines where the 1 percent annual chance floodplain and the 0.2 percent annual chance floodplain were relatively well-known recurrence intervals and elevation levels that could be calculated, while the FFRMS floodplain is a “mystery.” The commenter stated that with the FFRMS floodplain, the public would be faced with another set of regulatory definitions, creating inconsistencies and further confusing the various programs and their applicability and requirements. The commenter provided an example stating the higher flood risk standard for certain applications generated inconsistencies with the NFIP and the countless State and local regulations tied to the 1 percent annual chance floodplain. With what the commenter categorized as competing floodplain definitions, the commenter stated that Federal agencies, SLTTs, and the public would be left wondering which definition was the “real” definition—the climate-informed science definition, the freeboard definition, or the 0.2 annual chance floodplain definition. The commenter stated it would not always be clear which definition to follow under different circumstances and that while it may be beneficial for more people to understand their flood risk, the regulatory uncertainty and unpredictability of so many floodplain definitions would only multiply.

FEMA Response: FEMA disagrees that the framework to implement the FFRMS will create a confusing inundation of floodplain definitions—each of which could be used differently depending on the program and/or situation for which it is being used and/or applied. Consistent with current practice, FEMA will continue to make the floodplain determination as part of the action taken, reducing the burden on applicants in the process. As outlined in the FFRMS Policy, FFRMS requirements are consistent across FEMA's programs for those actions that are subject to the FFRMS. FEMA does not anticipate countless inconsistent floodplain determinations resulting from the implementation of this rulemaking for FEMA's programs as the appropriate floodplain definition is clearly outlined in the FFRMS Policy. FEMA notes that while other Federal agencies have their own implementing procedures for the Start Printed Page 56979 FFRMS, FEMA will coordinate with other agencies to avoid applying conflicting standards on the same action pursuant to Section H of the FFRMS policy.

FEMA agrees with the commenter that the majority of structures and facilities subject to FEMA's FFRMS implementation will not be residential in nature. FEMA does not believe the commenter's concerns are warranted regarding expansion of the FFRMS's applicability. As explained above, FEMA defines “action subject to the FFRMS” as “any action where FEMA funds are used for new construction, substantial improvement, or to address substantial damage to a structure or facility” in this rulemaking, and the FFRMS applies to grants for projects funding the new construction, substantial improvement, or repair of substantial damage under FEMA's grant programs and does not extend to all structures. FEMA's final rule is clear that FFRMS is limited in applicability to those Federally-funded actions.

Rather than bolstering the arguments against utilizing the FFRMS, FEMA believes the commenter's statements regarding the 1 percent AEP demonstrate a need to update the agency's floodplain determinations under part 9 to meet changing conditions and better ensure Federal investments are protected from flood damage, and that the natural values of floodplains are preserved. More than 45 years have passed since Executive Order 11988 and flooding continues to increase  [ 216 ] and impact Federal investments. [ 217 ] FEMA believes the updates made to part 9 in this final rule are an important step forward to improve resilience and better protect Federal investments from flood damage than the standards set over almost a half a century ago. FEMA disagrees with the commenter that the FFRMS approaches result in confusion for Federal agencies, SLTTs, or the public. The FFRMS Job Aid provides the methodology and process for FEMA to determine the FFRMS floodplain under each approach, and FEMA's FFRMS policy explains how each approach will be applied to specific actions based on the type and criticality of the action involved, the availability and actionability of data, and equity concerns. FEMA believes these resources provide sufficient clarity for implementation. To the extent stakeholders have questions after reviewing these resources, FEMA intends to provide SLTT partners and the public with additional resources to assist them in applying for FEMA-funded assistance programs.

FEMA further disagrees with the commenter that the agency's FFRMS policy approach is inconsistent with the NFIP minimum standards and other Federal, State, local, Tribal, and territorial standards. Rather, the FFRMS is generally a higher standard. Further, § 9.11(d)(6) of the final rule states a more restrictive Federal, State, or local floodplain management standard will be applied if higher than the FFRMS. FEMA believes the commenter's concerns regarding confusion between different floodplain approaches are unwarranted. The floodplain determination in part 9 has always been distinct from the NFIP minimum floodplain management standards. While FEMA understands that the FFRMS approaches provide additional optionality, the FFRMS policy helps clarify which approach is applicable to those actions subject to the FFRMS.

Comment: Another commenter stated the application of the FFRMS should be in progressive and adaptive fashion and requested additional guidance on how the FFRMS would be applied.

FEMA Response: As explained in § 9.5(a)(3), FEMA will apply the FFRMS only to new FEMA-funded actions involving new construction, substantial damage, or substantial improvement for which assistance is made available pursuant to declarations under the Stafford Act that are commenced on or after the effective date of the final rule, and new FEMA-funded actions involving new construction, substantial damage, or substantial improvement for which assistance is made available, pursuant to notices of funding opportunity that publish on or after the effective date of the final rule. Ongoing projects will not be impacted by this final rule. [ 218 ] FEMA will continue to analyze the effectiveness of the agency's FFRMS policy as part of the FFRMS implementation, and the policy will be reviewed, revised, extended, and/or rescinded within four years of the issue date.

Comment: The same commenter inquired as to how the final rule would impact the current way FEMA-regulated floodplains were handled during the NEPA process.

FEMA Response: FEMA's integrated reviews under E.O. 11988 and NEPA are unchanged by the final rule.

Comments: Two commenters sought clarification on how FEMA would ensure compliance with the rule. One commenter stated the rule did not address how FEMA would ensure compliance and enforcement of the FFRMS. The commenter noted FEMA would monitor and evaluate the implementation of the FFRMS by Federal agencies and recipients of Federal funds but did not specify how FEMA would do so. The commenter asked FEMA to provide more information and procedures on what mechanisms FEMA would use to verify that Federal actions complied with the FFRMS, what consequences FEMA would impose for non-compliance, and how FEMA would handle disputes or appeals regarding compliance. Another commenter also stated the rule did not include monitoring, evaluating, or compliance.

FEMA Response: FEMA currently leverages the 8-step process detailed in 44 CFR part 9 as the mechanism to implement Executive Order 11988 , as amended and will continue to use the 8-step process to monitor and verify compliance with the FFRMS. To monitor and evaluate the implementation of the FFRMS, FEMA will continue to rely on step 8 of the 8-step process. Step 8 of the process found at 44 CFR 9.6(b)(8) requires FEMA to review the implementation and post-implementation phases of the proposed action to ensure that the requirements stated in § 9.11 are fully implemented. Oversight responsibility is integrated into existing processes for each grant program. For each approved action, grant assistance is generally conditioned to follow the requirements determined Start Printed Page 56980 during the 8-step process. FEMA is not making changes to paragraph (b)(8) of § 9.6 in the final rule and will continue to use the current process to ensure compliance with the FFRMS. To address commenters' concerns regarding how the agency would address non-compliance, FEMA will rely on the provisions of 2 CFR part 200 . 2 CFR 200.339 also allows FEMA to take action to remedy a recipient's noncompliance with federal requirements, including those required by 44 CFR part 9 , such as imposing new conditions on the award or deobligating funding for the award if a recipient does not adhere to the requirements set forth during the part 9 review process. Disputes regarding compliance would follow the specific grant program's appeals process. [ 219 ]

Comments: Some commenters had questions regarding the costs associated with FFRMS implementation and whether or not implementation would result in delaying actions subject to the FFRMS. Some of these commenters raised specific concerns about increased costs. One commenter stated there would be a significantly increased cost of compliance for Federally funded projects as a result of the rule and stated the Federal government should bear the full cost of FFRMS implementation. The commenter also asked whether the FFRMS would be adopted for FEMA funding only or for all Federal agencies and whether the FFRMS would apply to Federally funded projects that are focused on flood damage reduction projects. Another commenter stated the FFRMS implementation, through higher vertical elevation or floodproofing, or other mitigation mandates, could significantly alter and raise the cost of water resource projects and ongoing operations and maintenance for water resources infrastructure systems, which were paid for by the local taxpayers. The commenter asked how the FFRMS would interface with other Federal agencies and impact non-Federal sponsor responsibilities for projects. A third commenter stated concern for the increased costs of meeting heightened standards and recommended FEMA identify opportunities to expand the agency's grants and otherwise reduce local costs to help ensure the new resilience standard did not prevent projects from going forward.

Two commenters raised concerns regarding equity and costs. One commenter stated the rule would increase the costs of Federally-funded projects and that while the higher standards would help decrease costs to the community and residents in the long term, the higher short-term costs could have the unintended effect of making needed projects infeasible, especially for communities of low-to middle-class incomes and taxbases. This commenter recommended FEMA work to increase funding to implement FFRMS through increasing grant funding cap ceilings, expanding funding opportunities, and lowering cost share requirements. Another commenter stated both the rule and FFRMS policy would potentially raise costs associated with Federal actions and implement ambiguous standards ill-suited to rural areas. The commenter stated the rule and FFRMS policy raised design standards for Federal actions, which would affect mitigation and public assistance projects for post-disaster recovery. The commenter stated the elevated design standards would increase project costs and these increased costs would be absorbed into applications and proposals for these projects. The commenter wrote that these projects already had limited available funding and were often prohibitively competitive for rural communities, creating an additional burden on these applicants.

FEMA Response: FEMA appreciates the commenters' concerns on the increased costs of projects and the commenter's requests to expand grant funding and grant funding caps, as well as lowering cost-share requirements. The cost of compliance with the FFRMS will be included in the total project costs and will be funded at each program's applicable cost-share. Some FEMA programs are capped in funding each year, thus, the additional costs of FFRMS requirements would not add to the total funding for these programs. The effects of the FFRMS requirements would be distributional within the existing funding caps and would not constitute new spending by FEMA. For disaster programs where funding is not capped, the application of the FFRMS will increase the total amount of funding provided under the program, and each project will be subject to the applicable cost-share. Cost-share requirements are determined consistent with specific grant program requirements.

As explained above, the FFRMS is only applicable to actions involving the use of Federal funds for new construction, substantial improvement or to address substantial damage to a structure or facility. This rulemaking is applicable only to FEMA-funded projects for FEMA programs such as IA, PA, and HMA, and grants processed by FEMA's GPD. This includes some flood damage reduction projects.

FEMA has always incorporated social concerns and economic aspects into the 8-step process as part of the practicability analysis. FEMA's revisions to part 9 reflect consideration of the type and criticality of the action involved, the availability and actionability of the data, and equity concerns in the implementation of Executive Order 11988 , as amended. FEMA also has an agency-wide initiative focused on reducing barriers and increasing opportunities so all people, including those from vulnerable and underserved communities, can get help when they need it. [ 220 ] FEMA reviews all proposed FEMA-funded actions for potential disproportionate and adverse human health and environmental effects on communities with environmental justice concerns using a standardized environmental justice compliance review process.

FEMA disagrees with the commenter's suggestion that the FFRMS is ill-suited to rural areas, as disasters impact all areas and flooding continues to increase across the United States, including in rural areas. [ 221 ] Rather, these areas can benefit from Federal investments that are more resilient to flooding. FEMA believes the FFRMS will ensure that Federal funding will result in more resilient rural communities, without overly burdening these communities as they seek to recover. While FEMA acknowledges some of the agency's grant programs have cost share requirements and that competition exists for FEMA funding, the agency has programs in place to assist rural and other disadvantaged communities. [ 222 ]

Comment: Two commenters stated concerns with delays. One commenter stated concerns with project delays regarding FEMA making the final decision on the information the applicant would use and making the final decision on how permitting agencies were processing and permitting federal actions. Another commenter raised similar concerns regarding permitting, stating the proposed rule and policy would create separate permitting standards for some Federal and non-Federal actions, adding complexity that necessitated additional expertise when administering local floodplain programs and disproportionately impacting rural communities that already lacked sufficient staffing and funding to administer these programs. This commenter also stated the proposed rule and policy would also lengthen project timelines for Federal actions. The commenter stated that FEMA making the decisions on both the information the applicant is using and how permitting agencies would process and permit Federal actions. The commenter stated this would add time, documentation, and coordination between local communities, project proponents, stakeholders, and even FEMA, for critical mitigation projects and urgent post-disaster recovery efforts that required expedience. The commenter requested that FEMA minimize red tape and expense for communities seeking to implement projects, as the proposed rule adds bureaucracy and increases the resources required to successfully implement meaningful projects.

Another commenter raised concerns regarding both costs and delays, requesting further clarification on whether the FFRMS allowed for FEMA funding to cover expenses associated with making necessary improvements and enhancements to roadways, bridges, and culverts or if the funding was only for the in-kind replacement of structures. The commenter stated additional funding should be considered for the delay in project delivery due to the application of the FFRMS.

FEMA Response: FEMA appreciates the commenters' concerns regarding project delays and costs. FEMA notes the determination on the information the applicant is using under part 9 has always been made by the agency and thus, FEMA does not anticipate administrative delays with projects as a result of that aspect of FFRMS implementation. The time taken to complete the 8-step process will be project specific. Additional time, documentation, and coordination may be necessary for projects subject to the FFRMS ( i.e., actions that involve new construction, substantial damage, or substantial improvement as they are typically the most complex types of actions that FEMA funds). As part of the final rule, FEMA adjusted for inflation certain thresholds that determine which actions are exempt from, or subject to, an abbreviated 8-step process. FEMA will also establish a procedure for future annual adjustments of these thresholds. The thresholds enable FEMA to exempt or expedite the requirements of 44 CFR part 9 by streamlining the process for those actions that offer little opportunity for alternate locations or actions, or minimization, due to practicability. These changes may mitigate, as to smaller projects, timing concerns raised by the commenters.

Regarding permitting actions, FEMA will provide additional guidance for the public and SLTT partners identifying what the FFRMS is, and how the agency will implement the updates to part 9 to assist applicants for FEMA-funded assistance programs. FEMA's regional offices will also provide technical assistance as part of the rule's implementation. For those SLTT entities that may be permitting actions, as explained above, FEMA's role under 44 CFR part 9 has not changed with this rule. The changes made in this final rule are to implement updates to Executive Order 11988 , as amended, and to otherwise update the 8-step process. Changes related to the floodplain determination implementing the FFRMS will only be applicable to those actions subject to the FFRMS as defined in the rule. FEMA notes this final rule does not apply to a local community's permitting processes under the NFIP's floodplain management regulations. Those regulations are found at 44 CFR part 59 et seq.

FEMA understands the final commenter's concerns regarding applicability of this rulemaking to improvements and enhancements to roadways, bridges, and culverts, as well as in-kind replacement of structures. In each scenario presented by the commenter, FEMA's funding is based on actual project costs for any FEMA-funded project. FEMA understands that any project may be delayed due to a variety of factors, and increased costs associated with those delays are generally part of the actual project costs. Additional costs incurred to comply with FFRMS would be eligible for FEMA funding.

Comment: Two commenters commented on the timing for implementing the rule. One commenter stated concern that the proposed changes could significantly restrict ongoing work. The commenter stated the proposed rule and policy did not identify when it would become effective, or how it would affect projects related to ongoing recovery efforts. The commenter requested the effective date be clarified and implemented so as to not disrupt ongoing recovery efforts. The other commenter requested FEMA consider “grandfathering” clause similar to the one provided in Executive Order 11988 .

FEMA Response: FEMA is issuing this final rule with an effective date of September 9, 2024. As explained in § 9.5(a)(3), FEMA will apply the FFRMS only to new actions for which assistance is made available pursuant to declarations under the Stafford Act that are commenced on or after the effective date of the final rule, and new actions for which assistance is made available pursuant to notices of funding opportunity that publish on or after the effective date of the final rule. Ongoing projects will not be impacted by this final rule. [ 223 ] FEMA does not believe a grandfathering clause is needed for this rulemaking.

Comments: Two commenters requested FEMA develop metrics for the rule and policy implementation. One commenter stated that creating metrics was essential. The commenter noted that the proposed policy outlined objectives but lacked specific metrics to gauge progress towards achieving them. The commenter stated the absence of suitable metrics guaranteed a transition into subjective assessments, making it impossible to balance trade-offs among objectives. The commenter recommended that FEMA establish appropriate metrics to ensure objective evaluation and avoid subjective interpretations. The commenter requested that FEMA include measurable metrics in the policy statement, allowing for a quantifiable assessment of advancement toward achieving well-defined and substantiated objectives.

Another commenter agreed that the policy statement establishes objectives without setting metrics for measuring progress towards those objectives. The commenter wrote the proposal was unbalanced, as it was confined almost exclusively to restrictions on floodplain occupancy and use, with no policy objective promoting economic development or even economic development rationally constrained by other considerations. The commenter stated that it is difficult to understand how the proposed regulation would be useful given the proposal's narrow focus on constraints and restrictions. The commenter wrote that although FEMA stated that the FFRMS would promote resilience, the NPRM apparently reflected FEMA's perspective that economic development had no place in resilience. The commenter recommended that the proposal be modified to establish the objective of economic efficiency in floodplain use and occupancy, while giving appropriate weight to the constraints on efficiency and development already inherent in the policy statement. Similar to the other commenter, this commenter stated that the proposal should be modified to express the metrics that would be used in establishing quantifiable progress toward clear and supported objectives. The commenter wrote that failing to establish appropriate metrics assured the effort would devolve into subjective evaluations where trade-offs among objectives became impossible.

FEMA Response: FEMA understands the commenters' concerns regarding measuring the effectiveness of the rule and policy; however, the agency disagrees that measurable metrics must be included in the regulation or policy to do so. FEMA disagrees that the absence of such metrics will result in subjective interpretations for the effectiveness of the rule and policy, as well as the FFRMS implementation for each action. FEMA's 8-step process and the results of the process are documented, and each applicant receives this information as part of the agency's compliance process. [ 224 ] FEMA will evaluate the effectiveness of the rule and policy as part of the agency's role in the IWG to reassess the FFRMS.

FEMA disagrees with the commenter that the rule and policy do not consider economic development. Consistent with Executive Order 14030 , [ 225 ] the FFRMS will prioritize Federal investment and conduct prudent financial management of Federal government resources to mitigate climate-related financial risk, while accounting for and addressing equity considerations and economic impacts. For individual actions, FEMA identifies and evaluates practicable alternatives to carrying out a proposed action in floodplains or wetlands. In determining the practicability of the alternatives, social concerns and economic aspects are considered in § 9.9. These requirements ensure that FEMA's approach to floodplain use entails consideration of specific community needs.

Finally, FEMA disagrees with the commenter that the agency does not consider economic development, as the 8-step process requires a practicability analysis that considers factors including economic aspects. FEMA thus does not believe the agency needs to revise the FFRMS policy's principles or the rule's policy statements to ensure economic aspects are considered.

Comments: Three commenters requested FEMA provide an appeals process. Two commenters wrote there was no viable process available to non-Federal entities to seek a review and adjudication of decisions made under the FFRMS. The commenters stated the impacts of the FFRMS would not be confined to the Federal government but would have far-reaching impacts on non-Federal public entities and the private sector. The commenters noted that Federal taxpayers should be protected from a Federal standard likely to impose costs without being subject to a benefits justification. The commenters recommended an appeals process be made available to non-Federal entities to review and adjudicate decisions made under the FFRMS. The third commenter requested an appeals process for communities that disagreed with a determination using the FFRMS. The commenters stated an appeals process would provide transparency and enable communities to have a voice in these important decisions that significantly impact them.

FEMA Response: FEMA does not believe a separate appeals process is required under part 9. FEMA conducts the 8-step process collaboratively with participation from applicants and grant program staff, with applicants having responsibility to provide information and participate in the process. [ 226 ] This collaborative process allows for resolution of disagreements and for FEMA to provide technical assistance on the requirements of 44 CFR part 9 . FEMA hopes to be able to resolve disagreements during this process so that a project may be made eligible. However, if a grant applicant disagrees with the application of the FFRMS and is subsequently denied funding for the project, the applicant should be able to avail itself of FEMA's existing appeals processes for its grant programs. [ 227 ] FEMA understands the commenter's concern regarding community participation but believes the current 8-step process sufficiently engages the public. FEMA will continue to notify the public at the earliest possible time of the intent to carry out an action in a floodplain or wetland and involve the affected and interested public in the decision-making process, as detailed further in § 9.8. Further, communities provide input into the floodplain determination for part 9. Pursuant to 44 CFR 9.11(d)(6) , if there is a more restrictive Federal, State, or local standard, it will be used. This includes the use of local CISA data and methods that have been adopted by a community for use in floodplain management, as long as such data results in a more Start Printed Page 56983 restrictive standard. FEMA values additional input from SLTT partners and the public in the 8-step process.

Regarding cost concerns, FEMA completed an analysis of the economic impact of this rulemaking, and the agency believes that the benefits of preventing property damage and potentially saving lives justify the costs of the rule. These benefits are a result of the improved protection of structures and facilities due to increased elevation and floodproofing standards in FEMA's implementation of the FFRMS. This rule will help to ensure that Federal investments are better protected from flood damage, and that the natural values of floodplains are preserved.

Comments: One commenter requested the rule require consideration of ways to prevent groundwater contamination when managing floodwater for use in water supply storage. The commenter suggested that the rule include provisions to pretreat or avoid the injection of “the first flush of stormwater runoff (generally the first runoff from 1.5 inches of rainfall), which can contain potential pollutants. The commenter also requested the rule acknowledge that MAR-related activities could be subject to other State and/or Federal regulations. Another commenter stated certain requirements for minimum conveyance, storage, and design criteria would be needed for all regional projects and watershed projects to ensure Federal funding eligibility with FFRMS implementation.

FEMA Response: FEMA understands the commenters' concerns but disagrees that any changes to the rule are required to ensure consideration of these issues. As previously explained, impacts are considered during the 8-step process including those referenced by the commenters. These considerations are not changing as part of this final rule and will continue to be utilized by FEMA when completing the analysis.

Further, Part 9 applies only to FEMA actions, and the FFRMS applies only to those actions where FEMA funds are used for new construction, substantial improvement, or to address substantial damage to a structure or facility for FEMA programs such IA, PA, and HMA, and grants processed by FEMA's GPD. Where applicants seek FEMA funding through these programs for the actions the commenters reference, part 9 applies.

Regarding a need to adapt design criteria, the FFRMS is a resilience standard that is applicable to structures and facilities. When considering design criteria, and particularly in cases where elevation as a minimization measure may not be feasible or appropriate for facilities, the FFRMS floodplain, determined according to the process described in section C of the FFRMS policy, establishes the level to which a structure or facility must be resilient. Resilience measures include using structural or nonstructural methods to reduce or prevent damage; elevating a structure; or, where appropriate, designing it to adapt to, withstand and rapidly recover from a flood event. To the extent practicable and in accordance with applicable grant program requirements, projects for facilities located within a FFRMS floodplain must be designed to help ensure resilience against flooding up to the flood elevation of the FFRMS floodplain.

Comment: A commenter requested the exception process for the FFRMS allow for appropriate balancing of the community's overall public health and safety priorities in project decisions. The commenter gave an example of a hospital being limited in making critical improvements because of the cost to incorporate the FFRMS as an example of where the community's overall well-being might be impacted.

FEMA Response: FEMA disagrees that a separate exception process is needed given the flexibility of the 8-step process. For individual actions, FEMA identifies and evaluates practicable alternatives to carrying out a proposed action in floodplains or wetlands. In determining the practicability of the alternatives, social concerns and economic aspects such as those raised by the commenter are considered in § 9.9.

FEMA will continue to notify the public at the earliest possible time of the intent to carry out an action in a floodplain or wetland and involve the affected and interested public in the decision-making process, as detailed further in § 9.8. FEMA values additional input from SLTT partners and the public in the 8-step process to help ensure FEMA actions meet community needs. FEMA notes any increased costs are generally eligible for funding under FEMA's assistance programs subject to cost share requirements.

Commenters had questions about how FEMA would coordinate with other Federal agencies when implementing the FFRMS. Commenters raised questions and concerns with how FEMA would work with other Federal agencies to implement the FFRMS and the interaction between the FFRMS and other programs such as the NFIP.

Comments: Commenters requested FEMA provide more information on how FEMA would complete coordination with other Federal agencies. A commenter requested clarification on how the agency would coordinate with other Federal agencies, and State and local governments to ensure consistent implementation of the FFRMS. One commenter asked how the primary agency would be determined and stated that many local agencies would not have the capability and capacity to navigate through different federal agencies with differing requirements for FFRMS implementation. Another commenter requested the proposed rule reconcile which agency's FFRMS procedures would be applied for projects with more than one Federal funding source. This commenter stated the NPRM did not provide a process to reconcile difference in requirements from different agencies and stated the differences between agencies that have already published FFRMS proposals. The commenter requested FEMA assure harmonization in the FFRMS criteria application across the Federal government. One commenter stated FEMA must also account for the central role that SLTT governments play in floodplain management, including designing climate resilience actions and implementing regulations. The commenter wrote consistent that expectations and procedures would benefit all sides by expediting interagency coordination and reducing confusion, delays, and accidental noncompliance.

FEMA Response: FEMA understands the concerns associated with consistent application of the FFRMS, and FEMA's FFRMS policy provides details on how FEMA will coordinate with other agencies when implementing actions in the same area as another Federal agency. See Section H, page 9. Specifically, FEMA's FFRMS policy states that when coordinating with other Federal agencies, FEMA will generally default to the FFRMS policy approach in FEMA's FFRMS policy, as appropriate. In addition, per 44 CFR 9.11(d)(6) , actions must be consistent with the NFIP, as well as any more restrictive Federal, State, or local floodplain management standards. Those floodplain management standards may include a more restrictive application of another Federal agency's FFRMS approach.

Additionally, FEMA's interagency consultative role in the broader implementation of the FFRMS across the Federal government, through the Start Printed Page 56984 agency's participation in the Interagency Working Groups and the FIFM-TF helps ensure consistent and effective implementation across the Federal government. FEMA's work in that context is intended to address the types of concerns raised in the comment regarding harmonizing application of the FFRMS criteria across the Federal government. Executive Order 11988 , as amended, further establishes the process by which the FFRMS will be reassessed in an interagency manner in conjunction with the WRC, the MitFLG, and the FIFM-TF. See Section 4(a) and (b).

FEMA understands the concerns raised by the commenters regarding local capability and capacity, and the agency will distribute additional resources to SLTT partners and the public identifying what the FFRMS is, and how the agency will implement the Executive Orders to assist applicants of FEMA-funded assistance programs. FEMA will also provide technical assistance through the agency's regional offices to support the FFRMS implementation. Additionally, FEMA notes the agency does consider the central role that SLTTs play in floodplain management. FEMA conducts the 8-step process collaboratively with participation from SLTT partners and grant program staff, with responsibilities and requirements for applicant participation in the 8-step process outlined in the long-standing requirements of 44 CFR 9.17 . FEMA also recognizes the role played by SLTTs in setting floodplain management standards for their communities. Pursuant to 44 CFR 9.11(d)(6) , a more restrictive Federal, State, or local standard will be used. FEMA believes the final rule and FFRMS policy outline consistent expectations and procedures for application of the 8-step process, minimizing confusion, delays, and accidental noncompliance.

Comments: Some commenters encouraged FEMA to engage with specific agencies when implementing FFRMS. One commenter encouraged FEMA to coordinate with other Federal agencies, such as HUD, SBA, USDA, DOE, DoD, to improve application and effectiveness of national floodplain standards. Another commenter suggested Federal agencies, including FEMA, NRCS, FWS, and others examine the efforts of Federal agencies to restore floodplains. The commenter stated their understanding that even for Federal agencies responsible for addressing water, soil, and habitat concerns, floodplain regulations are a significant barrier to restoration. The commenter stated the review of floodplain restoration efforts should not only cover the multi-million-dollar projects, but also include smaller-scale projects, as there are plenty of opportunities for small scale, impactful restoration projects that become too costly when implemented consistent with a regulatory process.

Another commenter requested that FEMA take a leadership role in tracking floodplain development on a national scale. The commenter stated there was no meaningful Federal commitment to track gains or losses in floodplain functions in the same way wetlands are tracked through the National Wetlands Inventory. The commenter referenced an estimate that 70 percent of the nation's floodplains had poor integrity due to development and alterations that limited floodplain functionality. The commenter noted this estimate provides a snapshot, but that it is essential to have nationwide statistics that allowed decision makers to understand and communicate floodplain loss. The commenter stated that floodplains are not broadly recognized by the public or decision makers for the valuable benefits they provide, and the lack of comprehensive, nationally-led data and analysis for floodplain functions has resulted in disjointed and unstable efforts focused on policy, funding, and communication in support of protecting and restoring floodplains in the United States, as well as a lack of data that allows an analysis of the impact that Executive Order 11988 has played. The commenter requested that FEMA, as the lead Federal agency charged with implementing a national floodplain management strategy, take a leadership role in tracking loss of functional floodplains as a component of the 8-step process when implementing Executive Orders 11988 and 13690. The commenter encouraged FEMA to work with HUD, the United States Geological Survey, the USACE, and other Federal agencies to track and quantify the effectiveness of the Executive Orders in avoiding floodplain development and preserving and restoring the natural and beneficial values of functional floodplains.

FEMA Response: FEMA's interagency consultative role in the broader implementation of the FFRMS across the Federal government, through the agency's participation in the Interagency Working Groups and the FIFM-TF helps ensure consistent and effective implementation. In this role, FEMA has coordinated, and will continue to coordinate, with other Federal agencies, including those listed by the commenters, on the FFRMS. Executive Order 11988 , as amended, further establishes the process by which the FFRMS will be reassessed in an interagency manner in conjunction with the WRC, the MitFLG, and the FIFM-TF. [ 228 ] See Section 4(a) and (b).

For individual actions subject to the FFRMS, FEMA will continue to coordinate with other agencies to expedite and unify the floodplain management review process, as detailed in the FFRMS policy. FEMA appreciates the commenter's concerns regarding floodplain restoration, but notes that the commenter's request for multiple Federal agencies to do a retrospective review of their efforts to restore floodplains is beyond the scope of this rulemaking, which involves updates to FEMA floodplain management regulations to implement the FFRMS. FEMA's regulations at part 9 address the commenter's concerns regarding the need to protect floodplains. Specifically, § 9.2 discusses the agency's policy to “restore and preserve the natural and beneficial values served by floodplains.” The final rule strengthens this policy by requiring the use of nature-based solutions when identified as a practicable alternative during the 8-step process as outlined in 44 CFR 9.9(b)(2) . Further, § 9.11(b) discusses how FEMA will take action to restore and preserve floodplains and wetlands. FEMA understands the need to include smaller-scale projects and the commenter's concerns regarding costs when complying with regulatory requirements but believes the rule and FFRMS policy helps address these considerations. The rule and FFRMS policy require FEMA to consider the type of criticality of the action involved, the availability and actionability of data, and equity concerns. Actions are only subject to the FFRMS if FEMA funds are used for new construction, substantial improvement, or to address substantial damage to a structure or facility.

FEMA understands the commenter's concerns regarding tracking floodplain development and the lack of a national inventory for floodplains similar to the National Wetlands Inventory. FEMA agrees that nationwide statistics could better support decision makers and encourages other Federal agencies to look across the spectrum of floodplain impacts for their own agency activities. However, FEMA has no statutory authority to mandate the more structured tracking system the commenter requests across the Federal government. Start Printed Page 56985

FEMA completed that analysis for the FFRMS consistent with its requirements under OMB Circular A-4. FEMA considered the costs and benefits associated with this rule, including the overall increased costs of FEMA projects, in the regulatory impact analysis provided on the public docket for this rulemaking. [ 229 ] FEMA believes that the benefits of preventing property damage and potentially saving lives justify the costs of the rule. These benefits are a result of the improved protection of structures and facilities due to increased elevation and floodproofing standards in FEMA's implementation of the FFRMS. This rule will help to ensure that Federal investments are better protected from flood damage, and that the natural values of floodplains are preserved.

Pursuant to OMB Circular A-4, agencies are required to monetize quantitative estimates whenever possible; however, if monetization is impossible, the agency must explain why and present all available quantitative information. An agency should also provide a description of the unquantified effects and the strengths and limitations of the qualitative information. FEMA requested public comments throughout the RIA because it was aware of the limitations of the data used to estimate the costs and benefits of the rule. FEMA's intention was to give the public the opportunity to submit data that was not available to FEMA at the time of publication of the NPRM but could help improve the estimates made for the final rule.

FEMA recognized in both its NPRM and RIA that there was a lack of actionable climate data for the FFRMS. FEMA expects that more data will be available as agencies implement the FFRMS, and that will be incorporated into interagency tools. FEMA further recognized that there was a limited amount of data available on the monetized benefits of freeboard that would be affected by the rule and requested comments from the public about whether there was available data that could be used for such estimates. FEMA conducted a quantitative benefits analysis for PA. Due to the limited quantitative analysis, FEMA also completed a qualitative analysis to meet its obligations under OMB Circular A-4 with respect to benefits by including the following: (1) literature reviews on the benefits of flood mitigation activities; (2) reports which analyzed potential savings from damage avoidance associated with including freeboard in the construction of new residential structures in coastal areas at various freeboard levels; and (3) a description of qualitative benefits which included the potential for lives saved, savings in time and money from a reduced recovery period after a flood, increased safety of individuals, increased public safety, reduced personal and community impacts, and reduction in future health issues related to flooding.

With respect to the overall costs for the rule, FEMA met its obligations under OMB Circular A-4 by producing qualitative and quantitative measurements of the cost of the application of the FFRMS by each grant program. FEMA notes any increased costs for FEMA actions are generally eligible for funding under FEMA's assistance programs subject to cost share requirements.

Comment: One commenter raised several questions about the implementation of FFRMS for roadways, bridges, and culverts and how FEMA would engage with other Federal and non-Federal agencies. The commenter raised several questions about how the FHWA and the Department of Transportation (DOT) regulations would interact with FEMA's FFRMS implementation and requested FHWA regulations apply to these actions. The commenter raised questions on the use of State regulations and asked how the FFRMS would impact scour calculations and designs. The commenter asked how FEMA would determine when a nature-based approach would be used, stating that FHWA and many States had their own guidance for the use of nature-based approaches. The commenter also stated all of the FFRMS approaches indicated higher vertical flood elevations and an expanded horizontal floodplain and inquired as to whether elevating a structure would also include potential roadway grade changes and raising a bridge structure if viable for resilience as some locations.

FEMA Response: As explained previously, this rulemaking only applies to actions where FEMA funds are used for new construction, substantial improvement, or to address substantial damage to a structure or facility under FEMA programs such as IA, PA, and HMA programs, and grants processed by FEMA's GPD. FEMA does not fund repairs or improvements to Federal-aid roads, and this rulemaking would not be applicable to those roads. Rather, as the commenter states, the FHWA regulations would govern those actions. Where FEMA may provide funding, FEMA's FFRMS policy provides details on how FEMA will coordinate with other agencies when implementing actions in the same area as another Federal agency. See Section H, page 9. When coordinating with other Federal agencies, FEMA will generally default to the FFRMS policy approach in FEMA's FFRMS policy, as appropriate. Where FEMA provides funding for these activities, FFRMS applies to improve resilience to facilities against both current and future flood risks.

Section 9.11(d)(6) of the final rule states that even when FEMA is providing funding, a more restrictive Federal, State, or local floodplain management standard will be applied. States with more restrictive standards continue to govern these actions. Section G.2 of FEMA's FFRMS policy further discusses flood risk minimization for facilities and clarifies that FEMA would allow any specific method to be used to help ensure resilience against flooding up to the flood elevation of the FFRMS floodplain in conjunction with any other applicable codes and standards.

In response to the commenter's concerns regarding nature-based approaches and conflicts with other Federal and State requirements, Section A.2 of FEMA's FFRMS policy states “Applicability: The Natural Features and Nature-Based Solutions requirements of this policy apply to all Actions subject to the full 8-step decision-making process.” As explained in Section F, it should be used where possible. [ 230 ]

To address the commenters inquiry on whether roadway grade changes and raising a bridge structure would be required, FEMA begins any analysis by confirming applicability. As defined in § 9.4, a “structure” means walled and roofed buildings, including a temporary housing unit (manufactured housing) or a gas or liquid storage tank. The example provided by the commenter is not a structure under part 9 but rather a facility. As section G.2 of FEMA's FFRMS policy states, “[t]he FFRMS is a resilience standard. Particularly in cases where elevation may not be feasible or appropriate for facilities, the FFRMS floodplain, determined according to the process described in section C of this policy, establishes the level to which a structure or facility must be resilient. Resilience measures include using structural or nonstructural methods to reduce or prevent damage; elevating a structure; or, where appropriate, Start Printed Page 56986 designing it to adapt to, withstand and rapidly recover from a flood event.”  [ 231 ]

Comments: A commenter recommended FEMA engage through comprehensive consultations with local governments, non-Federal stakeholders, and regional experts to gather insights and refine the currently proposed national approach to ensure that policies aligned with regional differences and addressed specific challenges identified by stakeholders. The commenter also recommended FEMA develop a robust communication strategy to clarify the integration of local government systems and policy implementation with non-Federal stakeholders, while also creating a means of providing feedback throughout the FFRMS implementation process.

The commenter further stated that the roles, responsibilities, and authorities of non-Federal sponsors of actions might not align with FEMA's FFRMS proposed policy and requested FEMA clarify how non-Federal sponsors and other stakeholders would engage with and be affected by the rule. The commenter noted collaboration between non-Federal sponsors, communities, the USACE, and FEMA can yield significant benefits, but stated the collaboration was contingent on a clear, justified, and achievable delineation of agency and stakeholder roles and responsibilities. The commenter stated the FFRMS proposed rule and policy failed to address the roles of non-Federal stakeholders, which could significantly hinder non-Federal stakeholders' understanding of their responsibilities within the FFRMS framework. The commenter stated the FFRMS lacked an explanation of how the policy aligns with other floodplain-related policies. The commenter stated that this oversight might burden local non-Federal sponsors with additional responsibilities related to addressing property damage and new construction, potentially creating confusion and additional workload, and importantly, likely forcing non-Federal sponsors to assume duties outside their legal authorities and core competencies, and expose them to potential liability.

The commenter recommended that FEMA provide greater clarity on the roles of State and local government and other non-Federal stakeholders. The commenter requested that FEMA consider and accommodate the resource and legal boundaries of non-Federal stakeholders, ensuring that policies and directives were realistic and compatible with their authorities and available resources and tailoring requirements that align with the authorities of non-Federal stakeholders. The commenter stated this entailed revising policies to avoid mandating actions that fall outside the legal jurisdiction of non-Federal stakeholders.

FEMA Response: FEMA disagrees with the commenter that additional engagement to refine the FFRMS is required. In addition to the comment period in 2023, FEMA completed outreach regarding FFRMS in 2015 as part of the development and publication of the Revised Guidelines, as well as the agency's prior NPRM in 2016. [ 232 ]

FEMA understands the commenter's concern regarding the role of non-Federal partners, but that role in the 8-step process remains unchanged as a result of this rulemaking. FEMA values the collaboration and coordination with SLTT and other non-Federal partners in the 8-step process and will continue to engage with stakeholders and the public throughout the 8-step process to meet the needs of communities and stakeholders impacted by FEMA actions subject to this rulemaking. Specifically for applicants for federal financial assistance, 44 CFR 9.17 outlines the specific roles and responsibilities that exist for them in the 8-step process.

Comment: The same commenter stated the rule lacked clarity on integration with local government systems and communications regarding policy implementation with non-Federal stakeholders. The commenter stated this oversight raised doubts about adaptability and alignment with existing regional policies, potentially leading to conflicts and inefficiencies in implementation. The commenter raised concerns regarding the removal of Flood Hazard Boundary Maps (FHBM) stating that the removal resulted in a lack of clear alternatives or specific evaluation methodologies tailored to different regions and thus failed to ensure region-specific evaluations and risks in applying standards uniformly across diverse regions. The commenter stated a “one-size-fits-all approach” overlooked the complexity of regional flood dynamics and other variabilities, leaving critical questions unanswered. The commenter stated a tailored, regionally sensitive strategy was imperative to ensure diverse regional needs and variations were appropriately considered and integrated into any proposed policies.

FEMA Response: FEMA understands the commenter's interest in ensuring effective integration with local government systems and communications with non-Federal stakeholders but disagrees that the agency's rulemaking and FFRMS policy are lacking. Rather, the rule at § 9.11(d)(6) ensures the use of any local standard that may be higher than that required under part 9 allowing for local differences to be considered and implemented. The commenter further misunderstands FEMA's edits to remove the term FHBM from the regulatory text. FEMA is not eliminating FHBMs from the 8-step process. As explained in the preamble to the NPRM, FEMA offers a range of flood risk products under the NFIP and categorizes these products as “regulatory” or “non-regulatory.” Regulatory flood risk products are created subject to procedural due process requirements, contain basic flood information, and are used for official actions such as identifying properties subject to mandatory flood insurance purchase requirements, or enforcing minimum building standards for construction in a floodplain in NFIP participating communities. Non-regulatory flood risk products are not tied to mandatory enforcement or compliance requirements for the NFIP and expand upon basic flood hazard information. References to FEMA's regulatory products under the NFIP, such as the FHBM, FIRM, and FIS are being eliminated in the regulatory text to allow flexibility to encompass the full range of NFIP products (both regulatory and non-regulatory) available for use with the 8-step process. For example, Start Printed Page 56987 the existing § 9.7(c) prescribes a sequence of steps to obtain the floodplain, flood elevation, and other information needed.

FEMA has made, and will continue to make, floodplain determinations partnering with applicants in the 8-step decision-making process. As explained in the NPRM, FEMA will use best available information, which may include information that is non-regulatory or FEMA preliminary flood hazard data. To be designated as the best available information, the information must be at least as restrictive as the information provided by effective FIRMs. FEMA published the FFRMS Job Aid to further explain how the agency will make these determinations with the implementation of FFRMS.

Further, as previously explained, SLTTs can provide input into the determination. As explained above, FEMA will use a more restrictive Federal, State, or local standard for actions under part 9. This includes the use of local CISA data and methods that have been adopted by a community for use in floodplain management, as long as such data results in a more restrictive standard. Allowing the use of local data helps resolve the commenter's concerns that FEMA is not considering regional flood dynamics and other variabilities.

Comments: Two commenters discussed outreach associated with the rulemaking process. One of the commenters expressed support for the extensive public outreach completed between 2015 and 2021 on the FFRMS. The other commenter requested FEMA reengage with States and local communities on the FFRMS proposed rule and policy. The commenter noted the floodplain program is administered at the local level and stated FEMA failed to conduct sufficient outreach or even hold a single public meeting to help explain the elaborate and expansive changes. The commenter stated local administrators and community officials deserved sufficient time to understand the proposed rule and policy changes and develop informed comments on how it might affect their programs. The commenter asked that FEMA perform additional outreach to educate local floodplain administrators, elected officials, and emergency managers on the proposed rule and policy.

Some commenters requested FEMA provide additional outreach, training, technical assistance, and community engagement as part of the FFRMS implementation. One commenter requested training, outreach, and coordination at the program, departmental, interagency, and intergovernmental levels for successful implementation of FFRMS. The commenter requested FEMA provide technical resources including comprehensive guidance, maps and resources, and technical assistance. Another commenter requested FEMA provide guidance and training materials to stakeholders to ensure a comprehensive understanding and consistent application of the FFRMS. One commenter requested FEMA develop accessible guidance and tools to facilitate and improve the benefit-cost analysis for both nature-based solutions and hybrid green-gray infrastructure approaches. Another commenter recommended FEMA conduct virtual and in-person workshops and listening sessions to explain the FFRMS, changes to 44 CFR part 9 (including the 8-step process), including applications for FEMA grants under HMGP, FMA and BRIC. Another commenter stated appreciation for FEMA's plans to assist applicants with FFRMS and the 8-step process and encouraged the agency to seek sufficient funding to adequately staff such an effort.

FEMA Response: As one commenter noted, FEMA completed significant outreach and stakeholder engagement during the course of the FFRMS development and rulemaking processes. FEMA believes those outreach efforts were sufficient and additional public meetings for this rulemaking were not required. [ 233 ] FEMA disagrees with one commenter requesting the agency complete additional outreach to allow for public comment. Local administrators and community officials had an opportunity to submit comments on the proposed rule and policy changes, and FEMA notes some communities did submit comments on this rulemaking. FEMA will perform additional outreach to SLTT partners, stakeholders, and the public, including distribution of additional resources to assist in FFRMS implementation.

FEMA agrees that successful implementation will require training, outreach and interagency coordination and appreciates the commenters' suggestions on ways to achieve effective outreach. FEMA participated in the IWG on Flood Resilience to support the implementation of the FFRMS. FEMA continues to collaborate with the IWG and other interagency groups consistent with Executive Order 11988 , as amended, and the Revised Guidelines. FEMA will distribute additional resources to the public and SLTT partners identifying what the FFRMS is, and how the agency will implement the Executive Orders, and these resources will help applicants as they apply for FEMA-funded assistance programs. FEMA will also provide technical assistance through the agency's regional offices in support of FFRMS implementation. FEMA will also further consider the outreach options shared by the commenters as the agency begins FFRMS implementation after this rulemaking.

Comments: Commenters provided feedback on incorporating equity and environmental justice into the 8-step process. While commenters indicated support for FEMA's rule and FFRMS policy as a means of bolstering the agency's commitment to addressing equity and environmental justice when addressing flood risks, others requested additional clarification or provided recommendations on ways FEMA could further advance equity and environmental justice in the rule and FFRMS policy. Commenters requested the agency incorporate social, economic, and environmental concerns into the 8-step process. These commenters also requested more outreach to underserved communities and ways to address the increased costs of actions subject to the FFRMS.

One commenter stated that flood impacts are not experienced equally across communities in the United States, referencing policies such as redlining and lower tax rates as forcing underserved populations into flood-prone areas and resulting in those Start Printed Page 56988 communities facing disproportionately high risk from flooding. The commenter stated these communities have also been disproportionately impacted by the environmental degradation resulting from floodplain development, underscoring the relationship between floodplain management and environmental justice. The commenter stated underserved communities have faced inequities in the distribution of flood risk reduction resources, partially because of reduced capacity and opportunity to respond to flood hazards compared to more well-resourced communities. The commenter stated that, based on these inequities, any proposal to update floodplain management standards would have an outsized effect on underserved communities. The commenter requested that FEMA consider the implicit connections between the FFRMS and environmental justice and the potential impact on Federally-protected treaty rights to floodplain resources. The commenter also requested FEMA consider the long-term benefits—including economic benefits—that can result from stricter floodplain management standards and upfront investments to ensure more resilient development projects.

This commenter further recommended a regular environmental justice and Tribal treaty rights assessment to review unforeseen burdens or missed opportunities with environmental justice communities and Tribal treaty rights-holders, consistent with Justice40 after the rule takes effect. The commenter requested FEMA include a structure to ensure that Tribal, low-income, and frontline communities and communities of color would be elevated in refining how the FFRMS is used and updated over time. The commenter requested FEMA explore technical assistance opportunities to ensure support for low-capacity communities. The commenter requested FEMA incorporate FFRMS into the agency's Justice40 efforts and prioritize funding to Tribes and underserved communities to increase flood resilience, stating this prioritization was particularly important in places where a more protective standard for the floodplain could raise upfront project costs and impact affordability for low-income communities, taxpayers, and rate payers. Another commenter raised similar concerns regarding equity, environmental justice, and community engagement. The commenter stated that FEMA has the opportunity to explicitly advance and promote environmental justice within the rule and, consistent with Executive Order 14096 , FEMA should provide opportunities for the meaningful engagement of persons and communities with environmental justice concerns who are potentially affected by Federal activities. Quoting Executive Order 14096 , the commenter requested FEMA provide timely opportunities for members of the public to share information or concerns and participate in the decision-making processes; fully consider public input provided as part of the decision making processes; seek out and encourage the involvement of persons and communities potentially affected by Federal activities; and provide technical assistance, tools, and resources to assist in facilitating meaningful and informed public participation. The commenter recognized FEMA's actions to incorporate meaningful engagement with environmental justice communities, but requested FEMA recommit to that engagement through this rulemaking.

Two commenters recommended FEMA revise the rule to ensure it explicitly addresses environmental justice concerns. One of these commenters stated that despite FEMA's statement that the proposed rule would not have adverse impacts on communities with environmental justice concerns, experience along with scientific and policy analysis found that Federal policies such as the FFRMS would have distributional impacts across sectors and communities, especially overburdened and underserved communities. The commenter cited to specific studies reflecting the level of flood risk increase for some disadvantaged communities and stated FEMA should ensure the final rule advanced environmental justice by requiring the consideration of disproportionate and adverse effects on communities with environmental justice concerns. Another commenter stated similar concerns with FEMA's statement in the proposed rule that the agency did not expect the rule to have a disproportionate and adverse human health or environmental effect on communities with environmental justice concerns and requested FEMA explicitly advance and promote environmental justice considerations in the final rule. The commenter stated that equity and environmental justice concerns must be acknowledged and weighed in the analysis of all FEMA-funded projects. This commenter requested guidance, tools, and resources to ensure best practices are used in project planning and design. The commenter stated flood-prone land tended to be cheaper, disregarding hidden long-term costs and recommended FEMA strengthen transparency in the public's awareness of flooding risks in any community development and prioritize long-term safety over initial cost savings. Another commenter shared the concern raised by these commenters that FEMA did not consider environmental justice issues when drafting the rule and recommended FEMA actively promote environmental justice in the final rule. This commenter also referenced Executive Order 14096 and stated that climate-driven flood hazards were expected to disproportionately impact Black communities in the South. The commenter further stated some estimates indicated the Southeast stood to suffer the most economic damage due to climate change with incalculable social costs. The commenter provided additional statistics regarding flood risks and referenced a specific seawall project as an example of common failures to adequately consider environmental justice concerns in the context of floodplain adaptation.

FEMA Response: FEMA appreciates the commenters' concerns on the increased costs of projects, equity, environmental justice, and community engagement. FEMA is committed to meaningful engagement on environmental justice and understands that flood impacts are not always experienced equally across communities in the United States. The agency has always incorporated natural environment, social concerns, and economic aspects into the 8-step process as part of the practicability analysis, and this rulemaking will not change that practice. FEMA's revisions to part 9 reflect consideration of the type and criticality of the action involved, the availability and actionability of the data, and equity concerns in the implementation of Executive Order 11988 , as amended. FEMA also has an agency-wide initiative focused on reducing barriers and increasing opportunities so all people, including those from vulnerable and underserved communities, can get help when they need it. [ 234 ]

FEMA reviews all proposed FEMA-funded actions for potential disproportionate and adverse human health and environmental effects on communities with environmental justice concerns using a standardized environmental justice compliance review process. This final rule will not Start Printed Page 56989 change that process. As an environmental justice review takes place on all FEMA proposed actions, FEMA does not believe an additional assessment is needed in conjunction solely with this final rule. Further, FEMA and the applicant may consider potential impacts on Tribal treaty rights, where applicable, when evaluating the practicability of alternatives in the 8-step process. As this would occur for all actions that potentially impact Tribal treaty rights, FEMA does not believe an additional assessment is needed in conjunction with this final rule.

Regarding the commenter's request that FEMA provide a way for these communities to engage on updates to the FFRMS, FEMA notes the agency is not solely responsible for revisions to the FFRMS or the Revised Guidelines. The MitFLG in consultation with the FIFM-TF will reassess the FFRMS annually, after seeking stakeholder input, and provide recommendations to the WRC to update the FFRMS, if warranted based on accurate and actionable science that takes into account changes to climate and other changes in flood risk. The WRC shall issue an update to the FFRMS at least every 5 years. [ 235 ] Consistent with the requirements of Executive Order 11988 , as amended, the interagency will engage with SLTTs and the public, including Tribal communities for any updates to the FFRMS.

As noted by the commenter, there are connections between the FFRMS and environmental justice. The FFRMS seeks to continue to improve the resilience of communities, including communities with environmental justice concerns, and help preserve the natural values of floodplains. Likewise, under the 8-step process, FEMA and the applicant may consider potential impacts on Tribal treaty rights, where applicable, when evaluating the practicability of alternatives. FEMA appreciates the commenter's request to consider economic benefits from stricter floodplain management standards and upfront investments, and the agency did consider the costs and benefits associated with this rule, including the overall increased costs of FEMA projects, [ 236 ] in the regulatory impact analysis provided on the public docket for this rulemaking. 237 FEMA believes that the benefits of preventing property damage and potentially saving lives justify the costs of the rule. These benefits are a result of the improved protection of structures and facilities due to increased elevation and floodproofing standards in FEMA's implementation of the FFRMS. This rule will help to ensure that Federal investments are better protected from flood damage, and that the natural values of floodplains are preserved.

Regarding the commenters' concerns that FEMA provide opportunities for engagement and participation in the decision-making process, FEMA completed significant outreach in 2015 as part of the development and publication of the Revised Guidelines. That outreach included over 25 meetings across the country with State, local, and Tribal officials and interested stakeholders to discuss the Revised Guidelines and 9 public listening sessions that were attended by over 700 participants from State, local, and Tribal governments, and other stakeholder organizations to discuss the Revised Guidelines. [ 238 ] FEMA believes those outreach efforts were sufficient. [ 239 ] FEMA notes that, in addition to engagement on the FFRMS and rulemaking, FEMA's 8-step process incorporates community engagement into the process. FEMA will continue to notify the public at the earliest possible time of the intent to carry out an action in a floodplain or wetland and involve the affected and interested public in the decision-making process, as detailed further in § 9.8, as well as provide the public notice with a statement documenting the outcome of the 8-step process as detailed in § 9.12. Beyond all of the foregoing, FEMA also provides public notice for proposed actions under NEPA and other environmental planning and historic preservation laws and executive orders. This rulemaking will not change those requirements.

Additionally, to further engage with communities in the FFRMS implementation, FEMA will distribute resources identifying what the FFRMS is, and how the agency will implement the Executive Orders. These resources will help applicants as they apply for FEMA-funded assistance programs. FEMA's regional offices will also provide technical assistance in support of FFRMS implementation. FEMA anticipates these resources could be used in project planning and design, as requested by one of the commenters. Furthermore, FEMA has staff dedicated to assisting with implementation of environmental justice planning and compliance, and will develop further resources to assist in implementing environmental justice requirements.

FEMA agrees with the commenters that flood risk is not uniformly distributed. However, the agency does not believe changes to the regulatory text or policy are required to help ensure consideration of disproportionate and adverse effects on communities with environmental justice concerns. FEMA currently reviews all proposed actions in the 8-step process to identify and address any disproportionate and adverse human health or environmental effects on communities with environmental justice concerns to advance environmental justice. This process will not change as a result of this rulemaking.

Additionally, through the 8-step process, FEMA identifies impacts such as the flooding risks associated with the occupancy or modification of floodplains and wetlands and the potential direct and indirect support of floodplain and wetland development that could result from the proposed action. FEMA understands the commenter's concerns regarding potential hidden long-term costs of flood-prone land purchases. FEMA believes the agency's flood risk mapping efforts increase transparency in the public's awareness of flooding risks, and the agency's floodplain management Start Printed Page 56990 programs further advance understanding of the impacts of development in floodplains.

FEMA appreciates the final commenter's information and example of challenges of failing to consider environmental justice concerns in Federal projects. FEMA acknowledges that the project described by the commenter was not a FEMA-funded project, but values the input provided by the commenter on the challenges faced when failing to consider environmental justice. FEMA is committed to meaningful engagement on environmental justice and seeking public input on proposed actions. As explained above, FEMA seeks input from the public as part of its reviews under Executive Orders 11988, 11990, 12898 and 14096, as well as NEPA, among other environmental planning and historic preservation laws and executive orders and has dedicated staff and a commitment to additional resources on environmental justice specifically.

Comment: Three commenters requested edits to the regulatory text to advance environmental justice with two suggesting specific edits. One commenter requested FEMA revise § 9.2(d) to identify environmental justice and avoid disproportionate effects to communities with environmental justice concerns as policy priorities. Another commenter requested FEMA revise § 9.6(b)(2) by adding language consistent with HUD's proposed rule to state that “when the proposed activity is located in or affects a community with environmental justice concerns under Executive Order 12898 , public comment and decision making under this part shall be coordinated with consultation and decision making under HUD policies implementing 24 CFR 58.5(j) or 50.4(l) .” The commenter also requested FEMA revise the principles in the proposed FFRMS policy to include a new principle on environmental justice to state that FEMA would work to reduce adverse impacts on communities with environmental justice concerns and engage communities in decision-making processes if the Federal action is a concern to these communities. This commenter requested FEMA revise § 9.11 to ensure FEMA would promote mitigation and minimization measures to address any disproportionate and adverse flood risks affecting these communities. Another commenter requested FEMA revise § 9.10 to require consideration of disproportionate and adverse effects on communities with environmental justice concerns, whether direct, indirect, or cumulative. That commenter requested FEMA encourage proactive community engagement and community-led planning within the final rule and recommended FEMA reassess part 9 and incorporate language to codify the agency's commitments to environmental justice and community engagement.

FEMA Response: FEMA does not believe the proposed edits to the regulatory text or FFRMS policy are necessary to address the commenters' environmental justice concerns. As explained above, FEMA has always incorporated natural environment, social concerns, and economic aspects into the 8-step process as part of the practicability analysis. FEMA's revisions to part 9 in this rulemaking reflect consideration of the type and criticality of the action involved, the availability and actionability of the data, and equity concerns in the implementation of Executive Order 11988 , as amended. FEMA also has an agency-wide initiative focused on reducing barriers and increasing opportunities so all people, including those from vulnerable and underserved communities, can get help when they need it. [ 240 ] Further, as explained above, FEMA reviews all proposed FEMA-funded actions for potential disproportionate and adverse human health and environmental effects on communities with environmental justice concerns using a standardized environmental justice compliance review process. This final rule will not change that process.

FEMA does not believe the specific changes requested to revise § 9.2(d) to identify environmental justice and avoid disproportionate effects to communities with environmental justice concerns as policy priorities are necessary, given the agency's consideration of natural environment, social concerns, and economic aspects in the 8-step process and the agency's review of all proposed FEMA-funded actions under Executive Order 12898 and 14096. FEMA further does not believe specific regulatory text is required to implement Executive Orders 12898 and 14096, as the agency already implements these requirements through other FEMA policies and processes. [ 241 ] As with the changes requested to § 9.2(d), FEMA does not believe that adding an additional principle to the FFRMS policy is necessary, given the agency's consideration of social concerns, which may include equity, and other factors under § 9.9(c), and environmental justice reviews conducted under Executive Orders 12898 and 14096 for proposed actions.

In § 9.11, FEMA details the requirements when actions must be located within or will affect a floodplain or wetland. The provisions of that section, as proposed, can be used to address flood risks affecting communities, including any disproportionate and adverse flood risks. FEMA is also required to address any disproportionate and adverse human health or environmental effects of actions on communities with environmental justice concerns, to the greatest extent practicable and permitted by law.

FEMA believes that the wording in § 9.10 is sufficient without further edits to enable the Agency to identify potential direct and indirect adverse impacts associated with the occupancy and modification of floodplains and wetlands and the potential direct and indirect support of floodplain and wetland development that could result from the proposed action. In Step 4, FEMA considers a wide variety of factors in identifying potential impacts of an action that may be of relevance to communities with environmental justice concerns, including pollution, public health, safety, and welfare, and numerous others.

FEMA is not updating significant portions of the public notice process in this rulemaking with respect to public comment and community engagement, as FEMA does not believe the current notice process is inadequate. However, FEMA did update § 9.8(c)(4)(i) to incorporate notice through the internet or another comparable method. When notice is provided electronically, FEMA will also provide links to electronic versions of relevant maps. FEMA will continue to notify the public at the earliest possible time of the intent to carry out an action in a floodplain or wetland and involve the affected and interested public in the decision-making process, as detailed further in § 9.8.

Comments: Several commenters expressed specific support for FEMA's revisions to part 9 and the FFRMS policy to further incorporate nature-based solutions into the 8-step process. Start Printed Page 56991 Commenters stated that the emphasis on natural features and nature-based approaches was important as these were innovative, sustainable solutions and aligned with other Federal, State, and local goals. Commenters requested FEMA implement these changes as soon as possible. Some commenters also requested that FEMA develop additional resources for nature-based solutions. One commenter recommended that FEMA require consideration of nature and nature-based approaches early in the 8-step process. The commenter stated that doing so was critical to protecting floodplain values, minimizing impacts to natural areas, ESA-listed species, and Tribal treaty rights, and effectively building resilience to flood impacts. The commenter requested that FEMA consider nature-based solutions in step 2 during public notice and that FEMA continue to provide and publish the best examples of where nature-based approaches were applied and led to flood risk reduction benefits. A commenter, while supporting FEMA's requirement to use natural features and nature-based approaches where possible, recommended that FEMA clearly assert the criteria that would satisfy the use of natural features and nature-based approaches either in the final rule or additional guidance.

FEMA Response: FEMA appreciates the commenters' discussion of the importance of natural features and nature-based approaches and agrees that it is important to implement these changes with this final rule in a swift manner. FEMA's policy will be reassessed on a four-year cycle to ensure the approach continues to meet the goals of Executive Order 11988 , as amended.

Regarding the commenter's request for consideration of nature-based solutions early in the 8-step process, FEMA's process at step 2 is to solicit any pertinent input from the public after the location determination for the proposed action and before the agency has made any decisions regarding practicable alternatives. Step 2 allows the public to provide information on potential alternatives, including nature-based solutions. FEMA notes the proposed action in step 1 may also incorporate nature-based approaches, which the public can comment on in step 2. FEMA does not believe the language of the regulatory text needs revision to address the concerns raised by the commenter as the agency's practice already incorporates the process outlined.

FEMA's FFRMS policy provides more information on the criteria to satisfy the use of natural features and nature-based approaches. FEMA plans to provide resources that will incorporate additional examples of nature-based approaches and will coordinate with other Federal agencies regarding the use of nature-based solutions as part of the FFRMS implementation and beyond. FEMA will distribute these and other resources for the public and SLTT partners to help applicants for FEMA-funded assistance programs. FEMA's regional offices will also provide technical assistance in support of the final rule's implementation.

Comment: A commenter requested FEMA further amend part 9 to clarify that that nature-based solutions must be considered in all cases, and documentation should be provided where such approaches were ultimately found to be not practicable.

FEMA Response: FEMA believes that the final rule addresses the commenter's concerns as nature-based solutions must be considered in all instances where alternatives can be considered in the 8-step process. FEMA's procedures for review of its actions under part 9 include documenting the 8-step process and will incorporate documentation of nature-based solution consideration as part of that process.

Comments: Two commenters requested FEMA remove “where appropriate” under Step 5, proposed § 9.6(b)(5), which stated that FEMA would integrate natural systems, ecosystem services, and nature-based approaches “where appropriate.” In contrast, two commenters requested FEMA recognize situations where nature-based solutions would not be appropriate. A commenter wrote because Executive Order 11988 , as amended, recognized nature-based approaches were not always possible or practical, that FEMA's rule must recognize situations where nature-based approaches were infeasible. The commenter stated that while nature-based approaches might be preferred, they might not always provide the optimal or even the most cost-effective solutions and recommended that FEMA incorporate language into part 9 requiring the agency to recognize the role of State and local agencies in ultimately approving nature-based approaches for addressing impacts to wetlands and floodplains when determining the practicability of the alternatives set out. Another commenter stated while nature-based and hybrid approaches could be prioritized, they may not be feasible to protect all infrastructure.

FEMA Response: The language “where appropriate” is important, as not all actions can integrate natural systems, ecosystem services, and nature-based approaches. FEMA funds a range of actions, and not all of those actions can utilize nature-based approaches. For example, FEMA funds structure repairs, and those types of repairs generally could not utilize a nature-based approach as an alternative.

FEMA's regulation and policy require the incorporation of nature-based approaches into the development of alternative actions to the extent possible, consistent with Executive Order 11988 , as amended. In addition, FEMA's FFRMS policy clarifies that nature-based approaches can also be incorporated as minimization measures where they are not possible as a practicable alternative. However, nature-based approaches will only be implemented where appropriate. Nature-based approaches are subject to the practicability analysis which relies on the factors identified in § 9.9(c). Those factors include legal constraints such as where state or local law is conflicting. For an alternative to be considered practicable, it must meet the need of the action FEMA is taking. Additionally, § 9.11(d)(6) requires FEMA to utilize any higher Federal, State, or local standards in the 8-step process.

Nature-based solutions apply to any FEMA-funded action that requires an analysis of alternatives, not just those that are subject to the FFRMS (new construction, substantial damage, or substantial improvement). The FFRMS applies to grants for certain projects under FEMA programs such as IA, PA, and HMA programs, and grants processed by FEMA's GPD. All Federal agencies will utilize the Revised Guidelines for their own FFRMS implementation.

Additionally, FEMA disagrees that additional language is required in part 9 to recognize the role of State and local agencies in the process for determining when nature-based solutions may be practicable for a particular action. FEMA conducts the 8-step process collaboratively with participation from SLTT partners and grant program staff, with responsibilities and requirements for applicant participation in the 8-step process outlined in the long-standing requirements of 44 CFR 9.17 . FEMA will work with SLTTs to determine what practicable alternatives may exist, including nature-based solutions.

Comment: A commenter recommended that FEMA apply nature-based approaches beyond the practicable alternatives analysis. The Start Printed Page 56992 commenter stated that the underlying assumption of the proposed rule was that nature-based approaches offered an alternative to reduce the effects of a traditional development project. While supporting the requirement to avoid floodplains and wetlands impacts, the commenter requested the rule also acknowledge that floodplains and wetlands restoration is an important flood risk reduction strategy in its own right. The commenter stated that Federal, State, and non-profit entities are focused on restoration efforts and that their investments are needed to accelerate the use of nature-based flood risk reduction strategies such as wetland and floodplain restoration. The commenter acknowledged that some of their comments may be outside the scope of the rulemaking, but stated that they submitted such comments because floodplain regulations and management are critical to whether we have more, less, or an indifferent amount of federal investments in nature-based approaches to floodplain restoration across the nation. The commenter stated that the nation desperately needs more floodplain restoration if we're going to move from reacting to disasters to being proactive and delivering on the multitude of co-benefits that healthy floodplains provide.

FEMA Response: FEMA appreciates the commenter's concerns but as explained in the preamble to the NPRM, 44 CFR part 9 only applies to FEMA actions. The FFRMS applies to grants for projects under FEMA programs such as IA, PA, and HMA, and grants processed by FEMA's GPD. All Federal agencies have their own requirements to implement the 8-step process and will utilize the Revised Guidelines for their own FFRMS implementation.

FEMA values the commenter's focus on the importance of nature-based approaches and will integrate these approaches where appropriate in actions under the 8-step process. FEMA-funded actions largely are identified by State and local applicants who design projects to meet their own communities' needs, which may include floodplain and wetland restoration. However, FEMA's mission extends beyond these actions, and the agency cannot eliminate the need to consider other types of actions such as the repair and replacement of public structures and facilities, such as schools and roadways. When evaluating such actions, FEMA will consider the practicability of nature-based approaches consistent with this rule.

Comment: One commenter also stated support for FEMA's use of nature-based solutions in the rule but stated the lack of examples and lack of a clear hierarchy when choosing among available solutions could diminish the impact of the agency's requirement. The commenter recommended FEMA require that alternatives protect and/or restore natural features and ecosystem processes to the maximum extent possible before resorting to other means; that nature-based approaches be incorporated to the maximum extent possible after maximizing protection and/or restoration of natural features and ecosystem processes; and allowing use of grey infrastructure only after nature-based options were deployed to the maximum extent possible. Another commenter wrote that where avoidance was not possible, landscape-level resilient design including green infrastructure and nature-based solutions should be incorporated meaningfully, even for activities that may not adversely impact floodplain function, to benefit and improve the resilience of surrounding communities. A third commenter recommended FEMA encourage and incentivize higher functioning nature-based approaches on acquired properties, stating that mitigation project applicants were often encouraged to simply grade and seed a parcel leaving ongoing maintenance concerns with only a minimal natural benefit. This commenter also requested that FEMA require documentation on the nature-based approaches considered and justification for the inclusion or exclusion. Finally, another commenter recommended that FEMA incorporate more information on when and why nature-based solutions would be appropriate alternatives to consider in Steps 3 and 6 and highlight best practices, such as wetlands preservation. The commenter added that part 9 should more specifically and clearly promote these approaches to ensure that FEMA consistently identified and pursued opportunities to restore natural and beneficial floodplain functions within or near the project site as a part of potential risk mitigation strategies. The commenter recommended FEMA add a subsection to § 9.11 discussing the benefits of these measures and specifying approaches that could be incorporated into project plans.

Two commenters recommended FEMA revise § 9.9(b)(2) to specifically identify wetlands restoration and preservation as a uniquely valuable complement or alternative to grey infrastructure. Another commenter requested FEMA incorporate stronger language on when and how to apply nature-based solutions and to highlight best practices, such as wetlands preservation.

FEMA Response: FEMA does not believe the final rule requires revision. FEMA's actions are focused on protection of life, safety, and improved property and FEMA does not typically fund actions that solely protect natural features and ecosystems. As such, FEMA is not necessarily taking actions where alternatives to protect natural features and ecosystem processes to the maximum extent possible are appropriate before resorting to other means. FEMA believes the commenter's concerns regarding wetlands preservation are already addressed in this final rule. Wetland conservation and restoration would be included under natural systems, ecosystem processes, and nature-based approaches provided in § 9.9(b)(2) as amended in this final rule. Additionally, the existing practicability factors set forth in § 9.9(c), including the natural environment factor, is sufficient to address the commenter's concerns.

FEMA prefers not to limit the regulatory text and instead provide additional information through FFRMS implementation resources to address the commenter's concerns. As explained above, the FFRMS policy does provide more information on the criteria to satisfy the use of natural features and nature-based approaches and FEMA plans to provide additional resources. These resources will incorporate additional examples of and information on nature-based approaches, such as the value of Indigenous knowledge and Traditional Ecological Knowledge (TEK). Where both a nature-based solution and a grey infrastructure solution are practicable, FEMA plans to generally prioritize the nature-based solution over a grey infrastructure solution as the commenter recommends. In addition, FEMA's FFRMS policy clarifies that nature-based approaches can also be incorporated as minimization measures where they are not possible as a practicable alternative. Further, as explained above, FEMA's procedures for review of its actions under part 9 include documenting the 8-step process and will incorporate documentation of nature-based solutions considered as part of that process. FEMA will distribute additional resources for the public and SLTTs as detailed above to further assist applicants when applying for FEMA programs.

Comment: Another commenter asked how FEMA would determine when nature-based solutions should be used. The commenter stated the FHWA and many State DOTs were developing or Start Printed Page 56993 had developed their own guidance for these items for riverine and tidal environments and that those agencies should be allowed to use their policies to fit specific projects.

FEMA's approach for facilities is meant to be flexible. As section G.2 of FEMA's FFRMS policy states “[t]he FFRMS is a resilience standard . . . Resilience measures include using structural or nonstructural methods to reduce or prevent damage; elevating a structure; or, where appropriate, designing it to adapt to, withstand and rapidly recover from a flood event.”  [ 242 ]

Comment: A commenter wrote to commend FEMA for incorporating reduced discount rates in the cost-benefit analysis of nature-based solutions. The commenter requested FEMA continue bolstering accountability in the assessment process by requiring practitioners to clearly describe the nature-based alternatives that were considered, and in cases where they are ultimately deemed not practicable, to provide an explanation and analysis for their reasoning as part of the final rule.

FEMA Response: FEMA appreciates the commenter's support and will continue to provide guidance to help communities recognize and capture the long-term benefits of nature-based solutions and all resilience actions in evaluating practicable alternatives and analyzing projects for cost-effectiveness.

FEMA's regulation and policy require the incorporation of nature-based approaches to the extent possible. In addition, FEMA's FFRMS policy clarifies that nature-based approaches can also be incorporated as minimization measures where they are not possible as a practicable alternative. As explained above, FEMA's procedures for review of its actions under part 9 include documenting the 8-step process and will incorporate documentation of nature-based solution consideration as part of that process.

Comment: A commenter requested FEMA more explicitly emphasize the protection and restoration of floodplain functions and nature-based alternatives when taking Federal actions in the floodplain by adopting rules that define the values of floodplains, the ecosystem processes or functions of floodplains that generate those values, and the attributes that are necessary for a floodplain to be “functional.” The commenter stated FEMA's rule failed to adequately describe the bio-geomorphology of a functional floodplain and the physical attributes of the floodplain necessary to obtain those values.

FEMA Response: FEMA appreciates the commenter's suggestion to integrate bio-geomorphology and attributes of functional floodplains into the regulation but does not believe additional changes are appropriate to the final rule or FFRMS policy based on the commenter's concerns. FEMA's definition of the floodplain in this rule is generally consistent with the definition of floodplain in the NFIP and with FEMA and other agencies' historic approach to such definitions and is intentionally broad to help ensure the agency can meet the needs of the action and protecting floodplains and wetlands consistent with Executive Order 11988 , as amended. For application of the FFRMS, FEMA defines specific floodplains in part 9 as using one of the approaches detailed in the FFRMS policy.

Concurrently, FEMA conducts other environmental and historic preservation reviews to determine whether proposed actions could have other impacts to or within floodplains and wetlands. FEMA is incorporating nature-based solutions into resilience efforts where appropriate and believes the final rule will help accomplish this goal. FEMA's regulation and policy do require the incorporation of nature-based approaches to the extent possible. In addition, FEMA's FFRMS policy clarifies that nature-based approaches can also be incorporated as minimization measures where they are not possible as a practicable alternative.

Comment: A commenter stated nature-based design elements and nature-based solutions allowed a structure to actively provide carbon sequestration, decrease the magnitude and frequency of maintenance leading to increased structural lifespan. The commenter recommended FEMA incorporate this alternative to traditional concrete as a nature-based solution to serve as a mitigation measure and design alternative.

FEMA Response: FEMA will use a range of nature-based solutions where possible and on a case-by-case basis depending on the project. Project location, including whether coastal or not, will be a factor in determining the types of available nature-based solutions FEMA may implement.

Comments: One commenter provided recommendations to encourage resilient design. The commenter supported FEMA's proposed changes to §§ 9.9 and 9.11, which in the commenter's view would increase climate resilience, but recommended FEMA require that the alternatives analysis process incorporate the consideration of an array of flood mitigation practices and feedback from state and local leaders. The commenter requested changes to §§ 9.9 and 9.11 to emphasize the effectiveness and benefits of landscape-level methods as effective alternatives to increase flood resilience and as mitigation for projects with no practical alternatives outside of the floodplain and incorporate landscape-level design strategies in developing alternatives. The commenter requested FEMA consider existing State, local, and non-governmental resilient design guidelines for the agency's own guidance and requested FEMA work with other Federal agencies to develop case studies and examples of projects that achieve appropriate resilience metrics in lieu of or in addition to elevation. Another commenter requested FEMA look for impacts beyond the project boundaries and requested FEMA consider off-site impacts and mitigation measures. The commenter recommended the rule's implementation and guidance emphasize the effectiveness and benefits of landscape-level practices that encompass the full property, not just the physical building site, to mitigate flood impacts for projects with no practical alternatives outside of the FFRMS floodplain. The commenter requested FEMA offer guidance to include development practices, such as No Adverse Impact or low-impact development, and landscape features and that any guidance should encourage projects to assess opportunities to restore the natural and beneficial functions of the floodplain and wetlands within or near the project site as a part of potential risk mitigation strategies.

FEMA Response: FEMA agrees that the rule will increase climate resilience. FEMA's current alternatives analysis process incorporates consideration of a range of flood mitigation practices. FEMA considers the following alternatives: (a) no action; (b) alternative locations; and (c) alternative actions, including alternative actions that use natural features or nature-based Start Printed Page 56994 solutions. Where possible, nature-based solutions, including those at the landscape-level, shall be used. Where natural features and nature-based solutions are not practicable as an alternative on their own to meet the needs of FEMA applicants, natural features and nature-based solutions may be incorporated into actions as minimization measures.

As explained above, the flood minimization measures found in § 9.11 are reliable methods of providing resilience to structures. FFRMS flood resilience measures consider both current and future flood risks to better protect Federal investments. The elevation requirement in § 9.11(d)(3) applies to structures and also allows floodproofing for non-residential structures. The FFRMS policy provides further explanation that structures that must be located within the FFRMS floodplain must be elevated or floodproofed to the FFRMS flood elevation. Additionally, the policy clarifies further that facilities can use elevation or any other appropriate minimization measure to protect the facility against the FFRMS flood elevation.

FEMA does not believe the final rule requires edits to address the commenters' concerns. As the commenter notes, FEMA's policy provides more detail on how the agency will implement nature-based solutions, and FEMA believes this level of detail is best provided in policy and additional resources rather than directly in the regulatory text.

As explained above, communities provide input into the floodplain determination for part 9. Pursuant to 44 CFR 9.11(d)(6) , a more restrictive Federal, State, or local standard will be used. This includes the use of local CISA data and methods that have been adopted by a community for use in floodplain management, as long as such data results in a more restrictive standard. FEMA values additional input from SLTT partners and the public in the 8-step process. Projects subject to FFRMS are frequently designed by such partners and will continue to be designed to meet local needs as appropriate.

FEMA will distribute additional resources for the public and SLTT partners identifying what the FFRMS is, and how the agency will implement the Executive Orders. These resources will help applicants as they apply for FEMA-funded assistance programs. FEMA will also provide technical assistance through the agency's regional offices in support of FFRMS implementation.

Comment: A commenter requested FEMA consider the life of the project when making flood risk protection decisions and emphasize the life of the project in the 8-step process, not just in the footprint of the project but its impact on the surrounding area. The commenter also requested the analysis of practicable alternatives result in an adequate assessment and documentation of the life cycle impacts of nature-based approaches and natural features.

FEMA Response: As explained further in the FFRMS Job Aid, [ 243 ] service life is considered in the determination of the FFRMS floodplain using CISA. Additionally, in the 8-step decision-making process FEMA considers whether a proposed action would be located within and whether it would affect a floodplain or wetland; FEMA avoids Federal actions in floodplain and wetland locations unless they are the only practicable alternatives and are able to minimize harm to and within floodplains and wetlands.

Further, the service life of the project is considered as part of the practicability analysis, including consideration of maintenance requirements. FEMA's procedures for review of its actions under part 9 include documenting the 8-step process and will incorporate documentation of nature-based solution consideration as part of that process.

Comments: Some commenters requested additional clarification or provided recommendations regarding how FEMA identifies and preserves wetlands as part of the 8-step process. Four commenters requested FEMA improve wetlands identification in the 8- step process. One commenter noted that FEMA reviewers currently consulted additional sources of information only if other listed sources provide inadequate information, which could mean a FEMA reviewer would stop the assessment after consulting the National Wetlands Inventory (“NWI”). The commenter stated the NWI was only one imperfect source and could not provide a definitive determination, as the NWI documented only the presumed presence of wetlands on a site and did not accurately capture the full delineation of wetlands at ground-scale. Two of the commenters requested FEMA update the regulatory text by directing reviewers to conclude the assessment of whether or not an action was in a wetland after consulting each of the four sources of information. Two other commenters agreed stating the determination of the presence or absence of a wetland in the project site should not be based solely on the NWI because of the NWI's tendency to underestimate actual wetland areas. Those commenters recommended FEMA encourage consulting various sources beyond NWI. One commenter noted that involving a trained wetland delineator to assess wetland indicators (soil, vegetation, hydrology) and delineate wetland boundaries was crucial to prevent the loss of critical wetlands, especially considering their role in flood water storage.

FEMA Response: FEMA did not change the existing regulation or process for identifying wetlands. FEMA relies on the NWI to identify wetlands for the purposes of applying the 8-step process under 44 CFR part 9 but will also accept other determinations as provided by regulatory agencies or applicants. FEMA does utilize information from on-site evaluations, including for locations not included in the NWI; however, requiring an on-site evaluation of the presence of wetlands for every potential action would severely delay the provision of disaster assistance to impacted communities.

FEMA is not changing the current process in step 4 in this rulemaking and the implementation of the FFRMS would only expand the floodplain of consideration in step 4 of the 8-step process. FEMA did not eliminate consultation with the edits made to § 9.10. The edits made to § 9.10 are to the factors used to identify the impacts to proposed actions. Those edits were made for consistency with other edits made in the rule. Specifically, FEMA defines “natural and beneficial values of floodplains and wetlands” to mean the features or resources that provide environmental and societal benefits. FEMA added additional clarification that water and biological resources are often referred to as “natural functions of floodplains and wetlands” and also incorporated additional clarifying examples of water resource values, living resource values, cultural resource values, and cultivated resource values for more consistency with the Revised Guidelines and Executive Order 11988 , as amended. FEMA also edited paragraph § 9.10(d)(2) for consistency with edits made in § 9.4 defining the natural and beneficial values of floodplains and wetlands.

Comment: One commenter requested FEMA take action to preserve wetlands Start Printed Page 56995 in this rulemaking, requesting FEMA prioritize wetlands preservation and prevent harm to wetlands to the greatest extent of the agency's authorities. The commenter recommended FEMA prioritize policy solutions that incentivize and fund the preservation of all remaining wetlands and look to climate-smart wetland restoration to maximize benefits. Noting the recent Supreme Court decision in Sackett v. EPA, [ 244 ] the commenter requested FEMA act through this rulemaking to provide whatever protection it can for wetlands. The commenter explained the permitting process under section 404 of the Clean Water Act prior to the Supreme Court decision for filling wetlands and stated the Sackett v. EPA decision  [ 245 ] limited the scope of section 404.

The commenter requested FEMA incorporate prohibitions on certain types of activities in wetlands similar to prohibitions on certain types of activities in floodplains and provided the example of prohibiting HMA funding for new construction or substantial improvements in a floodway or new construction in a coastal high hazard area unless the action constituted a functionally dependent use or facilitates an open space use. The commenter suggested FEMA add language to § 9.11(d)(1) to prohibit new construction and substantial improvement in a wetland, except for a functionally dependent use; or a structure or facility which facilitates an open space use and also requested FEMA amend the HMA and PA Policy and Program Guides to reflect these changes.

Two commenters requested FEMA add language to the regulatory text regarding the agency's requirement to restore and preserve both floodplains and wetlands. One commenter wrote this requirement was implemented in § 9.11(f), where FEMA established that if an action harmed or degraded a floodplain or wetland, the agency must implement measures to restore the natural and beneficial values; however, the commenter stated FEMA did not provide direction on the measures to be used and the extent to which the natural and beneficial values must be restored. The commenter recommended FEMA provide the criteria that would satisfy the restore and preserve requirement in the regulatory text or in associated guidance. The commenter also recommended FEMA require federal actions result, as fully as possible, in no net loss of both acreage and function for floodplains and wetlands. The commenter recommended FEMA require the type and extent of mitigation that applicants must undertake to satisfy the “restore and preserve” language where floodplains and wetlands were known to be negatively impacted. Another commenter requested FEMA add “or restore” after “preserve” in all the appropriate places in the regulatory text.

FEMA Response: FEMA believes the commenters' regarding wetlands preservation concerns are addressed by the existing regulation. As stated in § 9.2(d) and § 9.11(e), FEMA's policy is to preserve and enhance the natural values of floodplains and wetlands when the agency has the opportunity to do so. FEMA's longstanding requirements in the final rule at 44 CFR 9.11(e) outline the agency's requirements to restore and preserve the natural and beneficial values served by floodplains and wetlands. FEMA does not believe additional changes to the regulatory text or FFRMS policy are needed to achieve the commenters' goal of wetlands preservation.

FEMA did not propose to change the way that the 8-step process is applied to wetlands, and is not doing so in this final rule. FEMA notes the definition of wetlands in 44 CFR 9.4 has always been much broader than that under the Clean Water Act (CWA). Thus, under current practice the 8-step process has been applied to wetlands regardless of their jurisdictional status under the CWA. FEMA believes this commenter's concerns are already addressed by the existing regulation.

Additionally, FEMA understand the first commenter's desire to prohibit certain actions in wetlands but again believes the current 8-step process adequately addresses the commenter's concerns. In the 8-step decision-making process, wetland sites are avoided where possible. FEMA takes no action in a wetland unless the importance of the wetland site clearly outweighs the requirements to  [ 246 ] :

(i) Avoid the destruction or modification of the wetlands;

(ii) Avoid direct or indirect support of new construction in wetlands;

(iii) Minimize the destruction, loss or degradation of wetlands; and

(iv) Preserve and enhance the natural and beneficial values of wetlands.

FEMA notes the 8-step process governs FEMA actions and the Sackett case does not apply in this context. While FEMA does consider new construction in wetlands, to include the placement of fill, and will also consider alternatives, the 8-step process is not an authorization or permitting process. Additionally, FEMA notes the process is only applicable to actions funded or performed by FEMA and not more broadly applicable to actions performed by SLTTs or individuals using non-Federal funding.

The revisions to part 9 in this final rule do not change FEMA's long-standing requirement as part of FEMA's implementation of Executive Order 11988 , as amended, and Executive Order 11990 to only perform or fund actions within or affecting wetlands if those actions are the only practicable alternative. FEMA considers alternative locations, alternative actions, nature-based solutions, and the no action alternative under the practicability analysis and will only perform or fund the action when there are no practicable alternatives. FEMA will minimize any adverse impacts when doing so. FEMA believes the commenter's concerns requesting revisions to § 9.11(d)(1) to add prohibitions on specific actions in wetlands are unwarranted given the agency's long-standing process that is not changing as a result of the changes made in this final rule or FFRMS policy.

FEMA's mission is to help people before, during and after disasters. While this focus on saving life and property allows for the restoration and preservation of the natural and beneficial values served by floodplains and wetlands, that is not the primary mission of the agency. Accordingly, the majority of FEMA's actions within floodplain or wetlands for repairs, replacement, or mitigation of risk to existing structures and facilities. Requiring no net loss in area or function of floodplains or wetlands would limit the agency's ability to assist disaster-impacted communities, as well as reduce risk within those communities. Additionally, requiring mitigation from disaster-impacted communities may prolong or inhibit their recovery process. FEMA instead relies on the alternatives analysis required by 44 CFR part 9 and takes no action within floodplains or wetlands unless there is no practicable alternative.

FEMA recognizes the concerns of commenter seeking edits to the regulation and guidance to provide criteria to satisfy the restore and preserve requirement, but again disagrees that such edits are necessary in regulatory text or the FFRMS policy to achieve the goals of floodplain and wetlands restoration and preservation. FEMA notes that in this rulemaking the agency did not make changes to the restore and preserve requirements in former § 9.11(e) other than updating the Start Printed Page 56996 numbering (this rule moves former § 9.11(f) to § 9.11(e)). FEMA will provide additional information and implementation resources to SLTT partners, stakeholders, and the public as part of the FFRMS implementation and will consider the commenter's suggestions regarding additional information on the criteria to satisfy the requirements of new § 9.11(e) when finalizing those resources. FEMA will also consider issuing further guidance through the agency's grant programs on this point.

Regarding another commenter's request to add “or restore” after “preserve” throughout the regulatory text, FEMA notes that the regulatory text is consistent with the long-standing policy outlined in 44 CFR 9.2 . Specifically, it is the agency's policy to “restore and preserve the natural and beneficial values served by floodplains” and “preserve and enhance the natural values of wetlands.” Where floodplains are addressed in the regulatory text, “restore and preserve” is used, whereas “preserve” is used for wetlands, except for § 9.11(e)(3), which combines the two priorities more broadly in relation to natural and beneficial values of floodplains and wetlands. This language is consistent with Executive Order 11988 , as amended, which directs agencies to “restore and preserve the natural and beneficial values served by floodplains,” and Executive Order 11990 , which directs agencies to “preserve and enhance the natural and beneficial values of wetlands.” FEMA notes that the language in Executive Order 11990 omits “restore” in connection to wetlands.

Comments: Some commenters requested additional edits to the public notice requirements of the 8-step process. One commenter requested more specific guidance about the types and amount of information the notice would provide and the extent to which impacts will be identified and explained to the public and recommended FEMA revise the regulation to require FEMA to make site maps electronically available with the rest of its public notice. Two commenters requested the rule encourage community engagement and community-led planning by requiring early engagement with affected communities to understand the parameters of risks and vulnerabilities with engagement extending into the project design and implementation. The commenter requested public engagement go beyond the existing notice requirements to mandate proactive and meaningful outreach to affected communities, allowing communities to provide input that engineers and developers may not have and improving the overall flood risk knowledge of communities. A third commenter recommended FEMA incorporate language to § 9.6 and § 9.8 to codify an emphasis on environmental justice by providing notice to individuals with limited English proficiency and individuals with disabilities, as well as communities or groups of people who are potentially affected and who are not regular participants in Federal decision-making. Two other commenters agreed with the recommendation for access to individuals with limited English proficiency.

FEMA Response: FEMA is not updating significant portions of the public notice process in this rulemaking, as FEMA does not believe the current notice process is inadequate. However, FEMA did update § 9.8(c)(4)(i) to incorporate notice through the internet or another comparable method. During the public notice process, FEMA will also provide links to electronic versions of relevant maps.

FEMA does accept public comments on proposed actions during both the early and final public notice periods, addressed in §§ 9.8 and 9.12. Early public notice allows the public to provide initial input on alternatives to be considered and potential issues with a proposed action, which may include specific measures to minimize flood risk. The final public notice allows for the public to review the decision-making process conducted by the agency and provide any input before the action is taken. FEMA notes community planning, such as hazard mitigation planning, can inform the 8-step process.

FEMA notes this final rule does not apply to a local community's permitting processes under the NFIP's floodplain management regulations. Those regulations are found at 44 CFR part 59 et seq. FEMA defines “action subject to the FFRMS” as “any action where FEMA funds are used for new construction, substantial improvement, or to address substantial damage to a structure or facility.” The FFRMS applies to grants for projects funding the new construction, substantial improvement, or repair of substantial damage under FEMA programs such as IA, PA, and HMA programs, and grants processed by FEMA's GPD.

FEMA routinely translates agency materials into languages other than English as appropriate  [ 247 ] and consistent with FEMA's Language Access Policy. [ 248 ] Specifically incorporating this policy into the rulemaking is not necessary, as FEMA's process is set forth in the Language Access Policy. [ 249 ] That policy governs how the agency would handle written translations, as appropriate and consistent with Executive Order 13166 , Improving Access to Services to Persons with Limited English Proficiency, the DHS Language Access Plan, and Section 308 of the Stafford Act, 42 U.S.C. 5151 , as applicable. In accordance with those existing requirements, FEMA ensures appropriate translations of public notices for the 8-step process. [ 250 ] FEMA also ensures individuals with disabilities have effective communication access to FEMA programs and activities, consistent with requirements under sections 504 and 508 of the Rehabilitation Act of 1973, 29 U.S.C. 794 , 794d , and FEMA's Section 504 Implementation Plan. [ 251 ]

Comment: One commenter requested FEMA implement a public tracking system of all FEMA actions that are subject to part 9. The commenter stated a tracking system would ensure the public could assess the cumulative impacts of a proposed action. The commenter also requested FEMA accept public comment on proposed actions.

FEMA Response: FEMA does accept public comments on proposed actions during both the early and final public notice periods, addressed in §§ 9.8 and 9.12. Early public notice allows the public to provide initial input on alternatives to be considered and potential issues with a proposed action. Start Printed Page 56997 The final public notice allows for the public to review the decision-making process conducted by the agency and provide any input before the action is taken. The agency has updated the rule to allow for electronic notification of public notices to increase accessibility to the public.

FEMA appreciates the commenter's suggestion that the agency provide a public tracking system for part 9. FEMA provides data on actions taken by the agency through the OpenFEMA Data Sets. [ 252 ] FEMA is not proposing any additional systems of record with this rulemaking.

Commenters provided feedback on FEMA's review of and requirements regarding impacts to floodplains and/or wetlands in part 9. While one commenter provided support for the rule's prohibition against locating a proposed action in a floodplain or wetland if a practicable alternative exists outside the floodplain or wetland in proposed §§ 9.6(b)(3) and 9.9(d)-(e) and agreed with FEMA's approach of first avoiding impacts, then minimizing any impacts that must occur, and restoring impacted areas, other commenters provided recommendations for additional edits to the regulatory text.

Comment: One commenter requested FEMA revise § 9.10 to require consideration of disproportionate and adverse effects on communities with environmental justice concerns, whether direct, indirect, or cumulative.

FEMA Response: FEMA appreciates the commenter's concerns regarding equity and environmental justice. The agency incorporates natural environment, social concerns, and economic aspects into the 8-step process as part of the practicability analysis (addressed in 44 CFR 9.9 ). FEMA's revisions to part 9 reflect consideration of the type and criticality of the action involved, the availability and actionability of the data, and equity concerns in the implementation of Executive Order 11988 , as amended. FEMA also has an agency-wide initiative focused on reducing barriers and increasing opportunities so all people, including those from vulnerable and underserved communities, can get help when they need it. [ 253 ]

The impact analysis addressed in § 9.10 focuses on impacts to and from floodplains and wetlands associated with a proposed action. As part of the evaluation of impacts, FEMA considers the impacts addressed in § 9.10(d), which include factors that evaluate the impact of flooding on public health, safety, and welfare. In addition to this evaluation of flood hazard, FEMA reviews all proposed FEMA-funded actions for potential disproportionate and adverse human health and environmental effects on communities with environmental justice concerns using a standardized environmental justice compliance review process. FEMA believes these current practices address the commenter's concern, and revisions to the final rule are not necessary.

Comment: One commenter requested FEMA identify both the impacts on the floodplain and also the watershed in Step 4. The commenter noted that the subsequent steps in the process described consideration of this. The commenter also requested FEMA articulate and follow a “no adverse impact” principle. The commenter requested FEMA specifically address cumulative impacts of an action, as this is especially important when assessing flood impacts, as development actions and land use changes in a watershed would alter the floodplain.

FEMA Response: FEMA is not changing the current process in step 4 in this rulemaking. The implementation of the FFRMS would only expand the floodplain of consideration in step 4 of the 8-step process. The changes made in § 9.10 are intended as clarifying edits for consistency with other FFRMS implementing edits and are not substantive policy changes. FEMA did not propose the policy changes suggested by the commenter, and FEMA may take them under consideration in the future. Note that under step 1, FEMA considers whether proposed actions can impact or be impacted by a floodplain or wetland, not just whether or not the proposed action is located in a floodplain or wetland. This provision addresses the commenter's concerns regarding actions in the watershed impacting floodplains and wetlands.

Comment: Another commenter requested FEMA retain the language in current § 9.10(c) stating that “Regional Offices of the U.S. Fish and Wildlife Service may be contacted to aid in the identification and evaluation of potential impacts of the proposed action on natural and beneficial floodplain and wetland values.” The commenter stated that given USFWS's particular expertise in understanding coastal and wetland ecosystems, and the importance of maintaining the natural beneficial values of these habitats, the commenter recommended retaining the consultation language “rather than merely stepping it down to guidance.”

The commenter further recommended FEMA strengthen the language and require FEMA at least contact the USFWS when making any such evaluation in case the USFWS had concerns about or special understanding of the values of those habitats, including for threatened and endangered species.

FEMA Response: FEMA is not changing the current process in step 4 in this rulemaking and the implementation of the FFRMS would only expand the floodplain of consideration in step 4 of the 8-step process. This rule does not eliminate consultation with the edits made to § 9.10, as the existing regulatory text merely states the agency “may” contact the USFWS for impact identification on the natural and beneficial values of floodplains and wetlands. The edits made to § 9.10 removes this optional, internal U.S. government process from the regulation; the process will be further outlined in guidance. FEMA notes this section did not address FEMA's consultation requirements under the Endangered Species Act.

In this final rule, FEMA updates the definition of “natural and beneficial values of floodplains and wetlands” to include consideration of features or resources that provide environmental and societal benefits. The definition also includes examples of what “natural functions of floodplains and wetlands” means. FEMA does not believe additional edits to the final rule are required to address the commenter's concerns regarding coastal and wetland ecosystems and habitats for threatened and endangered species, because these concerns are addressed in the definition at 44 CFR 9.4 . The definition provides some examples but is not all inclusive, and FEMA will consider providing additional examples in guidance to further clarify and address the commenter's concerns.

FEMA edited § 9.10(d)(2) for consistency with edits made in § 9.4 defining the natural and beneficial values of floodplains and wetlands. Specifically, the edits to § 9.10(d)(2) add providing habitats and enhancing biodiversity under the living resource values FEMA will consider in step 4 of the 8-step process. In step 4, FEMA determines impacts to the floodplain, which include changes to the hydraulics and hydrology of the floodplain which informs potential impacts to protected species and their critical habitats. FEMA Start Printed Page 56998 will continue to perform Section 7 consultation under the Endangered Species Act as required. FEMA reviews all applicable actions under the Endangered Species Act, and such reviews are coordinated with the 8-step decision-making process.

Comment: While a commenter expressed appreciation of FEMA's recognition of the processes of storing floodwater and groundwater recharge, the commenter recommended the rule clarify that floodwater storage and groundwater recharge may have functions that extend beyond the time and area of a flood (such as the base flood). The commenter stated floodwater storage and groundwater infrastructure placed in the floodplain may result in continued inundation of floodplain areas. However, those types of infrastructure may be required to convey stored floodwater to groundwater recharge sites, minimizing impacts of flooding within the floodplain.

FEMA Response: Through the 8-step process, FEMA considers the impacts to and from the floodplain including the natural and beneficial functions of the floodplain and actions which may support development within the floodplain. Additional clarifications are not required in the regulatory text to address the commenter's concerns as the 8-step process resolves these concerns overall.

Comments: Some commenters requested FEMA prioritize avoidance of floodplains and wetlands as part of this rulemaking and FFRMS policy. Two commenters wrote a primary intent of Executive Orders 11988, as amended, and 11990 was avoidance of floodplains and wetlands development and stated avoidance was the most effective risk reduction strategy. Some commenters recommended FEMA issue guidance, with one comment recommending the guidance describe how regional offices should review projects post- Sackett v. EPA, [ 254 ] and strengthen the practicable alternatives analysis. Another commenter requested that the agency incorporate FFRMS guidance into PA and HMA guidance.

One commenter wrote the FFRMS was a process to assess the siting and design of a proposed action, rather than a mere elevation standard and requested FEMA promote avoidance as the preferred alternative to actions that would modify or occupy floodplains or wetlands. The commenter stated FEMA must consider design alternatives in Step 3 of the 8-step process at § 9.9. Three commenters wrote elevation and floodproofing were often prioritized instead and requested FEMA prioritize avoidance as the first alternative to actions that would modify or compromise floodplain function as the most effective risk reduction strategy, rather than using elevation or floodproofing as first design alternatives. Two commenters agreed that FEMA should strengthen Step 3 in § 9.9 to emphasize avoiding federal actions in floodplains and wetlands where practicable.

FEMA Response: While FEMA made edits to § 9.2(d) to reorder the agency's actions to prioritize minimizing the impact of floods on human health, safety, and welfare in this part, those edits do not change FEMA's long-standing requirement as part of implementation of Executive Order 11988 , as amended, to only perform or fund actions within or affecting floodplains if those actions are the only practicable alternative. See, e.g., new 44 CFR 9.9(d) . Through the 8-step process, FEMA will consider alternative locations, alternative actions, nature-based solutions, and the no action alternative under the practicability analysis. If there is no practicable alternative, FEMA may perform or fund the action and will minimize any adverse impacts when doing so. FEMA believes the commenters' concerns are unwarranted given this long-standing process that is not changing as a result of the changes made in this final rule.

FEMA agrees with one of the commenters that FFRMS is not merely an elevation standard. As section G.2 of FEMA's FFRMS policy states “[t]he FFRMS is a resilience standard. Particularly in cases where elevation may not be feasible or appropriate for facilities, the FFRMS floodplain, determined according to the process described in section C of this policy, establishes the level to which a structure or facility must be resilient. Resilience measures include using structural or nonstructural methods to reduce or prevent damage; elevating a structure; or, where appropriate, designing it to adapt to, withstand and rapidly recover from a flood event.”  [ 255 ]

As explained above, FEMA has not proposed changes to the way that the 8-step process is applied to wetlands. FEMA notes the definition of wetlands in 44 CFR 9.4 has always been much broader than that under the Clean Water Act (CWA). Thus, under current practice the 8-step process has been applied to wetlands regardless of their jurisdictional status under the CWA. However, the 8-step process does not have the same requirements of Section 404 of the Clean Water Act. While FEMA does consider new construction in wetlands, to include the placement of fill, and consider alternatives, the 8-step process is not an authorization or permitting process.

As previously explained, FEMA will distribute resources for the public and SLTT partners and the public identifying what the FFRMS is, and how the agency will implement the Executive Orders to further assist applicants for FEMA-funded assistance programs. FEMA will also provide technical assistance through the agency's regional offices in support of FFRMS implementation. FEMA notes while the PA and HMA guidance documents are instructive to applicants, FEMA's regulations at 44 CFR part 9 control the agency's actions for all of FEMA's programs.

Comments: Some commenters requested FEMA implement a “zero-rise” or “no rise” standard in the 8-step process. Four commenters stated that FEMA should require a “zero rise” standard for Federal actions where a regulatory floodway had not been designated. The commenters noted FEMA's edits to § 9.11 but recommended an additional edit to not permit any increase in flood levels when a regulatory floodway had not been designated.

Another commenter raised concerns about these requirements in the FFRMS policy. The commenter stated that the requirement for FEMA-regulated floodplains without a floodway in the FFRMS policy was unreasonable. The commenter wrote the requirement to include all anticipated development was challenging for applicants, as anticipated development might never happen or substantially change due to the project approval process and recommended limits be placed on what was included in the anticipated development to make the standard more reasonable.

FEMA Response: The changes made to § 9.11(d)(4) provide clarification that the agency will continue to require the NFIP's minimum standard (currently 1-foot rise) or, consistent with § 9.11(d)(6), a more restrictive standard adopted by a community. This has been a long-standing requirement of the NFIP. [ 256 ] FEMA's edits help ensure consistency with the NFIP's minimum standard while allowing the flexibility to utilize Start Printed Page 56999 a community's own more restrictive standards.

FEMA did not propose to prohibit any increase in flood levels when a regulatory floodway has not been designated, and prefers not to make such a change at this stage of the rulemaking. The current process for determining increases in floodplains when a regulatory floodway has not been designated is consistent with the requirements of the NFIP and of many communities throughout the country. FEMA may take the commenter's suggestion under consideration in the future.

Comments: Some commenters also requested FEMA prohibit the use of fill for elevation in the 8-step process. Commenter requested FEMA consider the impacts of using fill to achieve elevation requirements. One commenter stated elevation could have damaging impacts if implemented without considering stormwater runoff and that using fill dirt to achieve floodplain elevation requirements could push stormwater onto surrounding areas and worsen or create flooding problems for adjacent properties. Another commenter stated that while intended to reduce flood risk, using fill dirt to achieve floodplain elevation requirements could exacerbate flooding in the surrounding area. This commenter also noted that placing fill in floodplains could severely impact floodplain and wetland ecosystems that are critical habitat for endangered species. Some commenters referenced a recent TMAC report that identified several concerns and perverse incentives from the use of fill to achieve elevation and recommended FEMA discourage the use of fill. Commenters requested FEMA revise § 9.11 to prohibit the use of fill to achieve elevation requirements in the FFRMS floodplain. Where fill is unavoidable, commenters requested FEMA require that a project retain the volume of water onsite that is equivalent to the volume of fill used or have adequate compensatory flood storage requirements. One commenter requested that in the Special Flood Hazard Area, FEMA require elevation to meet FFRMS requirements to be on an open foundation. Another commenter recommended that where the use of fill was necessary as a last resort, added measures should be required to replace the on-site ecosystem benefits of disturbed wetlands.

FEMA Response: FEMA appreciates the commenters' concerns regarding the use of fill and agrees that the impacts of its use must be considered. As part of Step 4 where FEMA identifies impacts, the agency identifies any impacts to the floodplain which would include increasing flood risks to adjacent areas. In § 9.11(d)(4) and (d)(6), FEMA's minimization requirements ensure that fill within regulatory floodways or floodplains where no regulatory floodway is designated will generally not increase flood levels within the community. These minimization requirements ensure consistency with the NFIP or any more restrictive Federal, State, or local requirements. Until a regulatory floodway is designated, no fill is permitted within the base floodplain unless it is demonstrated that the cumulative effect of the proposed development, when combined with all other existing and anticipated development, will not increase the water surface elevation of the base flood more than the amount designated by the NFIP or the community, whichever is most restrictive. [ 257 ] Under § 9.11(d)(4), fill is also prohibited within a designated regulatory floodway that would result in any increase in flood elevation within the community during the occurrence of the base flood discharge. FEMA prioritizes elevation on open works over elevation on fill in § 9.11(d)(7), requiring elevation on open works rather than on fill in coastal high hazard areas and elsewhere, as practicable.

The substance of the requirements in § 9.11(d) was not changed as part of this final rule. FEMA did not propose to prohibit elevation on fill as suggested by some of the commenters, and prefers not to implement such a change at this stage of the rulemaking. FEMA will remain cognizant of the potential impacts of use of fill as part of the project approval process as described above in the 8-step process, and may take the comments under consideration for further action at a future date.

The revisions to part 9 do not change FEMA's long-standing requirement as part of implementation of Executive Order 11988 , as amended, to only perform or fund actions within or affecting floodplains and wetlands if those actions are the only practicable alternative. See, e.g., new 44 CFR 9.9(d) . No further edits are required to part 9 to address the commenter's concerns regarding fill in wetlands. As FEMA's current part 9 process currently prohibits actions in wetlands where there is a practicable alternative, fill and dredge practices to achieve elevation or to construct buildings/facilities in wetlands would only be allowed in those instances where there were no alternatives and the need to perform the action outweighed agency's requirements outlined in 44 CFR 9.9(e)(2) . New § 9.11(e) (current § 9.11(f)) requires restoration where applicable.

FEMA appreciates the commenters' reference to the recent TMAC recommendations on the use of fill. The TMAC recommended FEMA consolidate and clarify fill requirements for the NFIP in 44 CFR 60.3 and consider prohibiting the use of fill as an elevation technique for residential and commercial structures in the SFHA (both coastal and riverine); prohibiting fill as a floodproofing technique; and allowing a limited amount of fill for bridges, dams, and wastewater treatment facilities along with other uses functionally dependent on proximity to water. The TMAC also recommended that FEMA (1) require communities participating in the NFIP to quantify and put on file the impacts of proposed fill and other development on flood stages and the environment prior to issuing fill permits and (2) require notice to property owners and appropriate environmental agencies when increases in flood elevation or potential negative consequences were found and could not be mitigated. [ 258 ] These recommendations are clearly focused on the NFIP, not the 8-step process in part 9 in this rulemaking. As described above, the 8-step process contains sufficient flexibility to allow FEMA to address concerns related to use of fill during Steps 4 and 5 of the process. While FEMA is considering these recommendations consistent with the NFIP requirements, the agency notes TMAC recommendations are not binding on FEMA.

Comment: One commenter wrote requesting that FEMA eliminate Letter of Map Change (LOMC) exceptions for sites. The commenter cited HUD's proposed rule and stated that an exception could incentivize adding fill in a floodplain, which could lead to a reduced floodplain function, as well as increased flood risk to surrounding properties.

FEMA Response: FEMA's regulation does not specifically except areas or sites where FEMA has issued a Letter of Map Change (LOMC) from the 8-step process. In their original regulation, HUD did have a specific exception for any non-wetland site in a floodplain for which FEMA had issued a final Letter of Map Amendment (LOMA), final Start Printed Page 57000 Letter of Map Revision (LOMR), or a final Letter of Map Revision Based on Fill (LOMR-F) that removed the property from a FEMA-designated floodplain. The exception under HUD's original regulation also included conditional LOMAs, LOMRs, or LOMR-Fs if HUD or the responsible entity's approval was subject to the requirements and conditions of the conditional LOMA or LOMR. [ 259 ] FEMA notes that HUD removed these exceptions from 24 CFR 55.12(c)(8)(i) and (ii) in recent updates to their regulation. [ 260 ] As FEMA did not except those areas in the regulation, the FEMA rule does not require revision for the FFRMS floodplain to apply and for FEMA to conduct the 8-step process if those areas are determined to be within the expanded floodplain. FEMA notes the changes to part 9 in this final rule do not apply to the NFIP's regulations on mapping and changes to FEMA maps. Those regulations are found at 44 CFR part 70 et seq.

Commenters also recommended changes to the practicability analysis in the 8-step process.

Comments: A commenter stated concern that actions in floodplains and wetlands would be allowed only as a last resort under the rule and recommended that FEMA revise the regulations to more strongly clarify to officials implementing the regulations that actions in floodplains, especially those on already urbanized lands, could be allowed, provided flood resilience measures were employed. Conversely, another commenter recommended that FEMA prioritize avoidance as the first alternative to actions that would modify or compromise floodplain function as the most effective risk reduction strategy. The commenter recommended that where avoidance cannot be achieved, resilient design should be incorporated meaningfully. A third commenter stated the feasibility analysis should consider whether right-of-way is not available and condemnation is required.

FEMA Response: The revisions to part 9 do not change FEMA's long-standing requirement as part of implementation of Executive Order 11988 , as amended, to only perform or fund actions within or affecting floodplains if those actions are the only practicable alternative. See, e.g., new 44 CFR 9.9(d) . This rule does not alter the 8-step process requirement to evaluate practicable alternatives, which includes consideration of locations outside of the floodplain or wetlands. Through the 8-step process, FEMA considers alternative locations, alternative actions, nature-based solutions, and the no action alternative under the practicability analysis. If there is no practicable alternative, FEMA will perform or fund the action and will minimize any adverse impacts when doing so. FEMA believes the commenters' concerns are unwarranted, given this long-standing process that is not changing as a result of the changes made in this final rule. Further, the practicability factors, which are outlined in 44 CFR 9.9(c) , include the consideration of legal constraints, which would generally encompass the acquisition of right-of-way for proposed actions.

Comment: A commenter requested specific revisions to § 9.9 to include “the presence of threatened or endangered species or their critical habitat” as an example under “natural environment.” The commenter also requested FEMA include “the presence, absence, and/or effectiveness of local or state land management plans to conserve natural values of the floodplains and wetlands at issue.” Finally, this commenter requested FEMA include “participation of the impacted community or communities in the Community Rating System program” when analyzing the practicability of alternatives to proposed actions in floodplains or wetlands. The commenter requested FEMA edit § 9.9 to include examples of floodplain values, including “wildlife habitat and connectivity, including for threatened and endangered species” in § 9.9(e)(2)(iv) and § 9.9(e)(3)(iv).

FEMA Response: FEMA respectfully declines the commenter's request, as the agency believes many of these examples would be covered under the existing regulatory text, and no edits are required in this final rule to address these concerns. Specifically, the final rule lists “natural environment” and includes “habitat,” which addresses the commenter's concerns about the inclusion of threatened and endangered species or their critical habitat. “Social concerns” includes “land patterns;” under these factors, FEMA does consider local or state land management plans when considering practicability. FEMA appreciates the commenter's interest in the agency's Community Rating System (CRS) program. FEMA notes that the commenter's concerns regarding threatened and endangered species and their critical habitats is addressed in the CRS program through credits for communities that protect threatened and endangered species. [ 261 ] A community's participation in the CRS program does not impact an action's practicability under part 9. Updating part 9 to incorporate the CRS program is inappropriate, as the CRS program provides discounts to individual policyholders in NFIP participating communities and as explained above, part 9 applies only to Federally-funded actions.

Further, FEMA's regulatory text is consistent with the Revised Guidelines. Wildlife habitat and connectivity are already incorporated into the rule in the definition of “natural and beneficial values of floodplains and wetlands.” Specifically, that definition references “Living Resource Values” as “providing habitats and enhancing biodiversity for fish, wildlife, and plant resources.” This language encompasses the wildlife habitat and connectivity requested by the commenter, and no edits are required to the final rule.

Comments: Two comments offered alternatives to the 8-step process outlined in part 9. One commenter recommended retreating a mile from every coast, river, and flood area and making those areas public lands, swamps, or flood zones and that FEMA prohibit rebuilding when buildings are destroyed due to sea level rise and convert those areas into their suggested publicly owned buffer. Another commenter recommended using eminent domain to reclaim flood damaged structures and reclaim lands, wetlands, swamps, and other properties, allowing these areas to naturally buffer and absorb flooding. The commenter stated private property rebuilding should not take place in a flood zone using taxpayer dollars, subsidies, grants, or any form of tax revenue.

FEMA Response: FEMA did not propose, and does not believe it would be appropriate to implement, a standard that categorically prohibits rebuilding within one mile of every coast, river, and flood area.

Comment: Another commenter stated there would likely be instances where the cost of floodproofing or elevating Federal and non-Federal buildings with the new FFRMS floodplain would be found to be unreasonable. The commenter recommended against any kind of automatic seizure or destruction in those instances, but rather suggested developing a process in which factors Start Printed Page 57001 could be considered in determining the future disposition of such buildings and encouraged the ability to grandfather-in some buildings so they could maintain their functionality until such a time as they actually suffered flood damage.

FEMA Response: Part 9 only applies to FEMA actions and the FFRMS only applies to FEMA actions that are subject to the FFRMS. FEMA defines “action subject to the FFRMS” as “any action where FEMA funds are used for new construction, substantial improvement, or to address substantial damage to a structure or facility.”

Where part 9 applies, FEMA has always incorporated natural environment, social concerns, and economic aspects into the 8-step process as part of the practicability analysis. Specifically, if the minimization measures for a proposed action were found to be “unreasonable,” that may fall under the economic aspect of the practicability analysis. In these instances, FEMA has not proposed automatic seizure or destruction procedures in the regulatory text or policy. FEMA also works with program applicants to consider the appropriate service life for the action during the 8-step decision-making process to better understand the flood risks and safety prioritization for individual actions.

Comment: A commenter asked if FFRMS would be used as a selection tool for grant projects. The commenter noted that FEMA has previously considered a project's scope or service area for funding and stated the increase in floodplains from NOAA Atlas 14 revised flood maps would limit federal funding for some projects due to previous design criteria used on the downstream channels or development.

FEMA Response: FEMA will not use the FFRMS flood elevation as a selection tool for grant projects; rather, it is a design requirement for grant projects. Issues related to or impacting a project's scope or service area remain unchanged. Finally, FEMA disagrees with the commenter's statement that revised flood maps would limit federal funding for some projects. Revised flood maps where the floodplains increase would have no effect on project eligibility.

Comment: One commenter inquired whether the agency's findings would be beneficial to the “central Arizona project” given the dangers of flooding to the canal.

FEMA Response: FEMA appreciates the commenter's interest in this regulation. The FFRMS CISA State of the Science Report provides a review and update of the best-available, actionable science that can support application of the Climate-Informed Science Approach (CISA). [ 262 ] FEMA respectfully refers the commenter to the State of the Science Report and other tools to determine whether the FFRMS policy initiative more broadly may have an impact on a local project of interest. FEMA's part 9 controls the agency's implementation of Executive Order 11988 , as amended, and Executive Order 11990 .

Comments: Some commenters requested FEMA consider implementing the FFRMS for the NFIP. Another commenter requested FEMA require disclosure of past flood damages for FEMA-funded residential projects.

FEMA Response: As explained above, FEMA cannot accommodate the commenter's request to integrate the FFRMS into the minimum floodplain management standards for the NFIP because it is beyond the scope of this rulemaking. The NFIP is a program through which property owners in participating communities can purchase Federal flood insurance as a protection against flood losses. In exchange, a community must adopt and enforce floodplain management regulations that incorporate NFIP minimum floodplain management criteria developed by the Administrator. Further information regarding FEMA's minimum floodplain management standards for the NFIP can be found at 44 CFR part 59 et seq. Any update to those standards would require a rulemaking to revise the appropriate regulatory sections of the CFR. By contrast, the FFRMS, as implemented by this rulemaking, only applies to actions where FEMA funds are used for new construction, substantial improvement, or repairs to address substantial damage to structures and facilities.

Requiring disclosure of past flood damage for FEMA-funded residential projects is beyond the scope of this rulemaking. However, FEMA notes disclosure of prior flood damage, flood claims or losses, and the status of repetitive loss properties is important, and FEMA is pursuing options to require such disclosure, as evidenced in FEMA's 2023 legislative proposal submitted to the 118th Congress. [ 263 ]

In the NPRM, FEMA requested specific comment on accessibility issues. FEMA sought public comments on the impact of the proposed elevation requirement on the accessibility of covered facilities under the Fair Housing Act, the Americans with Disabilities Act (ADA), the Architectural Barriers Act (ABA), and section 504 of the Rehabilitation Act of 1973. FEMA invited comments on strategies the agency could employ to ensure accessibility requirements were met for properties that would be impacted by the rule. Additionally, FEMA invited comments on the cost and benefits of such strategies, including data that supported the costs and benefits. FEMA received five comments on accessibility. Some commenters provided FEMA with recommendations on strategies regarding accessibility, while other expressed concerns with potential increased costs of accessibility and elevation along with potential conflicts regarding accessibility laws.

Comments: One commenter recommended FEMA consider accessibility concerns as a factor in favor of selecting alternatives that minimize residential and essential structures within the floodplain. The commenter also stated projects should be designed to maximize both access and resilience by practicing avoidance to the extent practicable, consistent with Executive Order 11988 . Another commenter recommended FEMA issue design and regulatory guidance to address concerns or challenges over the effects of proposed elevations on accessibility of covered facilities, particularly those intended for use by disabled and elderly populations and stated guidance could ensure that floodproofing would not hinder accessibility. A third commenter noted that elevating structures was not always feasible, practical, or advisable and that seeking to meet both elevation and accessibility requirements created even more challenges and increased costs, sometimes rendering certain projects infeasible. Referencing HUD's Fair Housing Act's guidance on BFE challenges, the commenter recommended FEMA recognize the impracticability of requiring elevation in certain situations consistent with HUD's guidance. The commenter cited increased cost concerns and unintended consequences on individuals who rely on accessible housing.

Some commenters stated FEMA's request for comment on accessibility concerns indicated a conflict with implementation of the FFRMS and laws Start Printed Page 57002 governing accessibility. One commenter stated FEMA admitted the rule could potentially conflict with several acts aimed at protecting vulnerable populations such as the disabled and elderly. Another commenter stated the agency indicated the proposed rule threatened to violate the Fair Housing Act, the Americans with Disabilities Act, the Architectural Barriers Act, and section 504 of the Rehabilitation Act of 1973 and recommended FEMA identify and either exclude or limit these scenarios when applying the proposed standard.

FEMA Response: Through the final rule, FEMA seeks to prioritize minimizing the impact of floods on human health, safety, and welfare, including those of vulnerable populations. FEMA's request for comment in this area focused on ways the agency could further reduce or mitigate the impacts of the FFRMS implementation on these populations. Accessibility concerns would generally fall under social concerns and legal constraints in assessing practicability in the 8-step process. FEMA considers both the accessibility of a structure and the accessibility to community resources for those impacted. FEMA only takes action in the floodplain if there is no practicable alternative. Further, if an alternative would render a building inaccessible, it would not be a practicable alternative. FEMA agrees with one of the commenters that proper guidance can help reduce the impacts of elevation on accessibility. FEMA's existing guidance documents address concerns associated with the effects of elevation on accessibility. FEMA may address any additional specific concerns regarding FFRMS implementation as they arise on a case-by-case basis or via additional guidance. [ 264 ]

FEMA appreciates the importance of providing affordable, accessible housing. FEMA believes that the agency's policy approach provides flexibility to address these concerns. For example, construction of ADA-compliant access facilities or ramps is an eligible cost for FEMA's HMA structure elevation and mitigation reconstruction projects for homes. FEMA considered the costs and benefits associated with this rule, including the overall increased costs of FEMA projects, in the regulatory impact analysis provided on the public docket for this rulemaking. [ 265 ] FEMA believes that the benefits of preventing property damage and potentially saving lives justify the costs of the rule. These benefits are a result of the improved protection of structures and facilities due to increased elevation and floodproofing standards in FEMA's implementation of the FFRMS. This rule will help to ensure that Federal investments are better protected from flood damage, and that the natural values of floodplains are preserved. FEMA notes any increased costs are generally eligible for funding under FEMA's assistance programs subject to cost share requirements, including accessibility needs.

Regarding other conflicting laws, the commenters do not accurately state FEMA's position. FEMA sought comment on how the implementation of FFRMS may interact with specific legislation and strategies FEMA could employ to ensure accessibility needs were met. FEMA's policy approach provides flexibility to accommodate the specific needs of the vulnerable populations the commenter references, and FEMA believes the 8-step process requirements, specifically in considering the practicability of an action and potential impacts from the action, detailed above help resolve accessibility concerns.

FEMA received several comments specific to the agency's RIA associated with the rulemaking.

Comment: Commenters requested additional clarification and recommended edits to the alternatives detailed in the RIA. Specifically, two commenters stated FEMA should consider alternatives to the proposed standard and the various FFRMS approaches. The commenters stated that analyzing alternatives would include identifying cases where imposing the standard would create new risks and costs greater than the risk the standard sought to mitigate. The commenters further requested FEMA delay the final rule until these analyses were completed.

FEMA Response: Executive Order 11988 , as amended, directs agencies to perform or fund actions within or affecting floodplains only if those actions are the only practicable alternative. Through the 8-step process for individual actions, FEMA considers alternative locations, alternative actions, nature-based solutions, and the no action alternative under the practicability analysis. If there is no practicable alternative, FEMA will perform or fund the action and will minimize any adverse impacts when doing so.

On a project basis, FEMA has consistently leveraged benefit-cost analysis in grant programs requiring evaluation of cost effectiveness, such as those programs under Hazard Mitigation Assistance, and will continue to do so along with minimum standards for floodplain management across the agency's programs to help ensure that Federally funded projects are both cost-effective and result in more resilient communities. Additionally, during the 8-step process, FEMA will also evaluate the impacts from the proposed action (in Step 4) when determining the appropriate resilience or minimization measures in Step 5. The flexibility of the 8-step process allows FEMA to work with SLTTs to select the appropriate minimization measure for the action. FEMA requires that only practicable means to minimize harm to or within the floodplain are required for compliance with 44 CFR 9.11 , including consideration of economic aspects. If, in the course of implementation, FEMA identifies categories of projects for which the standard proves to be generally impracticable, FEMA may take appropriate action—such as issuing further guidance—at that time.

FEMA believes that the benefits of preventing property damage and potentially saving lives justify the costs of the rule. These benefits are a result of the improved protection of structures and facilities due to increased elevation and floodproofing standards in FEMA's implementation of the FFRMS. This rule will help to ensure that Federal investments are better protected from flood damage, and that the natural values of floodplains are preserved.

Comment: A commenter stated the RIA did not present information on the population at risk, or the residual risk to human life associated with each FFRMS approach. The commenter stated that FEMA should follow the requirements of the Principles and Requirements for Federal Investments in Water Resources (March 2013) and accompanying Interagency Guidelines  [ 266 ] to provide information to Start Printed Page 57003 owners and residents of flood-prone property the residual flood risk and availability of flood insurance. The commenter recommended that FEMA provide an estimate of the population at risk by FFRMS approach and an estimate as to how this would change by approach.

The commenter also requested information on FEMA's statements in the RIA regarding potential for lives saved by the rulemaking. The commenter stated that FEMA provided statistics on the number of fatalities from flash and river flooding but was unable to estimate how many of those fatalities would be avoided if the rulemaking were implemented. The commenter also stated that FEMA did not provide a quantification that would allow for a comparison among the FFRMS approaches. The commenter wrote that FEMA did not clarify whether the CISA would be safer than the FVA or 0.2PFA or whether elevating and floodproofing properties were necessarily safer than the no action alternative. The commenter further stated that floodproofing and elevation could instill a false sense of security that encouraged people to not evacuate or delay their departure in a flood. The commenter recommended that FEMA provide additional information in the RIA on this topic and include non-quantified costs to acknowledge it was conceivable that elevation and floodproofing could result in an increase in lives lost if those efforts provide a false sense of safety to the public.

FEMA Response: FEMA is leveraging Executive Order 11988 , as amended, and the Revised Guidelines for the FFRMS rulemaking and the FFRMS implementation. The Principles and Requirements for Federal Investments in Water Resources and the accompanying Interagency Guidelines (PR&G) do not generally apply to this rulemaking; rather, those requirements apply to actions associated with water development projects. [ 267 ] FEMA will apply the PR&G requirements to those specific actions as applicable, namely those actions where FEMA is taking an action associated with a water development project. Although the PR&G does not generally apply to this rulemaking, FEMA notes that the 8-step process includes public notice requirements detailed for steps 2 and 7, as further detailed in part 9.

Regarding the commenter's comment about how FEMA did not provide a quantification that would allow for a comparison among the FFRMS approaches, FEMA showed the comparison in Tables ES-12 and ES-13 within the RIA. These tables present the cost, transfer payments, and benefit estimates by FFRMS approach—where available data allow—and also present estimates of costs, transfers, and benefits by grant program for CISA, FEMA's primary approach.

FEMA added more text to the qualitative analysis within the benefits section of the RIA accompanying this final rule to further address the commenter's concerns regarding risk to human life and whether elevating or floodproofing properties under any of the FFRMS approaches is safer than taking no action. FEMA included a description of qualitative benefits, which included the potential for lives saved, savings in time and money from a reduced recovery period after a flood, increased safety of individuals, increased public safety, reduced personal and community impacts, and reduction in future health issues related to flooding. FEMA does not believe that it would be appropriate to refrain from taking this action based on the commenter's suggestion that the rule could instill a false sense of security. The commenter provided no evidence on this point, and FEMA does not believe it would be appropriate to fund less resilient projects in an effort to avoid making people feel secure in the event of a flood.

As explained in the NPRM, the CISA is FEMA's preferred policy approach, as FEMA believes it has the potential to be the best and most well-informed approach to building resilience in an equitable manner and ensuring a reduction in disaster suffering. CISA is designed to meet current and future estimates of flood risks unique to the location and thus provide the best overall resilience, cost effectiveness, and equity.

With regard to the commenter's recommendation that FEMA provide an estimate of the population at risk by FFRMS approach, FEMA cannot correlate population risk by floodplain expansion. FEMA could not use Geographical Information System (GIS) data, as the database identifies whether a project was in the floodplain, but because it did not categorize projects according to their location, FEMA was not able to distinguish projects located in coastal areas from those located in non-coastal areas. Additionally, the dataset does not break out multiple project worksites.

FEMA notes the agency's current alternatives analysis process incorporates consideration of a range of flood mitigation practices. FEMA considers the following alternatives: (a) no action; (b) alternative locations; and (c) alternative actions, including alternative actions that use natural features or nature-based solutions. When practicable, FEMA avoids actions within the floodplain. The flood minimization measures found in § 9.11 are reliable methods of providing resilience to structures. FFRMS flood resilience measures consider both current and future flood risks to better protect Federal investments. The elevation requirement in § 9.11(d)(3) applies to structures and also allows floodproofing for non-residential structures. The FFRMS policy provides further explanation for structures that must be located within the FFRMS floodplain must be elevated or floodproofed to the FFRMS flood elevation. Additionally, the policy clarifies facilities can use elevation or any other appropriate minimization measure to protect the facility against the FFRMS flood elevation. Minimization can include measures such as ensuring the impacted public knows their flood risk and has awareness of flood evacuation procedures.

Comment: Two commenters requested FEMA implement the revised 2 percent discount rate from OMB Circular A-4 for this rulemaking to represent future benefits more accurately. Another commenter requested clarification on the discount rates used in the RIA. That commenter recommended FEMA state that the analysis was conducted using the prescribed 7 percent discount rate and requested FEMA provide a sensitivity analysis using a 3 percent discount rate and a 10 percent discount rate if appropriate.

FEMA Response: The new OMB Circular A-4 discount rate is effective March 1, 2024, for regulatory analyses received by OMB in support of proposed rules, interim final rules, and direct final rules, and January 1, 2025, for regulatory analyses received by OMB in support of other final rules. The Start Printed Page 57004 FFRMS proposed rule was published on October 2, 2023. Given this timing, FEMA is using the previously established discount rate and is not applying the new OMB Circular A-4 discount rate to this final rule. For the RIA, FEMA provided discounted values using both 3 percent (social rate of time preference) and 7 percent (opportunity cost of capital) based on the version of OMB Circular A-4 that was in place at the time of publication of the NPRM.

Comment: A commenter requested several clarifications on the discount rates that were used within the RIA, including the discount rate used to generate the figures in Appendix E (Benefits). The commenter questioned why both the 3 and 7 percent discount rate for benefits were used within the analysis when the 50-year present value benefit uses a single 7 percent discount rate. And they sought clarification on how the 7 percent discount rate was used for benefits.

FEMA Response: FEMA utilizes a 7 percent discount rate for benefits, while the table(s) referenced uses both 3 and 7 percent discount rates. The benefits per structure consist of a 50-year stream of benefits, discounted to the year that the structure is constructed using a 7 percent discount rate. Since the RIA estimates 10 years' worth of projects, those benefits must be discounted again from the year of construction to the present ( i.e., to the beginning of Year 1) and annualized for comparison with 10 years' worth of costs. FEMA conducted its discounting from the year of construction to the beginning of Year 1 and conducted its annualization using both 3 and 7 percent discount rates, per the version of OMB Circular A-4 that was in effect at the time of publication. [ 268 ] FEMA has clarified this in this RIA.

Comment: A commenter requested clarifications and provided recommendations regarding administrative costs in the RIA. Specifically, the commenter asked for clarification on the administrative costs in tables 85 and 86 of the RIA, which summarize the low and high estimated impacts of the rule, stating these costs were shown as being the same for all of the alternatives in those tables while the RIA stated a range for the administrative costs. The commenter also requested clarification on table ES-12 and other tables that omitted administrative costs from the undiscounted total dollar figures while those costs were included in the undiscounted costs in tables 64-69 which show total costs by FFRMS approach. The commenter requested FEMA reconcile the issue. The commenter stated FEMA acknowledged there would be annual administrative costs but only included those costs in the economic analysis for the first 10 years of the period of the analysis. The commenter recommended FEMA either include annual administrative costs as they apply after the initial 10-year period or explain why they would no longer be included.

FEMA Response: The administrative costs are different in tables 85 and 86 in the RIA provided with the NPRM. FEMA created a range for estimating the administrative costs for two circumstances: (1) if all projects used the interagency Federal flood standard support tool (low estimate, as represented in Table 85) and (2) if all projects used the Job Aid (high estimate, as represented in Table 86) for the first 10 years under the CISA. In reality, the administrative costs will likely fall somewhere between the low and high estimates. These tables are still tables 85 and 86 in the RIA. Further, tables 64-69 show the costs of the three different approaches (CISA, FVA, and 0.2PFA), which include the administrative costs to show the total cost under each approach.

Table ES-12 is a summary table that shows the costs of each approach so that the reader can see the various options next to each other. The administrative cost is separated out because if FEMA added the administrative cost to each approach, it may be misinterpreted as triple counting. To address the commenter's concerns, FEMA included footnotes in Table ES-12 and Table ES-13. FEMA also removed the term “total” from the costs section within Table ES-12 and Table ES-13 as they are not the total cost as they do not include the administrative cost. The reader should add each individual approach to the FEMA administrative cost to obtain the total costs in Section 7.12. For example, CISA + FEMA administrative = total CISA cost.

FEMA examined the number of projects that will be subject to the requirements in the first 10 years after the rule's publication. FEMA's analysis focuses on the costs, benefits, and transfer payments ( i.e., impacts on FEMA grants) that will result over a 50-year period from the application of the requirements of the final rule to those projects, for a total period of analysis spanning 60 years. The costs and transfers occur in the first 10 years of the 60-year period because that is when the initial investment to elevate or floodproof those projects takes place. This is an upfront cost that occurs when the project is constructed. However, the benefits of the final rule are estimated over the 50-year useful life of the affected structures.

Comment: A commenter recommended FEMA use a more general cost index such as the Gross Domestic Product-Implicit Price Deflator (GDP-IPD) or an appropriate construction cost index instead of the U.S. Department of Labor's Bureau of Labor Statistics Consumer Price Index (CPI) to establish a 2021 common dollar basis.

FEMA Response: FEMA used CPI in majority of the analysis within the RIA, such as to adjust historical grant obligation amounts to constant dollars. However, FEMA used an Engineering News Record (ENR) Construction Costs  [ 269 ] factor to adjust the construction values to 2021 costs within the NPRM RIA. The ENR was used to represent the change in costs from 2016 to 2021. The value selected was a national cost average. This value is consistent with the approach used to calculate the initial construction costs, which applied the national average square foot cost. The adjustment factor from 2016 to 2021 applied was 1.17 or a 17% increase in construction costs over the period analyzed. FEMA used the same ENR data for the final rule's RIA but adjusted it to 2022 costs. While other sources indicated a larger range of construction cost increase, the ENR value was selected in the 2022 report as a lower-bound approach to the benefits analysis.

Comment: A commenter stated that FEMA acknowledged the costs of operating and maintaining elevation and floodproofing projects were not included in the RIA but instead were zeroed out. The commenter stated that while additional costs for operating and maintaining an elevated structure would be low, the costs for floodproofed structures could be substantial if floodproofing entailed generator/pumping stations. The commenter stated the omission was particularly glaring given the 50-year design life of the project and recommended FEMA include some reasonable estimate of these costs rather than zeroing them out, though the commenter did not provide any such estimates. The commenter also stated the RIA was incomplete without information on the estimated costs of Start Printed Page 57005 improving the flood resilience of facilities; however, the commenter did not provide a data source to use for estimating the cost of increased flood resilience for facilities.

FEMA Response: FEMA appreciates the commenter's concerns. FEMA requested available data that would assist FEMA in estimating the impact of the proposed increased flood resilience standards on specific types of facilities, including examples showing the cost of similar resilience measures, case studies, or other relevant information. FEMA did not receive any data. Instead, FEMA discusses the non-quantifiable costs within Qualitative Discussion of Additional Potential Costs section. FEMA was able to quantify the number of facilities that would be impacted by the rule as well as the incremental costs of applying the FFRMS to these facilities. FEMA conducted the analysis on facilities based on the best available information. FEMA acknowledges that there are lifecycle costs associated with floodproofing of structures, but these costs are unique to the type of structure and floodproofing methods used, and not generalizable across all potential projects nationwide. FEMA discusses these costs qualitatively in Section 7.11.3 of the RIA.

FEMA included a qualitative summary of the impacts that could not be quantified, such as increased resilience standards for facility projects, additional costs for adding requirements to buildings with basements, diversion of projects out of the floodplain, lifecycle maintenance costs for floodproofing and project delays and forgone projects, within the executive summary and conclusion section.

FEMA discusses facilities and the challenges with estimating economic impacts of the FFRMS. Because there are many methods for making facilities resilient, and due to the wide variety of projects considered facilities, FEMA could not make quantitative estimates of economic impacts for these projects that can be applied for all facility types nationwide.

Comment: A commenter requested FEMA further explain the omission of specific quantifiable costs, such as the costs for projects that may be diverted out of the floodplain, impacts to projects with existing basements, project delays, or foregone projects, that would result from the rule. The commenter stated these costs vary in terms of data and method calculation ability. In particular, the commenter questioned why impacts to structures with basements were not quantified because data are available about, for instance, the prevalence of basements geographically and depth-damage functions for structures with basements, as well as information from the Census of Construction. The commenter also questioned whether diversion out of the floodplain is a cost of the rule because, presumably, a project would only be diverted if a project owner determined that net benefits would be higher without the project in the floodplain.

FEMA Response: FEMA identified these as data limitations because the agency does not generally track the information referenced by the commenter. For example, FEMA does not track project applications where the applicant withdraws their application for Federal funding due to floodplain considerations.

In addition, FEMA appreciates the commenter providing data sources for structures with basements and has considered this data. These data sources provide national-level summary statistics and geographic information on structures with basements. FEMA is unable to apply this data to FEMA's project level data, since FEMA databases do not include fields for structures with basements, and FEMA is unable to correlate the Census of Construction data with its own project-level data. Additionally, this data pertains to residential construction, and only a small number of FEMA actions subject to the FFRMS are residential construction.

Comment: A commenter requested clarification on the discrepancy on “Appendix E: Benefits Net Present Value” heading on page 213, which would appear to indicate that Tables 1-18 display the Net Present Values, but the column headings in these tables are labeled “. . . Present Value Benefits. . . .” The commenter stated that the various values presented in said tables are elsewhere presented as Benefits rather than Net Benefit, as seen in a comparison of Table 84 with Tables 17 and 18 of Appendix E.

FEMA Response: The tables referenced by the commenter show the Present Value of the benefit streams expected from implementation of this rule. FEMA updated the table headings and footnotes as appropriate.

Comment: A commenter requested clarification on how the results of the analysis were presented in tables. Specifically, the commenter questioned the presentation of a single estimate for benefits the FFRMS approaches in the conclusion, the lack of monetization for benefits discussed qualitatively, how none of the FFRMS approaches have a positive net benefit, and how there was no rationale for not selecting 0.2PFA as the preferred approach, as the commenter calculates it is the FFRMS approach with the greatest net benefit.

FEMA response: The benefits are not the same for all of the FFRMS approaches. FEMA could not quantify every cost and benefit associated with this rule. However, FEMA was able to quantify the number of structures and facilities that would be impacted. FEMA quantified a portion of the benefits for the CISA for all PA Category E projects that are subject to the FFRMS. Specifically, FEMA estimates the present value benefits of one additional foot of freeboard for the 50-year useful life of PA Category E projects undertaken during the 10-year period of analysis, with the assumption that there will be a 59-inch SLR.

FEMA was only able to estimate quantitative benefits for PA Category E projects affected using CISA. FEMA cannot compare quantitative benefits to the costs for IA or HMA, since FEMA does not have a reliable data source to estimate the benefits for projects covered by these programs; HMA data cannot be broken out by building types and IA data is limited to residential-related projects, which are not included in the 2022 report. The table that the commenter created making such a comparison to demonstrate that 0.2PFA is the FFRMS approach has the highest net benefits is not accurate. The present value of benefits using CISA is not the same as the present value of benefits using FVA or 0.2PFA, as the number of projects impacted by each approach varies. FEMA did estimate the impact on PA projects for FVA, 0.2PFA and CISA in sections 7.14.2.1 through 7.14.2.6 within the RIA. However, these estimates cannot be applied to IA and HMA projects for the reasons stated above. In addition, there are additional costs and benefits that FEMA could not quantify for this analysis so FEMA discussed them in a qualitative manner. For example, qualitative benefits include the potential for lives saved, savings in time and money from a reduced recovery period after a flood, increased safety of individuals, increased public safety, reduced personal and community impacts, and reduction in future health issues related to flooding.

Accordingly, FEMA is unable to use the commenter's table to select the “alternative with the greatest net benefits” as the commenter stated, since the table is not inclusive of all of the rule's quantified and unquantified benefits.

Comment: A commenter sought clarification about how FEMA Start Printed Page 57006 compared the costs and benefits within the RIA. The commenter stated that it appeared as if the costs pertaining to “14,427 PA, IA, and HMA structures” are being associated with, or charged to, the benefits associated with “1,173 PA Category E projects.”

The commenter also expressed confusion over how FEMA used +5-ft freeboard for costs and then used +1-ft freeboard for benefits. The commenter asserted that the statement “FEMA does not have data to quantify the benefits of additional freeboard” was confusing because depth-damage functions are available. They presumed that this would account for CISA's poor economic performance relative to the other approaches.

FEMA Response: FEMA's quantitative benefit estimates are based on a 2022 report that analyzed the benefits of 1 foot of additional freeboard for various building types. FEMA used this report to quantify the benefits of 1 foot of freeboard, as this was the only data that was available. This allowed FEMA to monetize the benefits of an additional foot of freeboard for non-residential PA projects ( i.e., Category E projects). FEMA was unable to use the benefits study to estimate the benefits for HMA and IA projects, since HMA data cannot be broken out by building type, and IA data is limited to residential projects. Accordingly, FEMA's analysis acknowledges that when comparing the total monetized costs and benefits of the rule, it is an imperfect comparison: the total monetized costs are attributable to elevating or floodproofing PA, IA, and HMA structures between 1 and 5 feet (depending on the FFRMS approach used and the location of the project), while the total monetized benefits are attributable to elevating or floodproofing PA projects one additional foot.

FEMA does not claim that the benefits to PA Category E projects are associated with, or charged to, any of the other projects in this analysis. FEMA was able to estimate costs for PA, HMA, and IA, but only able to quantify benefits for PA Category E. FEMA expects benefits for all types of projects but does not have sufficient data for a quantitative estimate.

FEMA could not apply depth-damage functions to these projects, since they are only applicable to elevation or floodproofing at specified levels above the base flood elevation for specified flood zones. FEMA's project databases only identify whether a project is in the 1 percent annual chance floodplain and do not show what flood zone a project is located in. Because of this, FEMA cannot apply depth-damage functions to individual projects to determine the benefits from elevation or floodproofing.

FEMA supplements the monetized benefits with a qualitative discussion of additional benefits that FEMA could not monetize. Specifically, FEMA identified qualitative benefits, including reductions in damage to properties and contents from future floods, potential lives saved, public health and safety benefits, reduced recovery time from floods, and increased community resilience to flooding.

Comment: A commenter requested clarification about how FEMA would determine the necessary height to maximize net benefits for a given project under CISA. Specifically, the commenter asked what assumptions FEMA would use ( e.g., a 59-inch SLR, an 8.5 RCP) to determine elevations that result from “using the best-available, actionable hydrologic and hydraulic data and methods.”

FEMA Response: In the RIA, FEMA provided a summary of the estimated benefits per building type for PA projects. The analysis included both mitigation types (elevation and floodproofing) for 8-inch, 39-inch, and 59-inch SLR and both mitigation types for 4.5 and 8.5 RCP. For FEMA's primary estimate, FEMA used 59 inches of SLR due to it being the closest SLR option to the vertical rise, in accordance with FEMA's CISA+5-ft assumption. CISA is the preferred approach for the FFRMS if the data are available. Since 5 feet is equivalent to 60 inches (5 × 12 inches per foot), 59-inch SLR is the closest SLR option that FEMA had available for this portion of the analysis.

However, in practice, FEMA's FFRMS policy sets minimum elevation requirements to account for possible changes in future flood hazards and therefore, under the CISA, the elevation or floodproofing height would vary by location and criticality of the project. As explained above, FEMA is relying on the FFRMS CISA State of the Science Report to determine what CISA data is actionable and available and will use the FFRMS Job Aid methodology to determine the CISA, FVA, and 0.2PFA for FFRMS actions. The FFRMS CISA State of the Science Report  [ 270 ] discusses the SLR scenarios and what factors to consider when selecting the appropriate SLR projection. The FFRMS Job Aid recommends using the intermediate SLR scenarios for non-critical actions and intermediate-high SLR scenarios for critical actions. [ 271 ] As part of initial implementation, FEMA intends to leverage the FFRMS Job Aid as explained above.

Comment: A commenter requested clarification regarding a footnote in the RIA's Executive Summary, in which FEMA explains the scope of its analysis is limited to impacts from affected projects in the initial 10 years. The commenter questioned the validity of the analysis under the assumption that the analysis relied on a sample of a larger set and recommended that FEMA coordinate with water resource agencies for additional data on elevation and floodproofing.

FEMA Response: This commenter is misinterpreting the footnote. The footnote is explaining why FEMA has limited the analysis to impacts from projects in only the initial 10 years of the rule's implementation. It is not saying that the cost analysis is relying on a sample (the first ten years of implementation) of a larger set (the period of time in which the regulation would be in effect) as suggested.

Comment: One commenter wrote that the rule increased the efficiency and financial benefits of Federal investments and that it would be irresponsible to continue spending taxpayer dollars based on a backwards-looking assessment of flood risk. The commenter agreed with FEMA's assessment that the benefits of the rule justified the rule's costs. The commenter requested FEMA provide a more comprehensive and accurate accounting of benefits in the RIA and quantify and monetize a wider range of benefits, although the commenter did not provide any specific suggestions for doing so. The commenter noted that many of the RIA's unquantified benefits were of profound importance to communities and families residing in the floodplain, including lives saved, access to evacuation routes and essential services, better long-term health outcomes, and reduced recovery times. Additionally, the commenter recommended FEMA Start Printed Page 57007 place greater emphasis on describing, quantifying, and monetizing the benefits of conserving floodplains and wetlands and encouraging nature-based solutions. Finally, the commenter suggested FEMA consider a more nuanced approach to the final rule's distributional effects by assessing how the rule's benefits might be distributed across populations.

FEMA Response: While monetizing the reduction in damages that is anticipated from the rule would be a useful way to show the rule's benefits, not all of the benefits can be effectively monetized with available data. FEMA thoroughly researched methods to quantify and monetize as many benefits as possible for the proposed rule but did not find adequate sources to reliably quantify or monetize most benefits. FEMA continues to research methods and data for quantifying benefits, but since publication of the proposed rule, has not found data sources that would enable FEMA to further quantify the benefits of incremental amounts of freeboard. In addition, FEMA did not receive any data or methods from commenters that would allow FEMA to quantify what it found to be unquantifiable impacts. Accordingly, consistent with direction by OMB Circular A-4 for costs and benefits that are difficult to quantify, FEMA provided a literature review of relevant benefits that could be realized from flood mitigation, an analysis of benefits quantified for the rule, a qualitative description of additional benefits that could be realized from the rule, and a discussion of why FEMA was unable to quantify such benefits.

Regarding the commenter's recommendation to assess how the rule's benefits might be distributed across populations, FEMA agrees that ensuring equal access to FEMA funding for PA, IA, and HMA projects is important. The projects affected by this rule will be a subset of—only new construction or substantial improvement—projects currently funded through these programs. Accordingly, current FEMA initiatives address these concerns. For example, FEMA has an agency-wide initiative focused on reducing barriers and increasing opportunities so all people, including those from vulnerable and underserved communities, can get help when they need it. Additionally, FEMA reviews all proposed FEMA-funded actions for potential disproportionate and adverse human health and environmental effects on communities with environmental justice concerns using a standardized environmental justice compliance review process.

Comment: A commenter sought clarification of the term “cost-effective” within the RIA.

FEMA Response: FEMA added the definition of cost-effectiveness used within the RIA as “any alternative or measure whose discounted benefits are greater than its discounted costs” within the RIA to clarify this. FEMA acknowledges that it is possible define cost-effectiveness as ensuring the most efficient use of a given amount of resources, but notes that the definition in the RIA is consistent with BCA principles applicable to some FEMA grant programs.

Comment: A commenter stated that the gross omissions in the “BCA” render it useless, if not misleading as a BCA. The commenter referenced guidelines at both 40 CFR 1502.22 and Chapter III of Principles, Requirements and Guidelines for Water and Land Related Resources Implementation Studies (PR&G). The commenter did not provide data that would allow FEMA to fill the stated “omissions.”

FEMA Response: The commenter appears to be using the term “BCA” to refer generally to FEMA's regulatory impact analysis pursuant to E.O. 12866 and comparing the analysis to NEPA guidelines and PR&G. To the extent the commenter is referring generally to FEMA's regulatory impact analysis, FEMA recognizes that it has limitations based on available data, and provided qualitative analysis where it could not complete a quantitative analysis. OMB Circular A-4—the operating guidance for regulatory analysis conducted pursuant to E.O. 12866 —acknowledges that it may not be possible to express in monetary units all of the important benefits and costs. [ 272 ] Circular A-4 directs that if monetization is not possible, agencies should explain why and present all available quantitative information, and if agencies are not able to quantify the effects they should also present a description—along with strengths and limitations—of the unquantified effects.

FEMA adhered to this guidance. Although FEMA could not estimate the cost of the rule for facilities due to the highly project-specific nature of facilities projects, and the numerous options for making them resilient, FEMA was able to quantify the number of impacted facilities and explained why monetization was not possible. FEMA was unable to estimate the number of projects that would use each FFRMS approach per FEMA's policy, and so FEMA conducted an analysis assuming each FFRMS approach was the only one to demonstrate the range of possible costs. For benefits, FEMA acknowledged that the quantified estimates—where data allowed for quantification—represent only a portion of the increased risk reduction that will be achieved through this rule and discussed qualitatively other important benefits of the rule. When considering the total costs of the rule, FEMA noted that its choice of CISA as its preferred approach will use the best available and actionable scientific data to tailor future flooding risk to each project, ensuring that projects are built only to the elevation necessary and thus maximizing net benefits.

Comment: A commenter stated that the RIA did not comply with Circular A-4's requirements to present the net benefits for the different alternatives and provide a threshold or incremental analysis supporting the selection of FEMA's preferred alternative.

FEMA Response: As discussed above, Circular A-4 acknowledges that it may not be possible to express in monetary units all of the important benefits and costs. It notes that when important benefits and costs cannot be expressed in monetary terms, the calculation of net benefits is less useful, and “can even be misleading,” because in such cases, the calculation of net benefits do not provide a full evaluation of all of the relevant benefits and costs. Instead, Circular A-4 advises that in such circumstances agencies should exercise “professional judgment” in determining how important the non-quantified benefits and costs may be in the context of the overall analysis. [ 273 ]

As the commenter points out, Circular A-4 acknowledges that agencies “should also consider conducting a threshold analysis to understand the potential significance of these factors to the overall analysis.” FEMA considered including a threshold analysis, but such an analysis still would not have provided insight into the difference between the benefits of CISA, FVA, and 0.2PFA as data available to estimate quantitative benefits was limited to only one foot of freeboard for PA structure projects. The difference in unquantified impacts between the FFRMS approaches would result in comparison of thresholds comprising different sets of impacts. Accordingly, FEMA used its Start Printed Page 57008 professional judgment to determine that CISA is the best policy decision because it is meant to ensure that amount of additional flood protection for each project is determined by the best available, actionable hydrologic and hydraulic data and methods that integrate current and future changes in flooding based on climate science.

Comment: A commenter stated that the FFRMS RIA does not comply with the requirements for a Cost-Effectiveness Analysis (CEA) as detailed in OMB Circular A-4.

FEMA Response: FEMA recognizes it has limitations in the available data and agrees the RIA was not intended to be a CEA, as defined by OMB Circular A-4. FEMA notes that OMB Circular A-4 provides agencies with a choice of analytical approaches for regulatory analysis and does not require agencies to perform a CEA. [ 274 ] As mentioned above, FEMA provided qualitative analysis where it could not complete a quantitative analysis, as allowable under OMB Circular A-4. FEMA was unable to conduct a CEA because FEMA only had data available to estimate quantitative benefits of only 1 foot of freeboard for structures under the PA program. FEMA did not have data available to conduct the same quantitative analysis for projects under the IA and HMA grant programs or for additional levels of freeboard as applicable under each of the FFRMS approaches. Therefore, FEMA completed a Benefit Cost Analysis as it is more appropriate for this rulemaking given the wide range of unquantifiable benefits expected to accrue from each alternative.

Comment: FEMA requested public comment on any available data, examples showing the costs of similar resilience measures, case studies, or other relevant information that would assist FEMA in estimating the magnitude of the impact of the FFRMS on specific types of facilities. A commenter recommended contacting the “four water resource agencies” identified as “USACE, BuRec, DOE-TVA, and NRCS,” to what information in their current databases or relevant studies might be useful.

FEMA Response: FEMA appreciates this suggestion. FEMA has engaged with the U.S. Army Corps of Engineers (USACE), the Bureau of Reclamation (BuRec), the Tennessee Valley Authority (TVA), [ 275 ] and the National Resources Conservation Service (NRCS), and none of the agencies had relevant data or studies in relation to facilities that FEMA could use for this economic analysis. While such agencies—like FEMA—have access to some information on making facilities more resilient to flooding, [ 276 ] it is still not possible to use this information to generate estimates of the likely marginal cost of FFRMS implementation across FEMA-funded facility projects. The variety of projects, and unique characteristics of construction and repair of these projects does not allow FEMA to make estimates that can be broadly applied.

Comment: A commenter stated that the RIA is subject to the Principles and Requirements for Federal Investments in Water Resources March 2013. The commenter stated the RIA was inconsistent with the requirements of that document and supporting PR&G. Specifically, the commenter stated the RIA did not make any representation as to any alternatives that maximize public benefits relative to costs and failed to provide any representation of net public benefits. The commenter also stated the preferred alternative was not clearly defined and the commenter recommended FEMA disclose assumptions made and address uncertainties associated with the composition of the preferred alternatives consistent with the PR&G.

FEMA Response: As explained above, the PR&G does not generally apply to this rulemaking; rather, the PR&G applies to actions associated with water development projects. FEMA will apply the PR&G only to those specific actions under part 9 that are actions associated with a water development project.

Comment: One commenter noted that the baseline against which FEMA assessed the costs and benefits of this rule produced a “subjective assessment of the proposed rule's costs and benefits.” Specifically, the commenter stated that because FEMA said it was unable to conduct an analysis of the rule's effects separate from the effects of FEMA's recently implemented partial interim policies for Public Assistance (PA) and Hazard Mitigation Assistance (HMA) that the pre-guidance baseline it used was a “less-representative” analysis of the rule's costs and benefits.

FEMA Response: FEMA conducted its analysis under the pre-guidance baseline that considered the holistic effects of the partial interim policies for PA and HMA, as well as the proposed rule. At the time the Notice of Proposed Rulemaking (NPRM) RIA was conducted, these partial implementation policies had been in place for less than 2 years, which is an insufficient period to provide adequate data for analysis. These policies were issued as temporary, partial implementation of the FFRMS until FEMA could implement it through this rulemaking. FEMA conducted the Regulatory Impact Analysis against a pre-statutory baseline to capture the economic impacts of the FFRMS and more accurately measure the impacts of the rule against the world without the interim PA and HMA policies. Therefore, FEMA was unable to complete an in-depth analysis of the impact of these interim policies. Accordingly, FEMA used a pre-guidance baseline for this final rule to measure the impacts of the rule against the world without the interim PA and HMA policies.

Comment: A commenter provided several clarification edits.

FEMA Response: FEMA thanks the commenter for these suggestions. FEMA has added these clarifications to the RIA and updated the language as suggested.

Comment: A commenter suggested rounding dollar figures to an appropriate level of significance.

FEMA Response: FEMA appreciates this suggestion. FEMA adjusted the figures in the analysis, where feasible and appropriate.

Comment: A commenter stated that for the CISA floodplain analysis, the mid-point of +1′ and +10′ is +5.5′ would round to 6′. They recommend against characterizing the +5-ft CISA level as the mid-point.

FEMA Response: FEMA updated the RIA to clarify this was rounded down to 5-ft.

Comment: A commenter recommended deleting the “minimum, moderate, and maximum” for the SLR qualifiers throughout the document as the reader could come to a misunderstanding that the totality of the range for SLR rise is encompassed by the 8″ and 59″ figures. Start Printed Page 57009

FEMA Response: FEMA removed the terms minimum, moderate and maximum from 8-inch, 36-inch, and 59-inch, respectively as suggested.

Comment: A commenter stated that a footnote in the Executive Summary of the RIA could be misleading, as it stated that “the United States has suffered more than $1.7 trillion in flood-related damages over an approximately 40-year period.” The commenter noted that FEMA included tropical cyclones as a flood-related damage and stated that tropical cyclones entailed substantial wind making the $1.7 trillion figure potentially misleading.

FEMA Response: FEMA clarified within the footnote that severe storms can include wind-related damages, but the data does not separate these damages out.

Comment: A commenter sought clarification on the use of “Federal Investments,” stating that FEMA's use of the term might encompass actions taken by other agencies such as water resource agencies.

FEMA Response: FEMA's rule only applies to projects it funds under its grant programs. All other Federal agencies will implement the FFRMS using their own processes and procedures. FEMA made clarifications in the RIA to clarify use of the term “federal investments.”

Comment: A commenter suggested editorial changes to refer to “9.11” as 44 CFR 9.11 as it was unclear when it is standing alone.

FEMA Response: FEMA appreciates this clarification. FEMA made this change to 44 CFR 9.11 .

Comment: A commenter suggested editorial changes to Table ES-14.

FEMA Response: FEMA appreciates this suggestion. FEMA edited the RIA to reflect the commenter's requested changes.

Comment: A commenter corrected miscited footnotes.

FEMA Response: FEMA appreciates this suggestion. FEMA updated the footnotes as suggested by the commenter.

Comment: A commenter suggested removing page reference within a footnote as the footnote did not address avoided loss as stated in the RIA.

FEMA Response: FEMA typically includes a page number so that the readers can easily find the referenced source. FEMA updated the page citation to properly reflect the location in the document.

Comment: A commenter suggested reconciliation of different statements in the text in the bottom paragraph on page 17, Table ES-1, and the text in the second paragraph in the RIA regarding how FEMA analyzed the impact of each FFRMS expansion option as they are not consistent with one another.

FEMA Response: FEMA appreciates this suggestion. FEMA edited the document for consistency as suggested.

Comment: A commenter recommended re-titling Table ES-1 within the RIA since it was not consistent with its introductory text in the last paragraph on page 17.

FEMA Response: FEMA appreciates this suggestion. FEMA clarified the title to table ES-1.

Comment: A commenter recommended editorial changes to Table ES-3 within the RIA so that the rows were properly aligned.

FEMA Response: FEMA appreciates this suggestion. FEMA corrected this for the final rule.

Comment: A commenter recommended making editorial changes to the RIA and to use quotations around statements that were verbatim from an outside source.

FEMA Response: FEMA appreciates this suggestion. FEMA has gone through the document and made the recommended changes.

Comment: A commenter recommended FEMA edit a statement of present values, as present values are discounted by definition.

FEMA Response: FEMA appreciates this suggestion. FEMA removed the term undiscounted from the benefit statements for clarity purposes.

Comment: A commenter recommended FEMA edit the RIA to avoid confusion between discount rates and annual increases, providing an example within the Executive Summary of the RIA.

FEMA Response: FEMA clarified the wording to prevent confusion on the discount rates with annual increases.

Comment: A commenter pointed out inconsistency with the annualized CISA costs within Table ES-13 and ES-14.

FEMA Response: FEMA updated all of the costs for the final rule and reconciled this discrepancy.

Comment: A commenter requested FEMA delete an introductory sentence in RIA section 6.14 that states flooding is “by far the most common natural disaster type in the United States.”  [ 277 ] The commenter noted that NOAA distinguishes flooding as a category separate from tropical cyclones and storms which were both identified as having greater frequencies than flooding. The commenter also opined that storm damages are more properly associated with wind damage than with flooding.

FEMA Response: FEMA appreciates the commenter's concerns and deleted the sentence. Categorizing and calculating damage for different disaster types can be quite complex; however, the methodology set forth in the benefits section of the RIA is not dependent on resolution of these complexities. Further, it is not necessary to prove that flooding is the most common natural disaster type to state, as FEMA has in section 6.14 of the RIA, that there are benefits to mitigating against flooding.

Comment: A commenter requested rationale on why FEMA selected a 10-year period for the RIA. The commenter also recommended FEMA change language in the RIA to state that the agency limited the dollar-valuation to the projects impacted in the first 10 years following the rule's publication or expand the analysis to reflect economic concerns over the expected life of the regulation. The commenter stated additional discussion was needed regarding future effects and provided a number of questions around those effects including whether development within the floodplain would be progressively more likely to be diverted outside the floodplain over time and whether the costs of elevating or floodproofing would be expected to decline over time in real terms as contractors and architects adapt to the new requirements. The commenter asked whether it would be most appropriate to simply state that the first 10 years of the analysis was viewed as being a sample for the entire period or if the use of the maximum 8.5 RCP and the 59-inch SLR indicated a 50-year life for the regulation was suspected and that a shorter period of analysis was in order.

FEMA Response: FEMA appreciates the commenter's concerns regarding the analysis period. FEMA has clarified language throughout the RIA to further address the commenter's concerns. FEMA conducted the regulatory analysis using its standard 10 years of historical data and, based on this data, estimated the number of affected projects for the first 10 years after implementation of the rule. Circular A-4 directs that the timeframe for an agency's analysis “should cover a period long enough to encompass all the important benefits and costs likely to result from the rule.” FEMA believes estimating the number of affected projects over the initial 10 years and benefits over their 50-year useful life captures all the important benefits (protection from flooding) and costs (construction costs) likely to result from Start Printed Page 57010 the rule because FEMA does not expect a change in the types of costs or benefits after this time period. FEMA acknowledges that flooding is widely expected to increase in frequency and severity in the future, [ 278 ] so estimating the number of affected projects and their associated benefits farther into the future would become increasingly inaccurate as conditions change and the expected frequency and severity of disasters increases. However, due to increased flooding frequency and severity, FEMA believes that the benefits of increasing the protection of structures in the future is expected to continue to justify the cost of doing so beyond the 10-year timeframe that FEMA used for this analysis.

Regarding other future effects such as diversion of projects outside of the floodplain, FEMA notes that this is discussed within the RIA in the Qualitative Discussion of Additional Potential Costs section. The effect of the rule could be to divert some projects out of the floodplain. However, it is not possible to state with a reasonable degree of certainty how many projects this will affect, or the costs or benefits associated with diverting these projects out of the floodplain, as FEMA does not currently track this information. The costs and benefits, and the decision to build inside or outside of the floodplain, will be dependent on the specific location or characteristics of a property or project.

Comment: A commenter stated that they could not find the “2022 Benefits Analysis of Increased Freeboard for Public and Nonresidential Buildings in Riverine and Coastal Floodplains” file at regulations.gov under docket ID FEMA-2023-0026.

FEMA Response: FEMA verified that all of the supporting documents were listed on the site during the comment period, including the report referenced. [ 279 ]

Comment: A commenter pointed out confusion with the footnote “25 FEMA's project level data for IA, PA, and HMA delineate whether projects are in the Special Flood Hazard Area (1 percent annual chance floodplain) but do not show whether they are in the 0.2 percent chance floodplain” because FIRMs characteristically identify both the 1 percent annual chance floodplain and the 0.2 percent annual chance floodplain.

FEMA Response: FEMA agrees that the 0.2 percent annual chance floodplain, in locations where that floodplain is mapped, is available on FIRMs. However, the data availability issue noted in the footnote is that FEMA's project databases ( e.g., IA, PA, HMA) do not include FIRM data, so FEMA is not able to accurately determine whether a project is in the 0.2 percent chance floodplain. FEMA's project level data only indicate whether a project is located in the SFHA in most cases. Project databases do not contain accurate geolocation data, and addresses on file are for the recipient's address, which may not be the project location, so FEMA was unable to locate projects on a FIRM, or determine which flood zone a project was located in.

Comment: A commenter stated that FEMA's preferred policy approach is not clearly defined, as it consists of an unidentified mixture of CISA, FVA, and 0.2PFA, which requires the reader to speculate and make assumptions about the composition in order to draw conclusions. The commenter suggested FEMA discuss the uncertainty associated with the composition of the FFRMS approaches that comprise FEMA's preferred policy approach.

FEMA Response: FEMA selected CISA as the preferred policy approach, since FEMA believes it has the potential to be the best and most well-informed approach to building resilience in an equitable manner and ensuring a reduction in disaster suffering. CISA is designed to meet current and future estimates of flood risks unique to the location and thus provide the best overall resilience, cost effectiveness, and equity. FEMA added clarification on what the primary approach is earlier in the RIA.

FEMA acknowledges that its policy—which requires use of FVA and 0.2PFA when CISA data are not available and actionable—will result in an unknown mixture of projects using CISA, FVA, and 0.2PFA. OMB Circular A-4 suggests using central estimates “where such information exists” but authorizes the use of upper and lower bounds where it does not, together with any available information that might help in qualitatively determining which scenario is most likely to occur. FEMA conducted its analysis to consist of a range of potential costs, benefits, and transfers. FEMA analyzed the impact of the FVA, 0.2PFA, and CISA for each of the programs, PA, IA, and HMA, as if each approach were the only FFRMS expansion option. FEMA discussed that because the composition of applied FFRMS approaches will continue to change with the addition of CISA data over time, there is significant uncertainty in any such estimates. Accordingly, FEMA estimated the costs of the requirements for each of the approaches separately to create upper and lower bounds estimates of the possible outcomes. In addition, as discussed above, FEMA presents CISA as the primary estimate for the impacts of the rule because it is FEMA's preferred FFRMS approach and therefore, over time, it will become the most widely used FFRMS approach.

Comment: A commenter disagreed with FEMA's statement about how “RCP 4.5 and 8.5 are widely accepted scenarios that represent medium and low efforts to curb emissions, respectively.” They suggested better explaining the definitions of RCP 4.5 and 8.5 based on the EPA's language about RCPs.

FEMA Response: FEMA appreciates this suggestion. FEMA updated the use of RCP 4.5 and 8.5 and the definitions for the Final Rule RIA.

Comment: A commenter suggested explaining the terms “low estimate” and “high estimate” earlier in the RIA. They also suggested that instead of using a range, FEMA should present a best estimate for these values and discuss the uncertainty associated with such values in the Risk and Uncertainty section of the document. They also requested a sensitivity analysis showing how the decision might be affected if the values used proved to be unduly high or low. The commenter suggested that because of the number of variables contributing to the ranges ( e.g., discount rate, high and low), the presentation of information would be clearer if single, best-estimate, rounded values were used in the analysis.

FEMA Response: OMB Circular A-4 suggests using central estimates “where such information exists” but authorizes the use of upper and lower bounds where it does not. In the instances where FEMA uses a range, it is because FEMA does not have adequate justification for a single best estimate. FEMA conducted its analysis to consist of a range of potential costs, benefits, and transfers. For example, as discussed above, FEMA analyzed the impact of the FVA, 0.2PFA, and CISA for each of the programs, PA, IA, and HMA, as if each approach were the only FFRMS expansion option because it is unknown exactly how many projects will be subject to the FVA, 0.2PFA, or CISA requirements under the final rule, and how use of CISA will change as more data become available over time. Because FEMA analyzed each approach Start Printed Page 57011 separately, it is unable to provide a primary estimate, and instead had to rely on a range of possible impacts. In addition, FEMA does not have data to estimate whether certain non-residential new construction projects will elect to floodproof or elevate and therefore also used a range for the cost of meeting the rule's increased construction standards.

FEMA appreciates that the presentation of the range of impacts may not be as clear as a single point estimate. FEMA presents this information in tables, to help more clearly convey the information, and has also reviewed the language and streamlined for increased clarity.

Comment: A commenter provided editorial suggestions to the statement: “CISA is the only approach that ensures projects are designed to meet current and future flood risks unique to the location and thus provides the best overall resilience, cost effectiveness, and equity.” The commenter suggested the claim that CISA makes such an assurance is an overstatement of the risk reduction from the CISA.

FEMA Response: FEMA appreciates this suggestion. FEMA accepted this change in part: “CISA is designed to meet current and future estimates of flood risks unique to the location and thus provide the best overall resilience, cost effectiveness, and equity.”

Comment: A commenter provided suggested edits to FEMA's statement regarding whether the action was a significant regulatory action under Executive Order 12866 , as amended by Executive Order 14094 .

FEMA Response: This is standard language that FEMA uses in RIAs. FEMA provided footnotes to this statement clarifying the relevant sections of Executive Order 12866 .

Comment: A commenter recommended presenting the CISA-only analysis as an alternative or explaining why it was found to be unreasonable and including it in the section of the document on alternatives considered but not selected. If FEMA found a CISA-alone approach to be unreasonable, the commenter recommended changing all blanket statements in the document that describe CISA as the best approach for achieving overall resilience, cost effectiveness, and equity.

FEMA Response: The CISA is one of three approaches available under the FFRMS, and FEMA's preferred approach. However, because the CISA data is not available nationwide, a CISA-only approach is not currently feasible, and other FFRMS approaches are needed for areas where the CISA is not available. FEMA's implementation of the FFRMS allows for the use of the most appropriate approach depending on the data available for a given project. Although FEMA estimated the impacts of the CISA for affected programs as if it were the only FFRMS expansion option, just as it did for the FVA and 0.2PFA, FEMA was unable to use actual CISA estimates, as they are not yet available nation-wide and instead used an estimate. As the CISA data becomes more available, FEMA expects it to be the more widely-adopted. FEMA made clarifying edits to statements describing the CISA as the preferred approach.

Comment: A commenter encouraged FEMA to consider implications of FEMA's FFRMS policy on benefit-cost analyses for flood mitigation assistance grants.

FEMA Response: FEMA appreciates the commenter's concerns. FEMA's FFRMS policy will generally not change BCA requirements for FEMA programs. Certain Hazard Mitigation Assistance programs and Public Assistance projects are subject to a Benefit-Cost Analysis prior to approval, where the mitigation action must be determined to be cost-beneficial using FEMA's BCA tool. For FEMA's FMA program, the costs of additional elevation above the base flood elevation will be considered as part of the BCA. Currently, the BCA tool includes pre-calculated benefits that streamline the cost-effectiveness determination for structure elevation projects are limited to structures where some part of the structure is within the 1 percent annual chance floodplain. For an elevation project where the entire structure footprint is outside the 1 percent annual chance floodplain, FEMA will also require a BCA to show cost-effectiveness. For FEMA's PA program, cost-effectiveness requirements apply only to Hazard Mitigation measures on projects to restore disaster damaged structures and facilities. FEMA notes that any increased costs are generally eligible for funding under FEMA's assistance programs subject to cost share requirements. FEMA acknowledges that FFRMS requirements may impact individual BCA results, with the potential to cause some projects to pass that otherwise wouldn't, and vice-versa, but is not able to predict this for future individual projects because project-level analysis is not generalizable nationwide. For structures, FEMA estimates the marginal cost of implementing FFRMS to be relatively low, ranging from 0.32 percent (1 foot of elevation for new construction) to 8.07 percent (4 feet of dry floodproofing for a building retrofit) of total project cost, depending on the elevation required and the type of project. Given available evidence showing relatively small costs and even positive increases in Benefit-Cost Ratio in connection with additional elevation for studied residential buildings, FEMA does not expect FFRMS requirements to adversely affect the BCR for a large volume of projects. [ 280 281 ]

Comment: A commenter questioned the baseline data used for the floodplain expansion analysis in Appendix A. The commenter stated that FEMA should have compared the 1' freeboard measured to the “Effective/Preliminary 1 percent annual chance floodplain” instead of the “replotted” 1 percent annual chance floodplain.

FEMA Response: The goal of the floodplain expansion analysis performed by FEMA is to estimate the number of additional projects that would be affected by a requirement for a higher vertical elevation, and thus horizontal expansion, of the floodplain. When FEMA calculated the FFRMS floodplains for different freeboard values, FEMA used the latest high-accuracy ground elevation data. The original 1 percent annual chance floodplain boundaries were likely calculated using older ground elevation data. For consistency, FEMA compared the FFRMS freeboard-based floodplains to a 1 percent annual chance floodplain redrawn using the new ground elevation data. This approach provides the most consistent comparison of the difference in area between the 1 percent annual chance floodplain and the FFRMS floodplain ( i.e., specific levels of freeboard added to the 1 percent annual chance flood elevations). This approach does not account for differences between the redrawn 1 percent annual chance floodplain boundaries and the original 1 percent annual chance floodplain boundaries. Since the goal is to produce a statistical estimate of the impact of freeboard, FEMA assumed the differences between the original 1 percent annual chance boundaries and the redrawn 1 percent annual chance boundaries would be largely random and not essential to the goal of the estimate.

Comment: A commenter assessed that FEMA's statements that a study upon Start Printed Page 57012 which it relied considered various levels of SLR “by 2100” is problematic, as the study does not extend as far as the year 2100, and it actually only extends some 60 years into the future. The commenter sought clarification.

FEMA Response: FEMA would like to distinguish between the coastal and riverine flood studies used within the 2022 Report. [ 282 ] The riverine analysis considered two climate change scenarios to evaluate the amount of increase or decrease in riverine flood elevations over the next 50 years. These evaluated two widely accepted scenarios of the Representative Concentration Pathways (RCP) 4.5 and 8.5, which represent medium and low efforts to curb emissions.

The coastal study within the 2022 Report considered 12 different locations along a hypothetical coastal transect to evaluate the impact of various wave conditions in Zone A (areas with wave heights less than 1.5 feet) subject to coastal storm surge. The sea level rise conditions replicated a 2016 evaluation considered 8-inch, 20-inch, 39-inch, and 59-inch sea level rise by 2100. [ 283 ] The sea level rise assumptions are explained in the 2022 report. Specifically, when evaluating the increases in flood depths, the rise scenarios were considered in 10-year increments from 2022 to 2100, but the evaluation of the benefits is limited to the 50-year useful life of a project ( i.e., from 2022-2072). The assumed increase in flood depths is shown in Table 1 of the report in 10-year increments.

Consistent with FEMA's BCA guidance, [ 284 ] FEMA selected the 50-year project useful life which is the timeframe evaluated to determine the cost-effectiveness for a public building and is consistent with the assumption in the FEMA BCA Toolkit. FEMA's analysis focuses on the costs, benefits, and transfer payments ( i.e., impacts on FEMA grants), that will result over a 50-year period from the application of the requirements of the final rule to those projects, for a total period of analysis spanning 60 years. For example, if a structure is built in Year 10, the analysis covers 50 years of costs, benefits, and transfers for that structure starting in Year 10. However, if a structure is built in Year 11, that is outside of the first 10 years, and so the analysis does not consider the costs, benefits, or transfers of the FFRMS requirements on that structure. [ 285 ]

This rule makes changes to the NPRM in response to comments received, as well as minor technical edits. Specifically, in § 9.7(c)(3), FEMA made a clarifying edit by adding the words “information from” before the colon, such that the sentence reads “In obtaining the best available information, FEMA may consider other FEMA information as well as other available information, such as information from:”

FEMA also edited § 9.7(c)(3)(iv) to include the National Park Service as an agency within the Department of the Interior where FEMA obtains information. FEMA also edited § 9.7(c)(3)(ix) to include Indian Tribal governments; as revised, this paragraph now reads, “Agencies of State, Regional, and Indian Tribal governments.” While FEMA always considered Tribal information, the edits further confirm the agency's commitment to doing so. The changes made to § 9.7(c)(3) clarify that FEMA considers certain relevant and appropriate data in making the floodplain determination under part.

FEMA is also making minor technical edits in § 9.7(c)(1)(i)(C) and § 9.11(d)(3)(ii). In § 9.7(c)(1)(i)(C), FEMA is adding appropriate hyphenation to state “0.2-Percent-Annual-Chance Flood Approach (0.2PFA): The 0.2 percent annual chance flood” for consistency with the Revised Guidelines. In § 9.11(d)(3)(ii), FEMA is correcting a grammatical error from “water tight” to “watertight.”

FEMA's FFRMS policy is also being finalized with the publication of this rule and will be effective with the rule's implementation. FEMA is making minor clarifying edits to the FFRMS policy consistent with commenters' suggestions by further clarifying the use of the 0.2PFA in coastal areas and making other technical edits to the document for readability. Specifically, FEMA is making technical formatting and grammatical edits on pages 1, 2, 3, 4, 7, 8, and 13. FEMA is adding clarifying language in section C. In section C.2, FEMA is eliminating the reference to wave action in coastal areas at the end of the paragraph. In section C.3.a, FEMA is adding the following clarifying text in footnote 14: “In coastal areas Flood Insurance Rate Maps (FIRMs) and Flood Insurance Studies (FISs) provide 1 percent AC flood elevations that account for the effects of wave action. However, 0.2 percent AC flood elevations are generally stillwater elevations that do not account for the effects of wave action. In coastal areas, if the 0.2 percent AC flood elevation does not account for the effects of wave action, the FVA flood elevation must be used.” FEMA is further eliminating section C.3.c consistent with these edits. FEMA also edited Figure 1 in the FFRMS policy to clarify “AC” means “annual chance” at a commenter's request and reflect the clarifications to C.3 referenced above. Additionally, FEMA updated section G.2 to reflect “Flood Risk Mitigation for Facilities.” FEMA removed the term “non-structure” in that section because commenters expressed confusion about the term.

Executive Orders 12866 (Regulatory Planning and Review), as amended by Executive Order 14094 (Modernizing Regulatory Review), and 13563 (Improving Regulation and Regulatory Review), directs agencies to assess the costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). Executive Order 13563 emphasizes the importance of quantifying costs and benefits, reducing costs, harmonizing rules, and promoting flexibility. The Office of Management and Budget (OMB) has designated this Start Printed Page 57013 rule a “significant regulatory action” as defined under section 3(f) of Executive Order 12866 , as amended by Executive Order 14094 , but it is not significant under section 3(f)(1) because its annual effects on the economy do not exceed $200 million in any year of the analysis. Accordingly, OMB has reviewed this rule.

This analysis provides an assessment of the potential costs, benefits, and transfer payments from the Updates to Floodplain Management and Protection of Wetlands Regulations to Implement the Federal Flood Risk Management Standard (FFRMS) Final Rule. For further detail please refer to the Regulatory Impact Analysis (RIA) in the docket accompanying this rule.

FEMA is amending 44 CFR part 9 Floodplain Management and Protection of Wetlands and issuing a supplementary policy  [ 286 ] to implement the FFRMS and update the agency's 8-step decision-making process used to determine whether an action would be located within or affect a floodplain, and if so, whether and how to continue with, or modify, the action.

The FFRMS is a flood resilience standard that is required for Federally funded projects and provides a flexible framework to increase resilience against flooding and to help preserve the natural values of floodplains and wetlands. A floodplain is any land area that is subject to flooding and refers to geographic features with undefined boundaries. FEMA will incorporate the FFRMS into its existing processes to ensure that the floodplain for an action subject to the FFRMS is expanded from the current 1 percent annual chance (100-year) floodplain based on the one percent annual chance elevation  [ 287 ] to a higher vertical elevation and corresponding horizontal floodplain; and that, where practicable, natural systems, ecosystem processes, and nature-based approaches will be considered when developing alternatives to locating Federal actions in the floodplain.

Under current FEMA regulations set out in 44 CFR part 9 , the floodplain is defined as the 100-year floodplain (1 percent annual chance) for non-critical actions and the 500-year floodplain (0.2 percent annual chance) for critical actions. New construction or substantial improvement of structures located in a floodplain must be elevated to or above the 1 percent annual chance (100-year) flood level or base flood elevation (BFE). For critical actions, the new construction or substantial improvement of structures must be elevated to or above the 0.2 percent annual chance (500-year) flood level. Non-residential structures may be appropriately floodproofed rather than elevated to meet the applicable flood level.

This rule will implement the supplemental FFRMS policy in the expanded floodplain and codify implementation of the supplemental FFRMS policy in the current floodplain. FEMA has interim policies for PA and HMA that partially implement FFRMS, as discussed in further detail below. Depending on the program, these programs apply the supplemental FFRMS policy either to the base floodplain, or to both the 100-year (base floodplain) and 500-year floodplain (for critical actions). Following guidance in OMB Circular A-4, FEMA assessed each impact of this rule against a pre-guidance baseline. The pre-guidance baseline is an assessment against what the world would be like if the relevant guidance ( i.e., the partial interim policies for PA and HMA) were not implemented.

At the time the Notice of Proposed Rulemaking (NPRM) RIA was conducted, these partial implementation policies had been in place for less than 2 years. These policies were issued as temporary, partial implementation of the FFRMS until FEMA could implement it through this rulemaking. FEMA conducted this Regulatory Impact Analysis against a pre-statutory baseline to capture the economic impacts of the FFRMS and more accurately to measure the impacts of the rule against the world without the interim PA and HMA policies.

Under the final rule, the Climate-Informed Science Approach (CISA) would result in a flood elevation and corresponding horizontal expansion floodplain determination utilizing the best-available, actionable hydrologic and hydraulic data and methods that integrate current and future changes in flooding based on climate science. The CISA is FEMA's preferred policy approach, as FEMA believes it has the potential to be the best and most well-informed approach to building resilience in an equitable manner and ensuring a reduction in disaster suffering. CISA is designed to meet current and future estimates of flood risks unique to the location and thus provide the best overall resilience, cost effectiveness, and equity. The FFRMS requires FEMA to consider the criticality of the action involved, the availability and actionability of data, and equity concerns, as further explained in the supplementary policy. As actionable climate data are not currently available for all locations, FEMA will utilize the Freeboard Value Approach (FVA) and 0.2-Percent-Annual-Chance Flood Approach (0.2PFA) alternatives in the absence of actionable CISA data. Specifically:

  • For critical actions:  [ 288 ] FEMA will use the higher of the +3-foot FVA floodplain or the 0.2PFA floodplain. [ 289 ] Where the 0.2PFA data is not available, the +3-foot FVA will be utilized.
  • For non-critical actions: FEMA will use the lower of the +2-foot FVA or 0.2PFA. [ 290 ]

The floodplain established by the FVA is the equivalent of the 1 percent annual chance floodplain (also known as the 100-year flood), plus either 2 or 3 feet of vertical elevation, as applicable based on criticality, and a corresponding increase in the horizontal extent of the floodplain. The increased horizontal extent will not be the same in every case. When the same vertical increase is applied in multiple actions subject to the FFRMS in different areas, the amount of the increase in the horizontal extent of the respective floodplains will depend upon the topography of the area surrounding the proposed location of the action.

The term 0.2PFA refers to the elevation to which floodwater is anticipated to rise during the 0.2 percent annual chance flood (also known as the 500-year flood) and the associated floodplain. The 0.2PFA generally covers a larger area than the 1 percent annual chance floodplain. Start Printed Page 57014

Projects that are located near a Special Flood Hazard Area (SFHA), [ 291 ] but not in it, may be in the FFRMS floodplain. At the time the NPRM was published, there were no FEMA products depicting the boundary of the FFRMS floodplain. For this reason, FEMA and its interagency partners have developed and are continuing to develop various tools, including the FFRMS Floodplain Determination Job Aid published on FEMA's website and in the public docket with this rulemaking and a web-based decision support tool, Federal Flood Standard Support Tool (FFSST), that will provide the agency with guides to determine which FFRMS floodplain approach has available and actionable data, in map form, thus should be used for each project. The FFRMS Job Aid helps Federal agencies and their non-federal partners (including potential Federal financial aid recipients) conduct a screening to determine if a proposed Federally funded action will be located within an FFRMS floodplain, based on any of the three approaches in accordance with Sec. 2(a)(1) of Executive Order 11988 , as amended. FEMA will leverage the FFRMS Job Aid for determining the FFRMS floodplain when the final rule is implemented. FEMA will continue to collaborate across the Federal government to continue to develop the FFSST to facilitate the implementation of the CISA and the FFRMS.

FEMA developed a flexible approach to implementing the FFRMS to maximize the net benefits—quantified and unquantified—of the rule. Floods are expected to be more frequent and more severe over the next century due to the projected effects of changing conditions. [ 292 293 ] The ocean has warmed, polar ice has melted, and porous landmasses have subsided. [ 294 ] The global sea level has risen by about 8 inches since reliable record keeping began in 1880. [ 295 ] It is projected to rise upwards of 1 to 4 feet by 2100, affecting many coastal areas. [ 296 297 298 ] Floods are costly natural disasters; between 1980 and 2022, the United States suffered more than $2.0 trillion (in 2022 dollars) in flood-related damages. [ 299 ] This final rule will help protect FEMA funded investments from future floods and will help minimize harm in floodplains by changing the standards used to determine future risk for FEMA-funded new construction and substantial improvement, and/or to address substantial damage to Federally funded projects.

The requirements of this rule will apply to grants under FEMA programs such as Individual Assistance (IA), Public Assistance (PA), and Hazard Mitigation Assistance (HMA), as well as grants processed by FEMA's Grants Programs Directorate (GPD) (involving grants for preparedness activities), for projects funding new construction, substantial improvement, or repair of substantial damage. The primary focus of this analysis is to estimate the costs and benefits resulting from a higher vertical elevation and associated horizontal expansion of the floodplain for specific projects paid for with Federal funds. The expected impacts of this final rule primarily result from the cost of the increase in elevation or floodproofing requirements of structures in the FFRMS floodplain. The majority of these costs will be funded by FEMA through several grant programs. For the grant programs that have a cost-share requirement, FEMA grant recipients typically will bear about 25 percent of the elevation and floodproofing project costs. Additionally, FEMA expects to incur costs for administration of the FFRMS requirements, including training FEMA personnel.

To estimate the number of projects that will be subject to the requirements of this rule, FEMA used historical PA, IA, and HMA data. First, FEMA estimated the number of past new construction, substantial improvement, or repairs to substantial damage projects that are in the existing floodplain. Next, FEMA relied upon data from samples of floodplain expansion at varying levels of freeboard in inland and coastal areas to estimate an average percentage expansion of the floodplain under each of the three FFRMS approaches. FEMA then multiplied the expansion percentages by the estimated number of projects in the current floodplain to estimate the number of projects that will be in the expanded floodplain under each of the FFRMS approaches.

To estimate the cost of the FFRMS elevation requirements, FEMA used reports from the National Flood Insurance Program (NFIP) to determine the increased cost per square foot associated with elevation and floodproofing. FEMA presents the costs as a range because of uncertainty about whether new construction projects would choose to floodproof or elevate.

Finally, to present the total impacts of the final rule, FEMA analyzed the impact of the FVA, 0.2PFA, and CISA for each of the programs, PA, IA, and HMA, as if each approach were the only FFRMS expansion option. This is because it is unknown exactly how many projects will be subject to the FVA, 0.2PFA, or CISA requirements under the final rule, as it will continue to change with the addition of CISA data over time. Accordingly, FEMA estimated the costs of the requirements for each of the approaches separately. This allows FEMA to create a range for each approach. FEMA is opting to use this methodology because it allows for estimation of the highest and lowest probable costs, transfers, and benefits associated with each of the FFRMS expansion options for each of the programs.

FEMA limited its dollar-valuation to the projects impacted in the first 10 years after the rule's effective date. [ 300 ] FEMA's analysis focuses on the costs, benefits, and transfer payments ( i.e., impacts on FEMA grants), that will result over a 50-year period  [ 301 ] from the application of the requirements of the final rule to those projects, for a total period of analysis spanning 60 years. For example, if a structure is built in Year 10, the analysis covers 50 years of Start Printed Page 57015 costs, benefits, and transfers for that structure starting in Year 10. However, if a structure is built in Year 11, that is outside of the first 10 years and so the analysis does not consider the costs, benefits, or transfers of the FFRMS requirements on that structure. [ 302 ] The costs and transfers occur in the first 10 years of the 60-year period because that is when the initial investment to elevate or floodproof those projects takes place. This is an upfront cost that occurs when the project is constructed. However, the benefits of the final rule are estimated over the 50-year useful life of the affected structures.

The table below provides the estimated number of structures and facilities that will be affected by the final rule over the first 10 years, assuming that each approach is the only expansion option. Structures that are walled and roofed buildings, will comply with the FFRMS through elevating or floodproofing to the required height. Facilities, which are any human-made or human-placed items other than structures, such as roads and bridges, will require different mitigation measures in order to comply with the increased resiliency standard of the final rule. The monetized impacts of this rule are representative of the floodproofing and elevation mitigation measures that will be required of structures. However, for reasons explained in more detail later, FEMA was unable to monetize the impacts of the rule for facilities.

case study in distribution management

The final rule will increase construction and resiliency standards for FFRMS-affected structures and facilities. FEMA considers implementing these standards, whether through higher vertical elevation, floodproofing, or other mitigation measures, to be new economic activity that will result from this rule. Accordingly, these compliance activities are categorized as costs of this rule.

FEMA analyzed the impact of the FVA, 0.2PFA, and CISA for each of the programs, PA, IA, and HMA, as if each approach were the only FFRMS expansion option. FEMA selected the CISA as the primary approach as it is the preferred option. Using the CISA as the primary approach, FEMA has estimated that this final rule will affect 13,476 PA, IA, and HMA structures over the first 10 years. The low estimate  [ 305 ] cost will be between $134.0 million and $110.4 million, discounted at 3 and 7 percent respectively, with a 60-year annualized cost between $4.8 million and $7.9 million, discounted at 3 and 7 percent. The high estimate cost will be between $169.8 million and $139.9 million, discounted at 3 and 7 percent respectively, with a 60-year annualized cost between $6.1 million and $10.0 million, discounted at 3 and 7 percent respectively. These costs include additional training for FEMA staff, as well as the total cost for additional elevation and floodproofing. FEMA is unable to quantify the cost for increased resiliency standards for an estimated 26,985 affected facility projects over the first 10-year period of the analysis. Additionally, FEMA is unable to quantify the cost for projects that may be diverted out of the floodplain, impacts to projects with existing basements, project delays, or forgone projects that may result from this rule.

Because the cost to implement the FFRMS mitigation measures will be shared between FEMA and grant recipients according to statutory cost shares, there are also important distributional impacts. The majority of these costs will be borne by FEMA through additional grants (a transfer from FEMA to grant recipients). Grant recipients will bear the remaining costs. Using the CISA as the primary approach, FEMA estimates that this final rule will affect 13,476 structures in the first 10 years. FEMA presents the change in transfer payments from FEMA to grant recipients as a range because of uncertainty regarding whether new construction projects would be floodproofed or elevated. The low estimate ranges between $104.7 million and $86.2 million, discounted at 3 and 7 percent respectively, with a 60-year increase in transfers between $3.8 million and $6.1 million annually, discounted at 3 and 7 percent respectively. The high estimate ranges between $134.2 million and $110.5 million, discounted at 3 and 7 percent Start Printed Page 57016 respectively, with a 60-year increase in transfers between $4.8 million and $7.9 million annually, at 3 and 7 percent respectively.

Grant recipients will be responsible for between $22.6 million and $18.6 million, discounted at 3 and 7 percent respectively, with a 60-year annualized amount between $0.8 million and $1.3 million, at 3 and 7 percent respectively for the low estimate. The high estimate ranges between $27.8 million and $22.9 million, discounted at 3 and 7 percent respectively, with a 60-year annualized amount of $1.0 million and $1.6 million, at 3 and 7 percent respectively. Not included in these estimates are the additional grants FEMA will provide or the additional costs recipients will incur for their portion of the cost share, for any of the elevation and floodproofing costs that FEMA is unable to monetize.

FEMA has been able to quantify benefits for a small portion of projects affected by the rule. Using CISA as the primary approach, FEMA estimates that 1,154 PA Category E (Public Buildings)  [ 306 ] projects will be subject to the FFRMS in the first 10 years. Assuming a 59-inch Sea Level Rise, [ 307 ] FEMA estimates that the present value benefits of one additional foot of freeboard for the 50-year useful life of projects undertaken during the 10-year period of analysis ranges at the low end between $56.1 million and $46.2 million, discounted to the beginning of Year 1 at 3 and 7 percent respectively, with a 60-year annualized benefit between $2.0 million and $3.3 million. The high estimate ranges between $66.1 million and $54.4 million, discounted to the beginning of Year 1 at 3 and 7 percent respectively, with a 60-year annualized benefit between $2.4 million and $3.9 million. These quantified benefits include estimates of avoided physical damage, avoided displacement, and avoided loss of function for the 1,154 PA Category E projects over their 50-year useful life. In addition, unquantified benefits of this final rule include the reduction in damage to 12,322 affected IA and HMA structures and their contents from future floods, 26,985 PA and HMA facilities, potential lives saved, public health and safety benefits, reduced recovery time from floods, and increased community resilience to flooding.

Table 5 shows the summary of the total costs, benefits, and distributional impacts of the final rule.

case study in distribution management

FEMA provides PA grants to public and certain non-profit entities for the rebuilding, replacement, or repair of public and non-profit structures and facilities damaged by disasters. PA projects that involve new construction, substantial improvement, or repairs to address substantial damage are affected by this rule. FEMA divides its PA work into categories A-G. [ 308 ] Projects that get funding under PA Categories C (Roads and Bridges), D (Water Control Facilities), E (Public Buildings), F (Utilities), and G (Parks, Recreational Areas, and Other Facilities) are affected by this rule, but FEMA is only able to provide estimates of costs associated with Category E (Public Buildings). FEMA has adequate data to estimate the additional costs for structures subject to the FFRMS, so monetized impacts are only available for Category E projects. The remaining PA categories fund facilities that are not subject to the same elevation and floodproofing requirements as buildings.

44 CFR part 9 classifies projects as either structures or facilities. Under this rule, a structure is a walled and roofed building, including mobile homes and gas or liquid storage tanks. Structures will be subject to freeboard requirements to floodproof or elevate to a certain level above the BFE. Freeboard is the additional height above the BFE to which the structure is floodproofed or elevated for the purpose of reducing the risk of flood damage.

In contrast, facilities are any human-made or human-placed item other than a structure, including roads, bridges, power lines, water control facilities, and other types of infrastructure. Facility mitigation measures are more varied and highly project-specific. For example, damage to roads during flood events can be caused by numerous events, such as erosion and scour, inundation by floodwater, or debris blockage. Likewise, the mitigation measures to address the damages can include a variety of approaches, such as installing low water crossings, increasing culvert size, installing a relief culvert, adding riprap to a road embankment, and many others. [ 309 ]

Due to the highly project-specific nature of facilities projects, and the numerous options available for making them resilient, FEMA cannot estimate the costs of improving flood resiliency of facilities. Where FEMA provides funding for facilities to complete new construction, substantial improvement, or repairs to address substantial damage, the projects must incorporate minimization measures that will consider the FFRMS flood elevation. However, floodproofing and elevation to a specific height may not be appropriate as a minimization measure for facilities, depending on the facility. FEMA cannot estimate the cost due to the variability of those measures, which may include a variety of approaches. Facilities that are already located in the 1 percent annual chance floodplain for non-critical actions or 0.2 percent annual chance floodplain for critical actions must take resilience measures under current regulations. Based on 2013-2022 data, FEMA estimates that about 1,036 Category C projects, 120 Category D projects, 208 Category F projects, and 314 Category G projects may be affected by the FFRMS each year.

For PA Category E projects, if the FVA is the only expansion option, FEMA estimates the final rule will affect 899 projects over the first 10 years. The costs Start Printed Page 57019 would be incurred in the first 10 years of the 60-year period because that is when the investment in those projects takes place. Accordingly, FEMA estimated that the average annual costs in years 1-10 will range between $4.3 million and $5.5 million. The average Federal cost share for PA projects from 2013-2022 was 85.0 percent. Accordingly, FEMA estimates that it will cover 85.0 percent of the cost to elevate or floodproof PA projects, for a total of between $3.6 million and $4.7 million in additional grants per year for the first 10 years. Grant recipients will bear the remaining cost of between $0.6 million and $0.8 million per year for the first 10 years.

For PA Category E projects, if 0.2PFA is the only expansion option, FEMA estimates the final rule will affect 688 projects over the first 10 years. Because these costs are incurred in the first 10 years, FEMA estimated the average annual costs in years 1-10 will range between $2.5 million and $3.2 million. Using the historical average 85.0 percent Federal cost share, FEMA estimates that it will cover 85.0 percent of the cost to elevate or floodproof PA projects, for a total of between $2.1 million and $2.8 million in additional grants per year for the first 10 years. Grant recipients will bear the remaining costs of approximately $0.4 million and $0.5 million per year for the first 10 years.

For PA Category E projects, if CISA is the only expansion option, FEMA estimates the final rule will affect 1,154 projects over the first 10 years. Because these costs are incurred in the first 10 years, FEMA estimated the average annual costs in years 1-10 will range between $10.4 million and $14.5 million. Using the historical average 85.0 percent Federal cost share, FEMA estimates that it will cover 85.0 percent of the cost to elevate or floodproof PA projects, for a total of between $8.9 million and $12.3 million in additional grants per year for the first 10 years. Grant recipients will bear the remaining cost of between $1.6 million to $2.2 million per year for the first 10 years.

case study in distribution management

Individual Assistance (IA) grants are provided to individuals who, as a direct result of a disaster, have necessary expenses and serious needs that they are unable to meet through other means. IA funding is divided into Housing Assistance and Other Needs Assistance. Other Needs Assistance under IA provides financial assistance for medical, dental, childcare, funeral, personal property, transportation, or other necessary expenses or serious needs and is not subject to FFRMS requirements. Under Housing Assistance, FEMA may provide temporary housing assistance (financial assistance or direct assistance in the form of temporary housing units), a capped amount of financial assistance for the repair or replacement of disaster-damaged private residences; and, in rare circumstances, financial or direct assistance to construct permanent or semi-permanent housing.

The financial caps on housing repair or replacement assistance means IA grants do not generally fund new construction or substantial improvements. However, two types of IA grants are affected by the final rule: IA Permanent Housing Construction (PHC) projects, and sales and disposal of temporary housing units (THUs). PHC is Federal assistance that FEMA provides under IA for the purpose of constructing permanent housing where alternative housing resources are unavailable or scarce. IA also includes the sale and disposal of THUs such as mobile housing units and recreational vehicles; THUs located in the FFRMS floodplain will be subject to the requirements of this rule. FEMA regulations prohibit the floodproofing of residential structures at or below the BFE, and so elevation is the only option. [ 310 ]

FEMA has calculated the cost of elevating PHC structures, depending on FFRMS approach and location and type of project. [ 311 ] FEMA then subtracted certain costs that it determined to be part of the baseline. Specifically, numerous States and localities have existing freeboard requirements that will result in elevation costs and benefits regardless of this rule, so costs and benefits for these areas have been reduced based on existing requirements.

For IA, if the FVA is the only expansion option, FEMA estimates that the final rule will affect 1,434 structures over the first 10 years. These costs would be incurred in the first 10 years of the 60-year period because that is when the investment in those projects takes place. Accordingly, FEMA estimates average annual costs of $57,343 in years 1-10. Since there is no cost share for IA, FEMA will fund the entire cost of elevating IA projects through grants.

For IA, if the 0.2PFA is the only expansion option, FEMA estimates that the final rule will affect 1,434 structures Start Printed Page 57020 over the first 10 years. Because these costs would be incurred in the first 10 years of the analysis, FEMA estimates the average annual cost in years 1-10 is $57,343. Since there is no cost share for IA, FEMA will fund the entire cost of elevating IA projects through grants.

For IA, if the CISA is the only expansion option, FEMA estimates that the final rule will affect 1,924 projects over the first 10 years. [ 312 ] Because these costs would be incurred in the first 10 years of the analysis, FEMA estimates that the average annual cost in years 1-10 is $168,174. Since there is no cost share for IA, FEMA will fund the entire cost of elevating IA projects through grants.

case study in distribution management

FEMA provides Hazard Mitigation Assistance (HMA) grants to States, territories, Federally-recognized Tribes, and local communities for the implementation of hazard mitigation measures to increase resiliency to disasters. Hazard mitigation is defined as any action taken to reduce or eliminate long-term risk to people and property from natural hazards. HMA projects related to flood mitigation mainly include elevation of structures, floodproofing of structures, and acquisition of properties that are at a high risk of damage from flooding. HMA also funds various other types of projects such as minor flood control, property acquisition, and generators, but FEMA is unable to estimate the potential costs associated with these projects because the manner in which each applicant meets the resiliency standards will be fact-specific and dependent upon the nature of the design and purpose of the project. HMA grant program includes Hazard Mitigation Grant Program (HMGP), HMGP Post Fire, Pre-Disaster Mitigation (PDM), Building Resilient Infrastructure and Communities (BRIC), and Flood Mitigation Assistance (FMA). Between 2010 and 2019, FEMA funded a total of 841 minor flood control and generators projects, for an average of 84 such projects per year. Additional minor mitigation measures will have to be taken for these projects, if located in the expanded FFRMS floodplain.

FEMA used data from HMA grant approvals for projects that include the elevation or floodproofing of structures from 2010-2019 and a multi-step process to estimate the range of costs for elevating or floodproofing these structures to the FFRMS.

For HMA, if the FVA is the only expansion option, FEMA estimated the final rule will affect 7,755 structures over the first 10 years. These costs would be incurred in the first 10 years of the 60-year period because that is when the investment in those projects would take place. Accordingly, FEMA estimates average annual costs in years 1-10 of $1.8 million. Using the 75 percent Federal cost share, FEMA estimates that it will cover 75 percent of the cost to elevate or floodproof HMA projects, for a total of $1.4 million in additional grants per year in years 1-10. Grant recipients will bear the remaining cost of $0.5 million per year.

For HMA, if the 0.2PFA is the only expansion option, FEMA estimated that the final rule will affect 7,712 structures in the first 10 years. Because these costs would be incurred in the first 10 years of the analysis, FEMA estimates the average annual cost in years 1-10 will be $1.8 million. Using the 75 percent Federal cost share, FEMA estimates that it will cover 75 percent of the cost to elevate or floodproof HMA projects, for a total of $1.4 million in additional grants per year in years 1-10. Grant recipients will bear the remaining cost of $0.5 million per year.

For HMA, if the CISA is the only expansion option, FEMA estimated that the final rule will affect 10,398 structures over the first 10 years. Because these costs would be incurred in the first 10 years, FEMA estimates that the average annual cost in years 1-10 is $4.3 million. Using the 75 percent Federal cost share, FEMA estimates that it will cover 75 percent of the cost to elevate or floodproof HMA projects, for a total of $3.2 million in additional grants per year. Grant recipients will bear the remaining cost of $1.1 million per year.

case study in distribution management

Executive Order 11988 , as amended, requires agencies to improve the resilience of communities and Federal assets against the impacts of flooding. The FFRMS is a flood resilience standard that provides a flexible framework to increase resilience against flooding and help preserve the natural values of floodplains and wetlands. Incorporating the FFRMS ensures FEMA expands flood risk management from the current base flood elevation to a higher vertical elevation and corresponding horizontal floodplain to address current and future flood risk and ensure that projects funded with taxpayer dollars last as long as intended.

The affected population is FEMA grant recipients whose projects are located in the current and the expanded FFRMS floodplain. Grant recipients will be required to comply with the new standard by elevating or floodproofing projects located in the expanded FFRMS floodplain. Specific grant programs include PA, IA, and HMA. PA grant recipients include public and certain non-profit entities, IA grant recipients include individuals, and HMA grant recipients include States, territories, Federally-recognized Tribes, and local communities.

The implementation of the FFRMS will have negligible impacts on community property values, tax bases and the distribution of real income. Additionally, FEMA expects the impacts on affordable housing for low to moderate income households and disadvantaged communities to be minimal since most actions subject to FFRMS requirements are non-residential. FEMA only funds residential construction in the IA and HMA programs; FEMA funds 153 residential IA projects and 268 HMA residential projects per year on average.

Under current FEMA regulations set out in 44 CFR part 9 , the base floodplain is defined as the 100-year floodplain (1 percent annual chance), or for critical actions, defined as the 500-year floodplain (0.2 percent annual chance). New construction or substantial improvement of structures located in the base floodplain must be elevated to or above the 1 percent annual chance flood level or Base Flood Elevation (BFE) or floodproofed below the BFE. Critical actions located within either the 1 percent annual chance floodplain or the 0.2 percent annual chance floodplain must be elevated or floodproofed up to the corresponding elevation for the 0.2 percent annual chance floodplain where it is mapped. [ 313 ]

FEMA has interim policies for PA and HMA that partially implement FFRMS and ASCE 24 standards in some areas, discussed in further detail below. Depending on the criticality of the action, these programs apply the supplemental FFRMS policy either to the base floodplain, or to both the 100-year and 500-year floodplains for critical actions. At the time the NPRM RIA was conducted, these partial implementation policies had been in place for less than 2 years. These policies were issued as temporary, partial implementation of the FFRMS until FEMA could implement it through this rulemaking. FEMA conducted this Regulatory Impact Analysis against a pre-statutory baseline to capture the economic impacts of the FFRMS and more accurately to measure the impacts of the rule against the world without the interim PA and HMA policies. Likewise, data on projects that adhered to the ASCE 24 standards is not available. Accordingly, FEMA used a pre-guidance baseline for this final rule to measure the impacts of the rule against the world without these policies and in accordance with the current requirements of 44 CFR part 9 .

The June 3, 2022 PA interim partial implementation policy  [ 314 ] provides elevation requirements for critical and non-critical actions involving structures located in a designated floodplain. The policy established requirements for elevating and floodproofing structures funded under the PA program. The interim policy set forth principles at its issuance that ensure that communities affected by future flooding are less vulnerable to losses of life and property, that investment of PA program funds for projects in the floodplain are spent to protect structures from flood risk, that structures are elevated or floodproofed to address current and future flood risk, and that the policy is implemented in a consistent and equitable manner.

This policy is being applied to structures (walled or roofed buildings, including mobile homes and gas or liquid storage tanks) in a mapped or established 1 percent annual chance floodplain or 0.2 percent annual chance floodplain  [ 315 ] that have a substantial damage  [ 316 ] determination, require substantial improvement, [ 317 ] or involve new construction. [ 318 ] This applies regardless of the cause of damage.

The August 26, 2021 HMA interim partial implementation policy  [ 319 ] sets forth the elevation requirements for the use of FEMA HMA for non-critical actions involving structure elevation, dry floodproofing, and mitigation reconstruction projects in the 1 percent annual chance floodplain. [ 320 321 ]

The updated HMA interim policy, [ 322 ] which supersedes the initial HMA interim policy, provides elevation requirements for critical and non-critical actions involving structures (as defined in 44 CFR 9.4 ) located in a designated floodplain. This updated interim policy covers the additional flexibility for non-critical actions to select the lower of the 0.2PFA or +2-ft above the BFE and setting elevation requirements for critical actions involving structures.

By partially implementing the FFRMS and requiring a higher vertical flood elevation for certain non-critical actions, FEMA is helping to ensure that communities affected by future flood disasters are less vulnerable to losses of life and property. This policy purpose is to improve the resilience of non-critical actions involving structure elevation, dry floodproofing, and mitigation reconstruction projects located in the SFHA against the impacts of flooding, which are anticipated to increase over time due to changing conditions and other threats; and to ensure such projects will last as long as intended.

This final rule will increase costs for certain IA, PA, and HMA program projects, as well as result in administrative costs for FEMA. FEMA expects minimal effects on grants processed by FEMA's GPD because these programs involve grants for preparedness activities and generally do not fund new construction or substantial improvement projects. Future FEMA facilities that may be located within the FFRMS floodplain will also be subject to the requirements of the final rule.

FEMA is unable to quantify the cost for increased resiliency standards for the 26,985 facility projects estimated to be affected in the first 10 years after this rule's publication. Additionally, FEMA is unable to quantify the cost for projects that may be diverted out of the floodplain, impacts to projects with existing basements, project delays, or forgone projects that may result from this rule.

Using the CISA as the primary approach, FEMA estimates that the final rule will affect 13,476 PA, IA, and HMA structures over the first 10 years. Those costs are incurred in the first 10 years of the 60-year period because that is when the investment in those projects takes place. [ 323 ] Discounted over 60 years, the low estimate  [ 324 ] cost is between $134.0 million and $110.4 million, using 3 and 7 percent respectively, with a 60-year annualized cost of $4.8 million and $7.9 million, using 3 and 7 percent respectively (see Table 9). Discounted over 60 years, the high estimate cost is between $169.8 million and $139.9 million, using 3 and 7 percent respectively, with a 60-year annualized cost of $6.1 million and $10.0 million, using 3 and 7 percent (see Table 10). Monetized costs include additional training for FEMA staff as well as the cost for the additional elevation or floodproofing. FEMA is unable to quantify the cost for increased resiliency standards for an estimated 26,985 affected facility projects over the 10-year period of analysis. Additionally, FEMA is unable to quantify the cost for projects that may be diverted out of the floodplain, impacts to projects with existing basements, project delays, or forgone projects that may result from this rule.

case study in distribution management

FEMA believes that the benefits of the final rule will justify the costs. FEMA has identified qualitative benefits, including reductions in damage to properties and contents from future floods, potential lives saved, public health and safety benefits, reduced recovery time from floods, and increased community resilience to flooding. FEMA has also analyzed quantified benefits of one additional foot of freeboard for PA projects using the CISA.

This final rule will result in savings in time and money from a reduced recovery period after a flood, as well as the increased safety of individuals. Generally, if properties are protected, there will be less damage, resulting in less recovery time. In addition, higher elevations will help to protect people, leading to increased safety. FEMA is unable to quantify these benefits but discusses them qualitatively in the Regulatory Impact Analysis.

In support of these benefits, FEMA is using the 2022 Benefits Analysis of Increased Freeboard for Public and Nonresidential Buildings in Riverine and Coastal Floodplains  [ 325 ] (2022 Start Printed Page 57024 report) that analyzed potential benefits (such as a reduction in damages, displacement, and loss of function, from increased flood protection requirements for public and nonresidential use buildings located in riverine and coastal SFHAs). This report's scope included six construction methods in coastal and riverine areas: Elementary School 1-Story, Hospital 2-3 Stories, Police Station 2-Stories, Office Building (Business) 1-Story, Office Building (Business) 3-Story, and Office Building (Government office) 1-Story. The riverine analysis considered locations along 14 rivers, while the coastal analysis considered 12 different locations along a hypothetical coastal transect; both only considered scenarios based on future conditions.

Future conditions for the riverine analysis included two climate change scenarios: the Representative Concentration Pathways (RCP) 4.5 scenario and the RCP 8.5 scenario that represent various efforts to curb future emissions. [ 326 ] The study used these two climate change scenarios to evaluate the amount of increase or decrease in riverine flood elevations over the next 50 years. For the coastal analysis, the study included the impact of various sea level rise conditions in areas with wave heights less than 1.5-ft (flood zones A) that are subject to coastal storm surge. The sea level rise conditions replicated a 2016 evaluation considering 8-, 20-, 39- and 59-inch sea level rises by 2100. FEMA has evaluated benefits associated with the rule using both RCP 4.5 and 8.5 scenarios, and three of the four sea level rise conditions: 8-, 39-, and 59-inches.

The 2022 report used FEMA's BCA Toolkit to calculate benefits for each year between 2023 and 2072 and then used these projections to calculate the present value benefits for each scenario. [ 327 ] The Toolkit used standard depth-damage functions (curves) to estimate damages from inundation and to calculate the benefits of mitigation that included avoided physical damage, avoided displacement (costs incurred while staying in a temporary location following an event), and avoided loss of function (the economic impact to a community due to a lack of critical services). The study also considered the potential avoided losses (or benefits) associated with either dry floodproofing or elevation of nonresidential and public use buildings. [ 328 ] It compared existing freeboard requirements against one additional foot of freeboard; that is, the study evaluated the benefits of elevating or floodproofing to the BFE+2 from a current assumed height of BFE+1 for non-critical actions and to BFE+3 from a current assumed height of BFE+2 for critical actions.

According to this report, for critical facilities in coastal SFHAs, such as police stations and hospitals, inclusion of one additional foot of freeboard will provide increased protection and continuity of operations and result in a quantifiable benefit. Elevating buildings would help to maintain community resiliency farther into the future. The riverine analysis indicated that despite the large variation in the flood data for the 14 sites, inclusion of one additional foot of freeboard would result in quantifiable average benefits. Critical actions and schools had the highest benefits across various riverine locations.

FEMA has used this study to estimate the benefits of an additional foot of freeboard for non-residential PA projects. FEMA was unable to use the benefits study to estimate the benefits for HMA and IA projects, since HMA data cannot be broken out by building types and IA data is limited to residential-related projects.

For FEMA's primary estimate, FEMA used 59 inches of SLR due to it being the closest SLR option to the vertical rise in FEMA's +5-ft assumption for CISA. CISA is the preferred approach for the FFRMS if the data are available. Since 5 feet is equivalent to 60 inches (5 × 12 inches per foot), 59-inch SLR is the closest SLR option that FEMA had available for this portion of the analysis. Using CISA for all PA Category E projects that are subject to the FFRMS, with the assumption that there would be a 59-inch SLR, FEMA estimates that the present value benefits of one additional foot of freeboard for the 50-year useful life of 1,154 PA Category E projects undertaken during the first 10 years after the rule's effective date will be between $56.1 million and $46.2 million (low estimate), discounted at 3 and 7 percent respectively, with a 60-year annualized benefit of $2.0 million and $3.3 million, at 3 and 7 percent (See Table 11) and between $66.1 million and $54.4 million (high estimate), discounted at 3 and 7 percent respectively, with a 60-year annualized benefit of $2.4 million and $3.9 million, at 3 and 7 percent. (See Table 12).

Tables 11 and 12 show the number of projects constructed each year (column 2), the present value of the benefits as of the year in which they were constructed (column 3), and the present value of the benefits as of the beginning of Year 1, using a 3 percent and 7 percent discount rate (columns 3 and 4, respectively). For example, the benefits shown in Year 1 represent the present value of the benefits for the 115 Category E projects constructed in Year 1 over their 50-year useful life ( i.e., in Years 1-50 of the analysis). The analysis does not account for any benefits for Year 1 projects after their 50-year useful life. The benefits shown in Year 10 represent the present value of the benefits for projects constructed in Year 10 over their 50-year useful life, ( i.e., in Years 11-60 of the analysis).

case study in distribution management

Because the cost to implement the FFRMS mitigation measures will be shared between FEMA and grant recipients according to the statutory cost share, there are also important distributional impacts. The majority of elevation and floodproofing costs will be borne by FEMA through additional grants (a transfer from FEMA to grant recipients). Grant recipients will bear the remaining cost. The below section shows the additional transfers from FEMA to grant recipients. Using CISA as the primary approach, FEMA estimates that this final rule will affect 13,476 structures in the first 10 years resulting in an increase in transfer payments ( i.e., grants) over the 60-year period of analysis. FEMA's low estimate of the increase in transfer payments is between $104.7 million and $86.2 million, with a 60-year transfer between $3.8 million and $6.1 million annually, at 3 and 7 percent respectively (see Table 13). FEMA's high estimate of the increase in transfer payments is between $134.2 million and $110.5 million, with a 60-year transfer between $4.8 million and $7.9 million annually, at 3 and 7 percent discount rates, respectively (see Table 14).

case study in distribution management

In Tables 15 and 16, FEMA presents the cost, transfer payments and benefit estimates by FFRMS approach. FEMA also presents estimates of costs, transfers, and benefits by grant program for CISA, FEMA's primary approach. The administrative cost estimate is not broken down by grant program because much of the cost will exist regardless of the program. Quantitative estimates of benefits are only available for projects under PA category E (Public Buildings). Due to the highly project-specific nature of facilities projects, and the numerous options for making them resilient, FEMA cannot estimate the costs of improving flood resiliency of facilities. [ 329 ] Tables 15 and 16 show that the total 60-year benefits for non-residential PA Category E projects constructed in the first 10 years is $54.4 million (7 percent, high). This benefit is for adding one foot of freeboard, assuming a 59-inch SLR. Although the cost for residential and non-residential PA Category E projects is $133.3 million (7 percent, high), this cost represents 5 feet of freeboard (FEMA's assumption for CISA). [ 330 ] FEMA does not have data to quantify the benefits of additional freeboard, and thus the quantified benefits represent only a portion of the Start Printed Page 57027 increased risk reduction that will be achieved through this rule. Ensuring projects are built to the height necessary to avoid additional loss scenarios will provide additional unquantified benefits of avoided damages to the structure, decreased cleanup time and disruption to the community, and increased public health and safety. Moreover, FEMA's use of CISA as its preferred approach will use the best available and actionable scientific data to tailor future flooding risk to each project, ensuring that projects are built only to the height necessary and thus maximizing net benefits. Accordingly, FEMA believes the benefits of the rule—quantified and unquantified—will justify its costs.

case study in distribution management

In Table 17, FEMA presents the OMB A-4 Accounting Statement. FEMA's analysis presents a range for costs and transfers of +5-ft of freeboard, and the benefits of +1-ft of freeboard. The range is due to uncertainty about whether new construction PA Category E projects will choose to floodproof or elevate. [ 333 ] Accordingly, FEMA's PA minimum estimate assumes all new construction projects choose to floodproof and the maximum assumes all new construction projects choose to elevate. FEMA's analysis for HMA and IA projects do not have a range. Table ES-14 shows the primary costs and transfers using the CISA approach only and the average of the ranges. FEMA has calculated the total benefits using the minimum and maximum estimates of PA benefits. FEMA has calculated the primary benefit estimates using the CISA approach with a 59-inch SLR and then taking the average of this range.

case study in distribution management

This section considers the effects that this rule will have on small entities as required by the Regulatory Flexibility Act (RFA, 5 U.S.C. 601 et seq., Pub. L. 96-354) as amended by the Small Business Regulatory Enforcement Fairness Act of 1996 (SBREFA). The RFA generally requires an agency to prepare a regulatory flexibility analysis of any rule subject to notice and comment rulemaking requirements under the Administrative Procedure Act or any other statute, unless the agency certifies that the rule will not have a “significant economic impact on a substantial number of small entities.” 5 U.S.C. 605(b) . Small entities include small businesses, small organizations, and small governmental jurisdictions.

FEMA prepared a Final Regulatory Flexibility Analysis (FRFA) for this rule. This analysis is detailed in this section and represents FEMA's assessment of the impacts of this rule on small entities. Section 1 outlines FEMA's assessment of small entities that will be affected by the regulations. Section 2 presents FEMA's analysis and summarizes the steps taken by FEMA to comply with the FRFA.

This rule will affect FEMA grant recipients that receive Federal funds under the PA, IA, and HMA programs for new construction, substantial improvement to structures, or to address substantial damage to structures and Start Printed Page 57031 facilities. Recipients of these grants are primarily States, Tribal governments, local governmental jurisdictions, and certain non-profit organizations. FEMA does not provide grants to for-profit businesses.

The following addresses the below requirements of a FRFA:

(1) a statement of the need for, and objectives of, the rule;

(2) a statement of the significant issues raised by the public comments in response to the initial regulatory flexibility analysis, a statement of the assessment of the agency of such issues, and a statement of any changes made in the proposed rule as a result of such comments;

(3) the response of the agency to any comments filed by the Chief Counsel for Advocacy of the Small Business Administration in response to the proposed rule, and a detailed statement of any change made to the proposed rule in the final rule as a result of the comments;

(4) a description of and an estimate of the number of small entities to which the rule will apply or an explanation of why no such estimate is available;

(5) a description of the projected reporting, recordkeeping, and other compliance requirements of the rule, including an estimate of the classes of small entities which will be subject to the requirement and the type of professional skills necessary for preparation of the report or record;

(6) a description of the steps the agency has taken to minimize the significant economic impact on small entities consistent with the stated objectives of applicable statutes, including a statement of the factual, policy, and legal reasons for selecting the alternative adopted in the final rule and why each one of the other significant alternatives to the rule considered by the agency which affect the impact on small entities was rejected.

2.1 Statement of the need for, and objectives of the rule.

FEMA is responsible for publishing information on floodplain areas and identifying special hazards. FEMA is also responsible for several grant programs that use Federal funds to assist in construction or reconstruction following a disaster, as well as grants for hazard mitigation and recovery. These grants can potentially be used for locations within a floodplain.

To meet the requirements of section 2(d) of Executive Order 11988 , directing agencies to issue or amend existing regulations and procedures to implement the Executive Order, FEMA promulgated regulations located at 44 CFR part 9 . FEMA is revising 44 CFR part 9 to reflect the changes to Executive Order 11988 made by Executive Order 13690 .

The objective of the rule is to revise the regulations for locating actions subject to the FFRMS in an expanded floodplain to reduce the risk of flooding to those projects. In addition, for actions that are determined to be “critical actions” as defined by the rule, the rule will impose more stringent elevation and resilience requirements. This is necessary to protect actions where even a slight chance of flooding is too great.

The rule will also require the use, where possible, of natural features and nature-based approaches when developing alternatives for consideration that will accomplish the same purpose as a considered action but have less potential to affect or be affected by the floodplain. Common examples of a nature-based approach will be replacing concrete drainage systems with natural drainage or covering an area with plants to absorb water and reduce runoff.

Several programs exist to assist with flood mitigation or recovery efforts after a flood. [ 335 ] IA and PA are disaster relief programs and primarily provide assistance after a disaster. HMA Grants are provided to increase resilience to hazards, and these have been shown to be very effective. By requiring recipients of FEMA funding to consider an expanded floodplain and build a higher level of flood resilience into their projects, the rule will reduce the likelihood of further damage and help prevent the loss of life in future flooding events. This will compel recipients of Federal funds to build to higher flood resilience standards and avoid repetitive loss situations.

2.2 Statement of the significant issues raised by the public comments in response to the Initial Regulatory Flexibility Analysis (IRFA), a statement of the assessment of the agency of such issues, and a statement of any changes made to the proposed rule as a result of such comments.

FEMA did not receive any comments on the IRFA for this rule, and therefore did not make any changes to this FRFA due to public comments.

2.3 The response of the agency to any comments filed by the Chief Counsel for Advocacy of the Small Business Administration (SBA) in response to the proposed rule, and a detailed statement of any change made to the final rule as a result of the comments.

FEMA did not receive any comments on the proposed rule from the Chief Counsel for Advocacy of the SBA.

2.4 Description of and an estimate of the number of small entities to which the rule will apply or an explanation of why no such estimate is available.

This rule will affect certain recipients of FEMA grants. These will primarily be PA and HMA grant recipients, including States, Tribal governments, local governments, and certain non-profit organizations. The PA grant recipients will include Categories C, D, E, F, and G projects; however, FEMA is only able to provide reasonable estimates of the number of entities and costs associated with Categories E (public buildings) because Category E is for structures whereas projects funded under the remaining PA categories are for facilities. Facilities will not be required to floodproof or elevate but will instead need to be made resilient to the appropriate flood levels, which is highly project-specific in nature, and the lack of data for such projects makes it exceedingly difficult to estimate costs. Therefore, FEMA has included only estimates of the number of affected facility projects but was unable to estimate a corresponding cost. IA and GPD are not discussed in this analysis. IA provides grants directly to individuals, who are not small entities as defined in 5 U.S.C. 601(6) . FEMA finds that this rule will likely have no effect on GPD grants because GPD projects are not typically substantial improvement or new construction.

FEMA estimates that the FFRMS requirements will expand the floodplain between 5 percent and 43 percent based on a study  [ 336 ] conducted in 800 square miles of coastal and riverine areas representative of places where the FFRMS will apply. FEMA developed floodplain expansion estimates for two distinct areas of the country: coastal and riverine. The first estimate was for coastal areas where FEMA anticipates implementing the CISA approach using currently-actionable sea level rise data. The second estimate was the area that represented the rest of the country, where 0.2PFA or FVA approaches will likely be applied. A total of 400 square miles of mapped flood zones were used as the baseline estimate for each of the two areas of the country. FEMA selected Start Printed Page 57032 a random sample of 40 coastal and riverine areas representative of the areas where the FFRMS will apply, with at least 10 square miles in each sampled area to ensure varying topography was captured. FEMA calculated the floodplain expansion in each sample at various levels of freeboard so that there was a total of 400 square miles of expansion information for each area.

FEMA selected the CISA as the primary approach for evaluating the impacts of this final rule, since it is the preferred approach and is designed to meet current and future estimates of flood risks unique to the location and thus provide the best overall resilience, cost effectiveness, and equity. FEMA does not have data detailed enough to estimate the average CISA level within the United States for this analysis. Instead, FEMA assumes CISA values will range from 1- to 10-ft of freeboard, based on the anticipated interagency tools that are currently in development. FEMA anticipates applying the CISA in those rounded amounts as “climate-informed freeboard.” The 10-foot ceiling will account for the highest levels of anticipated sea level rise along the Gulf and Atlantic coasts. Depending on location, under the CISA, some places may be required to elevate or floodproof to +1-ft above the 1 percent annual chance plain, while other places may be required to use +10-ft above the 1 percent annual chance plain. However, FEMA does not have available data or research to estimate what the required levels or how many structures will be subject to the requirements. For analysis purposes, FEMA has calculated the expanded floodplain using the mid-point (rounded down), +5-ft CISA level, which FEMA estimates will expand the floodplain by 26 percent.

FEMA considered using the minimum and maximum levels, but the minimum and maximum levels will not reflect the impacts of the rule accurately. FEMA did not use the minimum level for this approach because it will reflect a large number of structures that were not elevated or floodproofed to a high enough standard, when the rule may actually require them to be subject to a higher standard. If FEMA modeled all structures at the minimum standard, the costs would be underestimated compared to the actual impact of the rule. The benefits of protecting the structures from flood will also be underestimated because at the minimum level, many structures will be left vulnerable to devastating flood damage. Likewise, FEMA did not use the maximum level because it will reflect a large number of structures elevated or floodproofed to a standard too high compared to what the rule may require. If FEMA modeled all structures at the maximum standard, the costs would be overestimated compared to the actual impact. The benefits of protecting the structures from flood could potentially be overestimated as well, and not reflect the actual impact of the rule.

PA provides grants to States, Tribal governments, local governments and certain non-profit organizations for rebuilding, replacement, or repair of public and non-profit facilities damaged by disasters. Where such rebuilding, replacement, or repair involves new construction, substantial improvement, and repair of substantial damage of structures in the expanded FFRMS floodplain, PA recipients will incur additional costs to comply with elevation and floodproofing requirements. From 2013-2022, 916 individual PA Category E grant recipients received FEMA funding for substantial improvement floodproofing  [ 337 ] or new construction. Under the CISA, with the 26 percent expansion of the floodplain, an additional 238 PA Category E projects (916 × 26 percent), for a total of 1,154 (916 + 238) projects, will be located in the 1 percent annual chance floodplain or expanded FFRMS floodplain over the 10-year period. FEMA randomly sampled 92 projects. [ 338 ] Of the 92 projects, 47 projects, or 51 percent (47 ÷ 92), meet the definition of small entities under the Regulatory Flexibility Act.

HMA provides mitigation grants to States, Tribal governments, local governments, and certain non-profit organizations to, among other things, relocate property outside of the floodplain, or to elevate or floodproof structures above the flood level. FEMA will apply the FFRMS to all actions subject to the FFRMS, and all structure elevation, mitigation reconstruction, and dry floodproofing projects. As noted in the Regulatory Impact Analysis, FEMA funded an average of about 50 HMA elevation, mitigation reconstruction, and floodproofing structure projects per year from 2020-2022. [ 339 ] Unlike PA grants, most HMA grants are for projects located in the floodplain, so for this analysis, FEMA assumes that all HMA elevation, mitigation reconstruction, and dry floodproofing projects are in the floodplain. FEMA cannot estimate what projects might be considered actions subject to the FFRMS in addition to structure elevation, mitigation reconstruction, and dry floodproofing projects because HMA data does not distinguish whether projects are considered new construction, substantial improvement, or repairs to address substantial damage. However, structure elevation, mitigation reconstruction, and dry floodproofing are the primary HMA projects relating to flood mitigation. [ 340 ]

With the 26 percent expansion of the floodplain, an additional 13 HMA projects per year (50 × 26 percent), for a total of 63 (50 + 13) projects, will be located in the 1 percent annual chance floodplain or expanded FFRMS floodplain. Assuming 51 percent  [ 341 ] of HMA grant recipients are small entities, approximately 32 (63 projects × 51 percent) small entities receiving HMA grants will be affected per year.

Facilities will not be required to floodproof or elevate but will instead need to be made resilient to the appropriate FFRMS floodplain. Resilience measures for facilities are highly project-specific, and FEMA lacks data for such projects, making it exceedingly difficult to estimate costs. FEMA could not estimate the cost of this rule on small entities for facilities. However, FEMA conducted an analysis to estimate the number of small entities for affected facility projects based on historical data.

In an average year, FFRMS will impact about 1,036 PA Category C Start Printed Page 57033 facilities. Based on a random sample of 91 projects, [ 342 ] FEMA found that grant recipients for 71 of the projects, or 76.9 percent (70 ÷ 91), met the definition of small entities under the Regulatory Flexibility Act.

In an average year, FFRMS will impact about 120 PA Category D facilities. Based on a random sample of 55 projects, [ 343 ] FEMA found that grant recipients for 37 of the projects, or 67.3 percent (37 ÷ 55), met the definition of small entities under the Regulatory Flexibility Act.

In an average year, FFRMS will impact about 208 PA Category F facilities. Based on a random sample of 68 projects, [ 344 ] FEMA found that grant recipients for 55 of the projects, or 80.9 percent (55 ÷ 68), met the definition of small entities under the Regulatory Flexibility Act.

In an average year, FFRMS will impact about 314 PA Category G facilities. Based on a random sample of 76 projects, [ 345 ] FEMA found that grant recipients for 40 of the projects, or 52.6 percent (40 ÷ 76), met the definition of small entities under the Regulatory Flexibility Act.

In an average year, FFRMS will impact about 84 HMA grant recipients that received FEMA funding per year for minor flood controls and generator projects. Based on a random sample of 46 projects, [ 346 ] FEMA found that grant recipients for 19 of the projects, or 41.3 percent (19 ÷ 46), were small entities under the definition of small entities under the Regulatory Flexibility Act.

2.5 Description of the projected reporting, recordkeeping and other compliance requirements of the rule, including an estimate of the classes of small entities which will be subject to the requirement and the type of professional skills necessary for preparation of the report or record.

FEMA will not be changing the application process for its grant programs. The majority of the costs for the increased elevation or floodproofing requirements of structures in the FFRMS floodplain will be funded by FEMA through several grant programs. Small entities, like all entities, will be subject to additional costs not covered by these grants for the floodproofing, elevation of structures, and flood resilience measures required by the rule. For the purposes of this analysis, and based on historical data, FEMA presents the costs such that all projects will choose to elevate because of the additional level of safety that elevation provides over floodproofing and a historically higher number of HMA projects that involved elevation as opposed to floodproofing. [ 347 ] FEMA uses an NFIP report to estimate the cost of the elevation requirements. [ 348 ] The report provides estimates for the cost of elevating structures as a percentage of total construction cost.

The cost of elevating an existing structure is considerably higher than the cost of retrofitting the structure to be floodproofed. Floodproofing involves sealing off areas below the flood level so that water cannot enter or altering the use of these areas so that flood waters may pass through without causing serious damage. Non-residential structures, where elevation is not feasible, may be floodproofed rather than elevated. Additionally, floodproofing existing properties may be less costly than elevating an existing property. So, where a project may floodproof rather than elevate, costs may be lower for some projects than the costs presented here. However, for existing properties that choose to elevate rather than floodproof, costs may be higher for some projects than the costs presented here because the NFIP report cost estimates are for when freeboard is included in the design of a structure. New buildings will be evaluated for both dry floodproofing (preventing the intrusion of floodwaters into the building by using a system of waterproofing and shields) and elevation (constructing higher), while existing buildings will only be evaluated for dry floodproofing.

As established above, FEMA estimates this rule will impact 47 small entity PA Category E projects annually. Using CISA as the primary approach, FEMA estimates that the total cost for the elevation and floodproofing requirements of this rule for all PA Category E projects will be between $10,434,180 ($104,341,798 ÷ 10 years) and $14,497,988 ($144,979,878 ÷ 10 years) annually for 115 (1,154 PA Total FFRMS action Category E projects ÷ 10 years) projects annually. Therefore, each project will cost between $90,732 ($10,434,180 ÷ 115 projects) and $126,078 ($14,497,988 ÷ 115 projects). There is an average of 47 small entity PA projects per year. Small entity projects will have a total average expected cost between $4,264,404 ($90,732 × 47 small entities PA projects) and $5,925,666 ($126,078 × 47 small entities PA projects) per year. The historical average cost share for PA Category E projects is 85.0 percent covered by FEMA and 15.0 percent covered by the recipients, with the majority of recipients receiving a 75 percent or a 90 percent cost share, depending on the type of disaster declaration. FEMA estimates that, for PA Category E projects, each small entity will have an average expected cost ( i.e., their portion of the cost share) of between $13,610 ($90,732 × 15.0 percent) and $18,912 ($126,078 × 15.0 percent) per project.

As established above, FEMA estimates that this rule will affect approximately 32 small HMA grant recipients per year. Using CISA as the primary approach, FEMA estimates that the total 10-year cost for the elevation and floodproofing requirements of this rule for HMA projects will be $4,319,206 ($43,192,063 ÷ 10 years) annually for 1,040 (10,398 HMA Total FFRMS action projects ÷ 10 years) projects annually. There is an average of 32 small entities HMA projects per year. The average HMA project cost is $4,153 ($4,319,206 ÷ 1,040 HMA projects) per project. The cost-sharing arrangement for HMA is 75 percent Federal and 25 percent recipient, so HMA recipients will be required to fund 25 percent of the costs to comply with the requirements of the rule. Each small entity cost share will have an average expected cost of $1,038 ($4,153 × 25 percent).

Reporting and recordkeeping are not expected to change, with the exception of minor changes to FEMA's Mitigation Grant Program/e-Grants system. FEMA will continue to make the determination of whether a project will take place in an FFRMS floodplain.

2.6 Description of the steps the agency has taken to minimize the significant economic impact on small entities consistent with the stated Start Printed Page 57034 objectives of applicable statutes, including a statement of the factual, policy, and legal reasons for selecting the alternative adopted in the final rule and why each one of the other significant alternatives to the rule considered by the agency which affect the impact on small entities was rejected.

The standards in this rule represent FEMA's efforts to implement Executive Order 11988 , as amended, which establishes executive branch-wide policy in this area. Executive Order 13690 establishes the FFRMS. The policies established in these EOs do not consider exempting small entities from all or part of the standard; the purpose of the FFRMS is to ensure that agencies expand management from the current base flood level to a higher vertical elevation and corresponding horizontal floodplain to address current and future flood risk and help ensure that projects funded with taxpayer dollars last as long as intended. Accordingly, the FFRMS will apply to all affected FEMA projects, including small entities.

As discussed previously, most of the cost of the mitigation standards required by this rule will be paid by FEMA in the form of additional PA, IA, or HMA grants. Cost sharing is required for most FEMA grant programs. For PA and HMA, affected small entities will be required to pay the recipient portion of the cost share, which is 25 percent in most cases. There are, however, some exceptions and cost shares can be waived or set at a different level by Congress for PA. FEMA does not have the authority to adjust the cost share specifically for small entities.

Executive Order 11988 , as amended, allows several approaches to determine the FFRMS floodplain. Section F of this Final Rule, FEMA's Implementation of Executive Order 11988 , as amended, and FFRMS, describes the FFRMS approaches allowed by Executive Order 11988 , as amended, and FEMA's considerations when selecting between the FFRMS approaches. FEMA will, in its accompanying policy, use the CISA as the preferred approach. FEMA has chosen the CISA as its preferred approach because it is the only one that uses the best available climate science to help ensure projects are designed to meet current and future flood risks unique to the location and thus provides the best overall resilience, cost effectiveness, and equity. Accordingly, FEMA believes its preferred approach will minimize the risk that affected small entities incur more costs than necessary because of overprotection or incur preventable costs from future damage because of under protection.

The CISA establishes the required vertical elevation and corresponding horizontal floodplain, through the best-available, actionable hydrologic and hydraulic data and methods that integrate current and future changes in flooding based on climate science, in accordance with the Revised Guidelines. When such data is not available, this rule and supplementary policy direct the use of other approaches depending on the criticality of the action. The rule also requires the use of natural systems, ecosystem processes, and nature-based approaches where possible.

The FFRMS is a flexible framework to increase resilience against flooding and help preserve the natural and beneficial values of floodplains. Incorporating the FFRMS into FEMA regulations will ensure that FEMA expands flood risk management from the current base flood elevation to a higher vertical elevation and corresponding horizontal floodplain to address current and future flood risk and helps ensure that projects funded with taxpayer dollars last as long as intended for all applicants, including small entities. FEMA considered a more protective approach for critical actions but did not select this approach. FEMA could have chosen a more protective approach in which it would determine the elevations established under CISA, FVA, and the 0.2PFA for critical actions and only allow the applicant to use the highest of the three elevations. This approach would ensure that applicants were protecting these critical assets at the highest level. However, this approach may lead to overbuilding and not be the most cost-effective or equitable approach for applicants including small entities.

FEMA also considered a more protective approach for all actions but did not select this approach. FEMA could have required use of the highest standard for all actions, regardless of criticality. While this approach would ensure that applicants, including small entities, were building all actions to the most protective level, this approach would likely lead to overbuilding and not be the most cost-effective, equitable approach, particularly for non-critical actions.

Small entities affected by the rule, as with any entity affected by the rule, will have the option to relocate outside of the floodplain. This may be preferable in cases where property can be obtained and new facilities built for less cost than elevating or floodproofing to the FFRMS level in the floodplain, and the recipient has the ability to relocate.

The Unfunded Mandates Reform Act of 1995, 2 U.S.C. 658 , 1501-1504 , 1531-1536 , 1571 , pertains to any rulemaking which is likely to result in the promulgation of any rule that includes a Federal mandate that may result in the expenditure by State, local, and Tribal governments, in the aggregate, or by the private sector, of $100 million (adjusted annually for inflation) or more in any one year. If the rulemaking includes a Federal mandate, the Act requires an agency to prepare an assessment of the anticipated costs and benefits of the Federal mandate. The Act also pertains to any regulatory requirements that might significantly or uniquely affect small governments. Before establishing any such requirements, an agency must develop a plan allowing for input from the affected governments regarding the requirements.

FEMA has determined this rulemaking will not result in the expenditure by State, Territorial, local, and Tribal governments, in the aggregate, nor by the private sector, of $100,000,000 or more in any one year as a result of a Federal mandate, and it will not significantly or uniquely affect small governments. [ 349 ] Therefore, no actions are deemed necessary under the provisions of the Unfunded Mandates Reform Act of 1995.

As required by the Paperwork Reduction Act of 1995 (PRA), Public Law 104-13 , 109 Stat. 163, (May 22, 1995) ( 44 U.S.C. 3501 et seq. ), FEMA may not conduct or sponsor, and a person is not required to respond to, a collection of information unless the collection of information displays a valid OMB control number. See 44 U.S.C. 3506 , 3507 . This final rule calls for no new collections of information under the PRA. The final rule includes information currently collected by FEMA and approved in OMB information collections 1660-0072 (FEMA Mitigation Grant Programs) and 1660-0076 (Hazard Mitigation Grant Start Printed Page 57035 Program (HMGP) Application and Reporting). With respect to these collections, this final rule will not impose any additional burden and will not require a change to the forms, the substance of the forms, or the number of recipients who would submit the forms to FEMA.

Under the Privacy Act of 1974, 5 U.S.C. 552a , an agency must determine whether implementation of a proposed regulation would result in a system of records. A “record” is any item, collection, or grouping of information about an individual that is maintained by an agency, including, but not limited to, his/her education, financial transactions, medical history, and criminal or employment history and that contains his/her name, or the identifying number, symbol, or other identifying particular assigned to the individual, such as a finger or voice print or a photograph. See 5 U.S.C. 552a(a)(4) . A “system of records” is a group of records under the control of an agency from which information is retrieved by the name of the individual or by some identifying number, symbol, or other identifying particular assigned to the individual. See 5 U.S.C. 552a(a)(5) . An agency cannot disclose any record, which is contained in a system of records, except by following specific procedures.

In accordance with DHS policy, FEMA completed a Privacy Threshold Analysis for this rule. This rule is covered by the following PIAs: DHS/FEMA/PIA-006 FEMA National Emergency Management Electronic Grants System, DHS/FEMA/PIA-025-Hazard Mitigation Grant Program (HMGP) System, DHS/FEMA/PIA-026 Operational Data Store and Enterprise Data Warehouse PIA, and DHS/FEMA/PIA-031 Authentication and Provisioning Services (APS). No updates to these PIAs are necessary. Further, this rule is covered under the following System of Records Notices (SORNs): DHS/FEMA-009 Hazard Mitigation, Disaster Public Assistance, and Disaster Loan Programs, 79 FR 16015 , Mar. 24, 2014; DHS/ALL-004 General Information Technology Access Account Records System (GITAARS), 77 FR 70792 , Nov. 27, 2012; and DHS/FEMA-008 Disaster Recovery Assistance Files. This final rule will not create a new system of records, and no updates to these SORNs are necessary.

Executive Order 13175 , “Consultation and Coordination With Indian Tribal Governments,” 65 FR 67249 , Nov. 9, 2000, applies to agency regulations that have Tribal implications, that is, regulations that have substantial direct effects on one or more Indian Tribes, on the relationship between the Federal Government and Indian Tribes, or on the distribution of power and responsibilities between the Federal Government and Indian Tribes. Under this Executive Order, to the extent practicable and permitted by law, no agency shall promulgate any regulation that has Tribal implications, that imposes substantial direct compliance costs on Indian Tribal governments, and that is not required by statute, unless funds necessary to pay the direct costs incurred by the Indian Tribal government or the Tribe in complying with the regulations are provided by the Federal Government, or the agency consults with Tribal officials.

FEMA reviewed this final rule under Executive Order 13175 and determined that this rule would not have a substantial direct effect on one or more Indian Tribes, on the relationship between the Federal Government and Indian Tribes, or on the distribution of power and responsibilities between the Federal Government and Indian Tribes.

Part 9 applies to FEMA disaster and non-disaster assistance programs, including IA, PA, and HMA programs, and grants processed by FEMA's GPD. Pursuant to section 8 of Executive Order 11988 , part 9 does not apply to assistance provided for emergency work essential to save lives and protect property and public health and safety, performed pursuant to sections 403 and 502 of the Stafford Act, as amended ( 42 U.S.C. 5170b and 5192 ).

Indian Tribes have the same opportunity to participate in FEMA's grant programs as other eligible participants, and participation is voluntary. The requirements of this rule do not affect Tribes differently than other grant recipients. FEMA's edits in this final rule specifically provide for Indian Tribal government information as a resource when making the floodplain determination under part 9, consistent with comments received.

Executive Order 13132 , “Federalism,” 64 FR 43255 , August 10, 1999, sets forth principles and criteria that agencies must adhere to in formulating and implementing policies that have federalism implications, that is, regulations that have “substantial direct effects on the States, on the relationship between the national government and the States, or on the distribution of power and responsibilities among the various levels of government.” Federal agencies must closely examine the statutory authority supporting any action that would limit the policymaking discretion of the States, and to the extent practicable, must consult with State and local officials before implementing any such action.

FEMA has determined this rulemaking does not have a substantial direct effect on the States, on the relationship between the national government and the States, or on the distribution of power and responsibilities among the various levels of government, and therefore does not have federalism implications as defined by the Executive Order.

Part 9 applies to FEMA disaster and non-disaster assistance programs, including IA, PA, and HMA programs, and grants processed by FEMA's GPD. Pursuant to section 8 of Executive Order 11988 , part 9 does not apply to assistance provided for emergency work essential to save lives and protect property and public health and safety, performed pursuant to section 403 and 502 of the Stafford Act, as amended ( 42 U.S.C. 5170b and 5192 ). The final rule does not significantly affect the rights, roles, and responsibilities of States, and involves no preemption of State law, nor does it limit State policymaking discretion.

Section 102 of NEPA ( 42 U.S.C. 4321 et seq. ) requires Federal agencies to evaluate the effects of a proposed major Federal action to determine if it will significantly affect the human environment, consider alternatives to the proposed action, provide public notice and opportunity for comment, and properly document its analysis. See 40 CFR parts 1501 , 1506.6 . DHS and its component agencies analyze proposed actions to determine whether NEPA applies and, if so, what level of analysis and documentation is required. 40 CFR 1501.3 . DHS Directive 023-01, Rev. 01 and DHS Instruction Manual 023-01-001-01, Rev. 01 (Instruction Manual) establish the policies and procedures DHS and its component agencies use to comply with NEPA and the Council on Environmental Quality (CEQ) regulations for implementing the procedural requirements of NEPA codified in 40 CFR parts 1500 through 1508 . The CEQ regulations allow Start Printed Page 57036 Federal agencies to establish in their NEPA implementing procedures categories of actions (“categorical exclusions”) that normally do not have a significant effect on the human environment. Categorically excluded actions do not require preparation of an environmental assessment or environmental impact statement. 40 CFR 1501.4 , 1507.3(e)(2)(ii) , 1508.1(d) . The Instruction Manual, Appendix A, lists the DHS categorical exclusions. Under DHS NEPA implementing procedures, for an action to be categorically excluded, it must satisfy each of the following conditions: (1) the entire action clearly fits within one or more of the categorical exclusions; (2) the action is not a piece of a larger action; and (3) no extraordinary circumstances exist that create the potential for a significant environmental effect.

The final rule updates the Floodplain Management and Protection of Wetland requirements to adopt the approaches outlined in Executive Order 11988 , as amended. This involves establishing the floodplain, using the vertical elevation and corresponding horizontal extent, in the 8-step decision-making process FEMA follows in applying Executive Order 11988 , as amended to its actions. FEMA's final rule amends regulations codified at 44 CFR part 9 to revise the definition of the floodplain based on the approaches in Executive Order 11988 , as amended, consisting of the Climate-Informed Science Approach (CISA), the freeboard value approach (FVA), the 0.2-percent-annual-chance flood approach (0.2PFA), and any other method identified in updates. The final rule allows FEMA to select and prioritize among these approaches. The rule revises the 8-step decision-making process to incorporate consideration of the approaches in determining if the project is in the floodplain. The rule also adds a requirement, where possible, to use natural systems, ecosystem processes, and nature-based approaches in the development of alternatives for Federal actions in a floodplain. The result of redefining the floodplain and applying the approaches outlined in Executive Order 11988 , as amended, may be that structures and facilities determined to be in the floodplain (“the FFRMS floodplain”) would be designed to be more resilient, and more structures and facilities—due to the corresponding horizontal expansion of the floodplain—might be subject to an elevation requirement and/or other mitigation measures. Further, with the expanded horizontal floodplain, and application of the 8-step decision-making process, which allows for Federal actions in the floodplain only if there is no practicable alternative, it is possible some structures or facilities that otherwise would be constructed in a high-risk flood area, would be constructed elsewhere. This would result in better protection of people and their property, the floodplain and environment. When placing the action in the floodplain cannot be avoided, implementing mitigation measures to actions in the FFRMS floodplain will not only promote public safety and lessen flood risk, but may also reduce the impact of the action on the floodplain, and thereby contribute to preserving the natural and beneficial values of the floodplain per the mandate in E.O. 11988 . Similarly, the requirement to use natural systems, ecosystem processes, and nature-based approaches, where possible, in alternatives to the proposed action, would contribute to restoring and preserving the natural and beneficial values of the floodplain.

FEMA has determined NEPA applies to the final rule because it fits the definition of a “major federal action.” CEQ's NEPA regulations define “major federal action” to include “new or revised agency rules,” regulations and policies. 40 CFR 1508.1(q)(2) .

FEMA analyzed the final rule and finds it meets the three DHS criteria for a categorical exclusion. FEMA has determined consistent with the first criterion, the rule clearly fits within the categorical exclusion found at A3 in the DHS Instruction Manual, Appendix A. Categorical exclusion A3 states “promulgation of rules, issuance of rulings or interpretations, and the development and publications of policies” may be categorically excluded if such actions “interpret or amend an existing regulation without changing its environmental effect.” Instruction Manual, Appendix A, A3(d). The final rule may result in requiring a structure or facility to have either higher elevation or floodproofing, or more resilient design. The rule provides for a higher resilience standard than the existing rule. It is possible the expanded horizontal floodplain may discourage placing a “Federal action” in the floodplain, as under the 8-step decision-making process, an action may be located in the floodplain only if there is no practicable alternative. In the event there is a practicable alternative, and new construction is consequently located outside the floodplain, the effect of the final rule would be to benefit the environment by contributing to restoring and preserving the values of the floodplain, as well as enhancing public safety. FEMA's environmental and historic preservation review would ensure that the agency takes into account other potential environmental impacts of locating outside the floodplain.

If the Federal action must be located in the FFRMS floodplain, that is, there is no practicable alternative, it will be subject to one of the three approaches or a combination of them. FEMA's preferred approach is CISA. If the CISA is used, it could result in an estimated average of 5 feet of additional elevation for a structure (or floodproofing to that level). FEMA prefers the CISA because it uses the best actionable and available climate-informed science to determine the floodplain is the most effective way to make the action resilient. If the CISA data is not available and/or actionable, the final rule provides alternatives for determining the floodplain for critical actions and non-critical actions: for non-critical actions, the lesser of the freeboard value approach (2 or 3 feet above base flood elevation) or the 0.2 percent annual flood; and for critical actions, the higher of the freeboard value approach or 0.2 percent annual flood. Given the CISA or the combination of approaches may be used, the potential for the change in elevation (or floodproofing) levels varies. Further, if communities have stricter standards, which they are required to apply, the communities will still apply that standard, and thus, application of the FFRMS would not require a change in elevation. If the “Federal action” is substantial improvement or addresses substantial damage to a structure or facility, it would involve action in a pre-built environment, with the only change being the structure or facility might be elevated or floodproofed to the appropriate higher level. If design rather than elevation, or in addition to elevation, is used to comply with the FFRMS resilience standard, it is not anticipated it will significantly impact the environment. As part of implementing the FFRMS resilience standard, nature-based solutions are required in alternatives to the proposed action, where possible. When applied, they will benefit the environment by contributing to restoring and preserving the natural and beneficial values of the floodplain. None of the changes required by any of the combined FFRMS approaches are anticipated to change the environmental effects of application of the 8-step process. Categorical exclusion A3 applies to this regulatory action, however any of the Federally funded actions to which the FFRMS applies (new construction, substantial Start Printed Page 57037 improvement and repair of substantial damage) will undergo separate NEPA analysis.

In addition to and apart from application of the decision process in this final rule, all Federal actions, new construction, substantial improvement, and actions addressing substantial damage, are subject to NEPA review and must comply with NEPA requirements. Each Federal action subject to the FFRMS will be evaluated on an individual basis under NEPA and related environmental laws, regulations, and executive orders. The Federal action will not be approved unless it meets all applicable environmental and historic preservation requirements. Further, the Federal actions subject to the proposed rule must comply with all applicable floodplain requirements. See 44 CFR 9.11(d)(6) (referring to requirement to be consistent with the criteria of the NFIP at 44 CFR part 59 et seq. or any more restrictive Federal, State, or local floodplain management standard).

FEMA therefore concludes the final rule clearly fits within categorical exclusion A3. FEMA also finds the final rule meets the second and third DHS criteria for applying a categorical exclusion. The final rule is not a piece of a larger action, as it will be implemented independently of other FEMA actions and is a separate action unto itself. Furthermore, FEMA finds adopting the floodplain management and protection approaches outlined in Executive Order 11988 , as amended, presents no extraordinary circumstances that increase the potential for significant environmental effects to the environment. Accordingly, the final rule is categorically excluded, and no further NEPA analysis or documentation is required.

Under Executive Order 12898 , “Federal Actions To Address Environmental Justice in Minority Populations and Low-Income Populations,” ( 59 FR 7629 , Feb. 16, 1994); and Executive Order 14096 , “Revitalizing Our Nation's Commitment to Environmental Justice for All” ( 88 FR 25251 , Apr. 26, 2023), FEMA incorporates environmental justice into its policies and programs. Executive Order 14096 charges agencies to make achieving environmental justice part of their missions, consistent with statutory authority, by identifying, analyzing, and addressing disproportionate and adverse human health and environmental effects and hazards of Federal activities, including those related to climate change and cumulative impacts of environmental and other burdens on communities with environmental justice concerns.

This final rule will not have a disproportionate and adverse human health or environmental effect on communities with environmental justice concerns. FEMA addressed specific comments related to environmental justice above.

This rule will not affect a taking of private property or otherwise have taking implications under Executive Order 12630 , “Governmental Actions and Interference With Constitutionally Protected Property Rights” ( 53 FR 8859 , Mar. 18, 1988).

This final rule meets applicable standards in sections 3(a) and 3(b)(2) of Executive Order 12988 , “Civil Justice Reform” ( 61 FR 4729 , Feb. 7, 1996), to minimize litigation, eliminate ambiguity, and reduce burden.

This final rule will not create environmental health risks or safety risks for children under Executive Order 13045 , “Protection of Children From Environmental Health Risks and Safety Risks” ( 62 FR 19885 , Apr. 23, 1997).

“Voluntary consensus standards” are standards developed or adopted by voluntary consensus standards bodies, both domestic and international. These standards include provisions requiring owners of relevant intellectual property to agree to make that intellectual property available on a non-discriminatory, royalty-free, or reasonable royalty basis to all interested parties. OMB Circular A-119 directs agencies to use voluntary consensus standards in their regulatory actions in lieu of government-unique standards, except where inconsistent with law or otherwise impractical. The policies in the Circular are intended to reduce to a minimum the reliance by agencies on government-unique standards.

Consistent with then-President Obama's Climate Action Plan, [ 350 ] the National Security Council staff coordinated an interagency effort to create a new flood risk reduction standard for Federally funded projects. The views of Governors, mayors, and other stakeholders were solicited and considered as efforts were made to establish a new flood risk reduction standard for Federally funded projects. The FFRMS is the result of these efforts.

Under the Congressional Review Act (CRA), 5 U.S.C. 801-808 , before a rule can take effect, the Federal agency promulgating the rule must submit to Congress and to the Government Accountability Office (GAO) a copy of the rule; a concise general statement relating to the rule, including whether it is a major rule; the proposed effective date of the rule; a copy of any cost-benefit analysis; descriptions of certain actions under the Regulatory Flexibility Act and the Unfunded Mandates Reform Act; and any other relevant information or requirements under any other Act and any executive orders. FEMA has submitted this rule to the Congress and to GAO pursuant to the CRA. OMB has determined that this rule is not a “major rule” within the meaning of the CRA.

  • Floodplains; Reporting and recordkeeping requirements

For the reasons discussed in the preamble, the Federal Emergency Management Agency (FEMA) is amending 44 CFR part 9 as follows:

1. The authority citation for part 9 is revised to read as follows:

Authority: 6 U.S.C. 101 et seq.; 42 U.S.C. 4001 et seq.; 42 U.S.C. 4321 et seq.; E.O. 11988 of May 24, 1977, 42 FR 26951 , 3 CFR , 1977 Comp., p. 117; E.O. 11990 of May 24, 1977, 42 FR 26961 , 3 CFR , 1977 Comp. p. 121; E.O. 13690 , 80 FR 6425 ; E.O. 14030 , 86 FR 27967 .

2. Revise § 9.1 to read as follows:

This part sets forth the policy, procedure, and responsibilities to implement and enforce relevant sections of the National Flood Insurance Act of 1968, as amended, and the Flood Disaster Protection Act of 1973, as Start Printed Page 57038 amended, 42 U.S.C. 4001 et seq., the National Environmental Policy Act of 1969, 42 U.S.C. 4321 et seq., as amended, and other relevant statutory authorities in conjunction with Executive Order 11988 , Floodplain Management, as amended, and Executive Order 11990 , Protection of Wetlands.

3. Amend § 9.2 by revising paragraph (b) and adding paragraphs (c) and (d) to read as follows:

(b) The Agency will provide leadership in floodplain management and the protection of wetlands, informed by the best available and actionable science, to bolster the resilience of communities and Federal assets against the impacts of flooding, which are anticipated to increase over time due to the effects of changing conditions which adversely affect the environment, economic prosperity, public health and safety, and national security.

(c) The Agency shall integrate the goals of the Orders to the greatest possible degree into its procedures for implementing the National Environmental Policy Act ( 42 U.S.C. 4321 et seq. ).

(d) The Agency shall:

(1) Minimize the impact of floods on human health, safety, and welfare;

(2) Avoid long- and short-term adverse impacts associated with the occupancy and modification of floodplains and the destruction and modification of wetlands;

(3) Avoid direct and indirect support of floodplain development and new construction in wetlands wherever there is a practicable alternative;

(4) Reduce the risk of flood loss;

(5) Promote the use of nonstructural flood protection methods to reduce the risk of flood loss;

(6) Minimize the destruction, loss, or degradation of wetlands;

(7) Restore and preserve the natural and beneficial values served by floodplains;

(8) Preserve and enhance the natural values of wetlands;

(9) Involve the public throughout the floodplain management and wetlands protection decision-making process;

(10) Adhere to the objectives of the Unified National Program for Floodplain Management; and

(11) Improve and coordinate the Agency's plans, programs, functions, and resources so that the Nation may attain the widest range of beneficial uses of the environment without degradation or risk to health and safety.

4. Revise § 9.3 to read as follows:

Any provision of this part held to be invalid or unenforceable as applied to any action should be construed so as to continue to give the maximum effect to the provision permitted by law, unless such holding is that the provision of this part is invalid and unenforceable in all circumstances, in which event the provision should be severable from the remainder of this subpart and shall not affect the remainder thereof.

5. Amend § 9.4 by:

a. Adding in alphanumeric order definitions for “0.2 percent annual chance flood elevation”, “0.2 percent annual chance floodplain”, “1 percent annual chance flood elevation”, and “1 percent annual chance floodplain”;

b. Revising the definitions of “Action” and “Actions Affecting or Affected by Floodplains or Wetlands”;

c. Adding in alphabetical order a definition for “Action subject to the Federal Flood Risk Management Standard”;

d. Removing the definitions of “Base Flood” and “Base Floodplain”;

e. Adding in alphabetical order a definition for “Base flood elevation”;

f. Revising the definitions of “Coastal High Hazard Area”, “Critical Action”, and “Emergency Actions”;

g. Adding in alphabetical order definitions for “Federal Flood Risk Management Standard (FFRMS)”, “Federal Flood Risk Management Standard (FFRMS) floodplain”, “Federally funded project”, and “FEMA Resilience”;

h. Removing the definitions of “FIA” and “Five Hundred Year Floodplain”;

i. Revising the definition of “Flood or flooding”;

j. Removing the definitions of “Flood Fringe”, “Flood Hazard Boundary Map (FHBM)”, “Flood Insurance Rate Map (FIRM)”, and “Flood Insurance Study (FIS)”;

k. Revising the definitions of “Floodplain”, “Functionally Dependent Use”, and “Mitigation”;

l. Removing the definition of “Mitigation Directorate”;

m. Adding in alphabetical order definitions for “National security”, “Nature-based approaches”, “Natural and beneficial values of floodplains and wetlands”, and “Natural features”;

n. Removing the definition of “Natural Values of Floodplains and Wetlands”;

o. Revising the definition of “New Construction”;

p. Removing the definition of “New Construction in Wetlands”;

q. Revising the definitions of “Orders”, “Practicable”, “Regulatory Floodway”, “Restore”, “Structures”, and “Substantial Improvement”;

r. Adding in alphabetical order a definition for “Support of floodplain and wetland development”;

s. Removing the definition of “Support”; and

t. Revising the definition of “Wetlands”.

The additions and revisions read as follows:

0.2 percent annual chance flood elevation means the elevation to which floodwater is anticipated to rise during the 0.2 percent annual chance flood (also known as the 500-year flood).

0.2 Percent annual chance floodplain means the area subject to flooding by the 0.2 percent annual chance flood (also known as the 500-year floodplain).

1 percent annual chance flood elevation —see the definition of base flood elevation in this section.

1 percent annual chance floodplain means the area subject to flooding by the 1 percent annual chance flood (also known as the 100-year floodplain or base floodplain).

Action means

(1) Acquiring, managing, and disposing of Federal lands and facilities;

(2) Providing federally undertaken, financed, or assisted construction and improvements; and

(3) Conducting Federal activities and programs affecting land use, including, but not limited to, water and related land resources, planning, regulating, and licensing activities.

Actions affecting or affected by floodplains or wetlands means actions which have the potential to result in the long- or short-term impacts associated with:

(1) The occupancy or modification of floodplains, and the direct or indirect support of floodplain development, or

(2) The destruction and modification of wetlands and the direct or indirect support of new construction in wetlands.

Action subject to the Federal Flood Risk Management Standard (FFRMS) means any action where FEMA funds are used for new construction, substantial improvement, or to address substantial damage to a structure or facility.

Base flood elevation means the elevation to which floodwater is anticipated to rise during the 1 percent annual chance flood (also known as the base flood or 100-year flood). The terms “base flood elevation,” “1 percent annual change flood elevation,” and “100-year flood elevation” are Start Printed Page 57039 synonymous and are used interchangeably.

Coastal high hazard area means an area of flood hazard extending from offshore to the inland limit of a primary frontal dune along an open coast and any other area subject to high velocity wave action from storms or seismic sources.

Critical action means any action for which even a slight chance of flooding is too great. Critical actions include, but are not limited to, those which create or extend the useful life of structures or facilities:

(1) Such as those which produce, use or store highly volatile, flammable, explosive, toxic or water-reactive materials;

(2) Such as hospitals and nursing homes, and housing for the elderly, which are likely to contain occupants who may not be sufficiently mobile to avoid the loss of life or injury during flood and storm events;

(3) Such as emergency operation centers, or data storage centers which contain records or services that may become lost or inoperative during flood and storm events; and

(4) Such as generating plants, and other principal points of utility lines.

Emergency actions means emergency work essential to save lives and protect property and public health and safety performed under sections 403 and 502 of the Robert T. Stafford Disaster Relief and Emergency Assistance Act of 1988 ( 42 U.S.C. 5170b and 5192 ).

Federal Flood Risk Management Standard (FFRMS) means the Federal flood risk management standard to be incorporated into existing processes used to implement Executive Order 11988 , as amended.

Federal Flood Risk Management Standard (FFRMS) floodplain means the floodplain established using one of the approaches described in § 9.7(c) of this part.

Federally funded project —see the definition of Action subject to the Federal Flood Risk Management Standard in this section.

FEMA Resilience means the organization within FEMA that includes the Federal Insurance and Mitigation Administration, the Grants Program Directorate, and the National Preparedness Directorate.

Flood or flooding means the general and temporary condition of partial or complete inundation of normally dry land areas from the overflow of inland and/or tidal waters, and/or the unusual and rapid accumulation of runoff of surface waters from any source. 0.2 percent annual chance flood means the flood which has a 0.2 percent chance of being equaled or exceeded in any given year (also known as the 500-year flood). 1 percent annual chance flood means the flood which has a 1 percent chance of being equaled or exceeded in any given year (also known as the 100-year flood or base flood). The terms “base flood,” “1 percent annual chance flood,” and “100-year flood” are synonymous and are used interchangeably.

Floodplain means any land area that is subject to flooding. The term “floodplain,” by itself, refers to geographic features with undefined boundaries. For the purposes of this part, the FFRMS floodplain shall be established using one of the approaches described in § 9.7(c). See the definitions of 0.2 percent annual chance floodplain, 1 percent annual chance floodplain, and Federal Flood Risk Management Standard floodplain in this section.

Functionally dependent use means a use which cannot perform its intended purpose unless it is located or carried out in close proximity to water.

Mitigation means steps necessary to minimize the potentially adverse effects of the proposed action, and to restore and preserve the natural and beneficial floodplain values and to preserve and enhance natural values of wetlands.

National security means:

(1) A condition that is provided by either:

(i) A military or defense advantage over any foreign nation or group of nations;

(ii) A favorable foreign relations position; or

(iii) A defense posture capable of successfully resisting hostile or destructive action from within or without, overt or covert.

(2) National security encompasses both national defense and foreign relations of the United States.

Nature-based approaches means the features (sometimes referred to as “green infrastructure”) designed to mimic natural processes and provide specific services such as reducing flood risk and/or improving water quality. Nature-based approaches are created by human design (in concert with and to accommodate natural processes) and generally, but not always, must be maintained in order to reliably provide the intended level of service.

Natural and beneficial values of floodplains and wetlands means features or resources that provide environmental and societal benefits. Water and biological resources are often referred to as “natural functions of floodplains and wetlands.” These values include, but are not limited to:

(1) Water resource values (storing and conveying floodwaters, maintaining water quality, and groundwater recharge);

(2) Living resource values (providing habitats and enhancing biodiversity for fish, wildlife, and plant resources);

(3) Cultural resource values (providing open space, natural beauty, recreation, scientific study, historic and archaeological resources, and education; and

(4) Cultivated resource values (creating rich soils for agriculture, aquaculture, and forestry).

Natural features means characteristics of a particular environment ( e.g., barrier islands, sand dunes, wetlands) that are created by physical, geological, biological, and chemical processes and exist in dynamic equilibrium. Natural features are self-sustaining parts of the landscape that require little or no maintenance to continue providing their ecosystem services (functions).

New construction means the construction of a new structure or facility or the replacement of a structure or facility which has been totally destroyed. New construction includes permanent installation of temporary housing units. New construction in wetlands includes draining, dredging, channelizing, filling, diking, impounding, and related activities.

Orders means Executive Order 11988 , Floodplain Management, as amended, and Executive Order 11990 , Protection of Wetlands.

Practicable means capable of being done within existing constraints. The test of what is practicable depends on the situation and includes consideration of all pertinent factors, such as natural environment, social concerns, economic aspects, legal constraints, and agency authorities.

Regulatory floodway means the area regulated by Federal, State, or local requirements to provide for the discharge of the base flood so the cumulative rise in the water surface is no more than a designated amount above the base flood elevation.

Restore means to reestablish a setting or environment in which the natural functions of the floodplain can operate. Start Printed Page 57040

Structure means a walled and roofed building, including a temporary housing unit (manufactured housing) or a gas or liquid storage tank.

Substantial improvement means any repair, reconstruction or other improvement of a structure or facility, which has been damaged in excess of, or the cost of which equals or exceeds, 50 percent of the pre-disaster market value of the structure or replacement cost of the facility (including all “public facilities” as defined in the Robert T. Stafford Disaster Relief and Emergency Assistance Act of 1988) before the repair or improvement is started, or if the structure or facility has been damaged and is proposed to be restored. Substantial improvement includes work to address substantial damage to a structure or facility. If a facility is an essential link in a larger system, the percentage of damage will be based on the cost of repairing the damaged facility relative to the replacement cost of the portion of the system which is operationally dependent on the facility. The term “substantial improvement” does not include any alteration of a structure or facility listed on the National Register of Historic Places or a State Inventory of Historic Places.

Support of floodplain and wetland development means to, directly or indirectly, encourage, allow, serve, or otherwise facilitate development in floodplains or wetlands. Development means any man-made change to improved or unimproved real estate, including but not limited to new construction, mining, dredging, filling, grading, paving, excavation or drilling operations, or storage of equipment or materials. Direct support results from actions within floodplains or wetlands, and indirect support results from actions outside of floodplains or wetlands.

Wetlands means those areas which are inundated or saturated by surface or ground water with a frequency sufficient to support, or that under normal hydrologic conditions does or would support, a prevalence of vegetation or aquatic life typically adapted for life in saturated or seasonally saturated soil conditions, including wetlands areas separated from their natural supply of water as a result of construction activities such as structural flood protection methods or solid-fill road beds, and activities such as mineral extraction and navigation improvements. Examples of wetlands include, but are not limited to, swamps, fresh and salt water marshes, estuaries, bogs, beaches, wet meadows, sloughs, potholes, mud flats, river overflows, and other similar areas. This definition is intended to be consistent with the definition utilized by the U.S. Fish and Wildlife Service.

6. Amend § 9.5 by revising paragraph (a)(3), the first sentence of paragraph (b)(1), and paragraphs (c) through (g) to read as follows:

(3) The amendments to this part made on September 9, 2024 apply to new actions for which assistance is made available pursuant to declarations under the Robert T. Stafford Disaster Relief and Emergency Assistance Act of 1988 on or after September 9, 2024 and new actions for which assistance is made available pursuant to notices of funding opportunities published on or after September 9, 2024. For ongoing actions for which assistance was made available prior to that date, legacy program regulations (available at http://www.fema.gov ) shall apply.

(1) Executive Order 11990 , Protection of Wetlands, contains a limited exemption not found in Executive Order 11988 , Floodplain Management, as amended. * * *

(c) Decision-making involving certain categories of actions. The provisions set forth in this part are not applicable to the actions enumerated in paragraphs (c)(1) through (10) of this section except that the Regional Administrators shall comply with the spirit of Executive Order 11988 , as amended, and Executive Order 11990 to the extent practicable. For any action which is excluded from the actions enumerated below, the full 8-step process applies (see § 9.6) (except as indicated at paragraphs (d), (e), and (g) of this section regarding other categories of partial or total exclusion). The provisions of this part do not apply to the following (all references are to the Robert T. Stafford Disaster Relief and Emergency Assistance Act of 1988, Public Law 93-288, as amended, except as noted):

(1) Assistance provided for emergency work essential to save lives and protect property and public health and safety performed pursuant to sections 403 and 502;

(2) Emergency Support Teams (section 303);

(3) Emergency Communications (section 418);

(4) Emergency Public Transportation (section 419);

(5) Fire Management Assistance (section 420), except for hazard mitigation assistance under sections 404 and 420(d);

(6) Community Disaster Loans (section 417), except to the extent that the proceeds of the loan will be used for repair of facilities or structures or for construction of additional facilities or structures;

(7) The following Federal Assistance to Individuals and Households Program (section 408) categories of assistance:

(i) Financial assistance for temporary housing (section 408(c)(1)(A));

(ii) Lease and repair of rental units for temporary housing (section 408(c)(1)(B)(ii)), except that Step 1 (§ 9.7) shall be carried out;

(iii) Repairs (section 408(c)(2));

(iv) Replacement (section 408(c)(3)); and

(v) Financial assistance to address other needs (section 408(e)).

(8) Debris clearance and removal (sections 403 and 502), except those grants involving non-emergency disposal of debris within a floodplain or wetland (section 407);

(9) Actions under sections 406 and 407 of less than $18,000. Such $18,000 amount will be adjusted annually to reflect changes in the Consumer Price Index for All Urban Consumers published by the Department of Labor;

(10) Placement of families in existing resources and Temporary Relocation Assistance provided to those families so placed under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980, Public Law 96-510.

(d) Abbreviated decision-making process applying steps 1, 4, 5, and 8. The Regional Administrator shall apply steps 1, 4, 5, and 8 of the decision-making process (§§ 9.7, 9.10, and 9.11) to repairs under section 406 of the Robert T. Stafford Disaster Relief and Emergency Assistance Act of 1988, Public Law 93-288, as amended, between $18,000 and $91,000. Such $18,000 and $91,000 amounts will be adjusted annually to reflect changes in the Consumer Price Index for All Urban Consumers published by the Department of Labor. For any action which is excepted from the actions listed below (except as otherwise provided in this section regarding other categories of partial or total exclusion), the full 8-step process applies (See § 9.6). The Regional Administrator may also require certain other portions of the decision-making process to be carried out for individual actions as is deemed necessary. Steps 1, 4, 5, and 8 of the decision-making process apply to actions under section 406 of the Stafford Act referenced above except for: Start Printed Page 57041

(1) Actions in a floodway or coastal high hazard area; or

(2) New construction, substantial improvement, or repairs to address substantial damage of structures or facilities; or

(3) Facilities or structures which have previously sustained damage from flooding due to a major disaster or emergency or on which a flood insurance claim has been paid; or

(4) Critical actions.

(e) Abbreviated decision-making process applying steps 1, 2, 4, 5, and 8. The Regional Administrator shall apply steps 1, 2, 4, 5, and 8 of the decision-making process (§§ 9.7, 9.8, 9.10, and 9.11, see § 9.6) to certain actions under Section 406 of the Robert T. Stafford Disaster Relief and Emergency Assistance Act of 1988, Public Law 93-288, as amended, provided in paragraphs (e)(1) and (2) of this section. Steps 3 and 6 (§ 9.9) shall be carried out except that alternative sites outside the floodplain or wetland need not be considered. After assessing impacts of the proposed action on the floodplain or wetlands and of the site on the proposed action, alternative actions to the proposed action, if any, and the “no action” alternative shall be considered. The Regional Administrator may also require certain other portions of the decision-making process to be carried out for individual actions as is deemed necessary. For any action which is excluded from the actions listed below (except as otherwise provided in this section regarding other categories of partial or total exclusion), the full 8-step process applies (see § 9.6). The Regional Administrator shall apply steps 1, 2, 4, 5, and 8 of the decision-making process (§§ 9.7, 9.8, 9.10, and 9.11, see § 9.6) to:

(1) Replacement of building contents, materials, and equipment (section 406).

(2) Repairs under section 406 to damaged facilities or structures, except any such action for which one or more of the following is applicable:

(i) FEMA estimated cost of repairs is more than 50 percent of the estimated reconstruction cost of the entire facility or structure or is more than $364,000. Such $364,000 amount will be adjusted annually to reflect changes in the Consumer Price Index for All Urban Consumers published by the Department of Labor; or

(ii) The action is located in a floodway or coastal high hazard area; or

(iii) Facilities or structures which have previously sustained structural damage from flooding due to a major disaster or emergency or on which a flood insurance claim has been paid; or

(iv) The action is a critical action.

(f) Other categories of actions. Based upon the completion of the 8-step decision-making process (§ 9.6), the Regional Administrator may find that a specific category of actions either offers no potential for carrying out the purposes of the Orders and shall be treated as those actions listed in paragraph (c) of this section, or has no practicable alternative sites and shall be treated as those actions listed in paragraph (e) of this section, or has no practicable alternative actions or sites and shall be treated as those actions listed in paragraph (d) of this section. This finding will be made in consultation with FEMA Resilience and the Council on Environmental Quality as provided in section 2(d) of Executive Order 11988 , as amended. Public notice of each of these determinations shall include publication in the Federal Register and a 30-day comment period.

(g) The National Flood Insurance Program (NFIP). (1) FEMA Resilience shall apply the 8-step decision-making process to program-wide actions under the NFIP, including all regulations, procedures, and other issuances making or amending program policy, and the establishment of programmatic standards or criteria. FEMA Resilience shall not apply the 8-step decision-making process to the application of programmatic standards or criteria to specific situations. Thus, for example, FEMA Resilience would apply the 8-step process to a programmatic determination of categories of structures to be insured, but not to whether to insure each individual structure.

(2) The provisions set forth in this part are not applicable to the actions enumerated below except that FEMA Resilience shall comply with the spirit of the Orders to the extent practicable:

(i) The issuance of individual flood insurance policies and policy interpretations;

(ii) The adjustment of claims made under the Standard Flood Insurance Policy;

(iii) The hiring of independent contractors to assist in the implementation of the NFIP;

(iv) The issuance of individual flood insurance maps, Map Information Facility map determinations, and map amendments; and

(v) The conferring of eligibility for emergency or regular program (NFIP) benefits upon communities.

7. Revise § 9.6 to read as follows:

(a) Purpose. This section sets out the floodplain management and wetlands protection decision-making process to be followed by the Agency in applying the Orders to its actions. The numbering of Steps 1 through 8 does not require that the steps be followed sequentially. As information is gathered through the decision-making process, and as additional information is needed, reevaluation of lower numbered steps may be necessary.

(b) Decision-making process. Except as otherwise provided in § 9.5 regarding categories of partial or total exclusion when proposing an action, the Agency shall apply the 8-step decision-making process. FEMA shall:

(1) Step 1. Determine whether the proposed action is located in a floodplain and/or a wetland as established by § 9.7; and whether it has the potential to affect or be affected by a floodplain or wetland (see § 9.7);

(2) Step 2. Notify the public at the earliest possible time of the intent to carry out an action in a floodplain or wetland, and involve the affected and interested public in the decision-making process (see § 9.8);

(3) Step 3. Identify and evaluate practicable alternatives to locating the proposed action in a floodplain or wetland (including alternative sites, actions, natural features, nature-based approaches, and the “no action” option) (see § 9.9). If a practicable alternative exists outside the floodplain or wetland FEMA must locate the action at the alternative site.

(4) Step 4. Identify the potential direct and indirect impacts associated with the occupancy or modification of floodplains and wetlands and the potential direct and indirect support of floodplain and wetland development that could result from the proposed action (see § 9.10);

(5) Step 5. Minimize the potential adverse impacts to or within floodplains and wetlands and minimize support of floodplain and wetland development identified under Step 4. Restore and preserve the natural and beneficial values served by floodplains, and preserve and enhance the natural and beneficial values served by wetlands. Integrate nature-based approaches where appropriate (see § 9.11);

(6) Step 6. Reevaluate the proposed action to determine first, if it is still practicable in light of its exposure to flood hazards, the extent to which it will aggravate hazards to others, and its potential to disrupt floodplain and wetland values; and second, if alternatives preliminarily rejected at Step 3 are practicable in light of the information gained in Steps 4 and 5. FEMA shall not act in a floodplain or wetland unless it is the only practicable location ( see § 9.9); Start Printed Page 57042

(7) Step 7. Prepare and provide the public with a finding and public explanation of any final decision that the floodplain or wetland is the only practicable alternative (see § 9.12); and

(8) Step 8. Review the implementation and post-implementation phases of the proposed action to ensure that the requirements stated in § 9.11 are fully implemented. Oversight responsibility shall be integrated into existing processes.

8. Amend § 9.7 by revising paragraphs (a), (b), (c), and (d)(3) and (4) to read as follows:

(a) Purpose. This section establishes Agency procedures for determining whether any action as proposed is located in or affects a floodplain established in paragraph (c) of this section or a wetland.

(b) Information needed. (1) The Agency shall obtain enough information so that it can fulfill the requirements in this part to:

(i) Avoid Federal action in floodplain and wetland locations unless they are the only practicable alternatives; and

(ii) Minimize harm to and within floodplains and wetlands.

(2) In all cases, FEMA shall determine whether the proposed action is located in a floodplain or wetland. Information about the floodplain as established by paragraph (c) of this section and the location of floodways and coastal high hazard areas may also be needed to comply with this part, especially § 9.11.

(3) The following additional current and future flooding characteristics may be identified by the Regional Administrator as applicable:

(i) Velocity of floodwater;

(ii) Rate of rise of floodwater;

(iii) Duration of flooding;

(iv) Available warning and evacuation time and routes;

(v) Special problems:

(A) Levees;

(B) Erosion;

(C) Subsidence;

(D) Sink holes;

(E) Ice jams;

(F) Debris load;

(G) Pollutants;

(H) Wave heights;

(I) Groundwater flooding;

(J) Mudflow.

(vi) Any other applicable flooding characteristics.

(c) Floodplain determination. In the absence of a finding to the contrary, FEMA will determine that a proposed action involving a facility or structure that has been flooded previously is in the floodplain. In determining if a proposed action is in the floodplain:

(1) FEMA shall determine whether the action is an action subject to the FFRMS as defined in § 9.4.

(i) If the action is an action subject to the FFRMS, FEMA shall establish the FFRMS floodplain area and associated flood elevation by using the process specified in (c)(3) of this section and one of the following approaches:

(A) Climate-Informed Science Approach (CISA): Using a climate-informed science approach that uses the best-available, actionable hydrologic and hydraulic data and methods that integrate current and future changes in flooding based on climate science. This approach will also include an emphasis on whether the action is a critical action as one of the factors to be considered when conducting the analysis;

(B) Freeboard Value Approach (FVA): Using the freeboard value, reached by adding an additional 2 feet to the base flood elevation for non-critical actions and by adding an additional 3 feet to the base flood elevation for critical actions;

(C) 0.2-Percent-Annual-Chance Flood Approach (0.2PFA): The 0.2 percent annual chance flood; or

(D) Any other method identified in an update to the FFRMS.

(ii) FEMA may select among and prioritize the approaches in this paragraph (c)(1) by policy.

(iii) FEMA may provide an exception to using the FFRMS floodplain and corresponding flood elevation for an action subject to the FFRMS and instead use the 1 percent annual chance (base) floodplain for non-critical actions or the 0.2 percent annual chance floodplain for critical actions where the action is in the interest of national security, where the action is an emergency action, or where the action is a mission-critical requirement related to a national security interest or an emergency action.

(2) If the action is not an action subject to the FFRMS as defined in § 9.4, FEMA shall use, at a minimum:

(i) The 1 percent annual chance (base) floodplain and flood elevation for non-critical actions; and

(ii) The 0.2 percent annual chance floodplain and flood elevation for critical actions.

(3) FEMA shall establish the floodplain and corresponding elevation using the best available information. The floodplain and corresponding elevation determined using the best available information must be at least as restrictive as FEMA's regulatory determinations under the NFIP where such determinations are available. In obtaining the best available information, FEMA may consider other FEMA information as well as other available information, such as information from:

(i) Department of Agriculture: Natural Resources Conservation Service, U.S. Forest Service;

(ii) Department of Defense: U.S. Army Corps of Engineers;

(iii) Department of Commerce: National Oceanic and Atmospheric Administration;

(iv) Department of the Interior: Bureau of Land Management, Bureau of Reclamation, National Park Service, U.S. Fish and Wildlife Service, United States Geological Survey;

(v) Tennessee Valley Authority;

(vi) Department of Transportation;

(vii) Environmental Protection Agency;

(viii) General Services Administration;

(ix) Agencies of State, Regional, and Indian Tribal governments; or

(x) Local sources such as Floodplain Administrators, Regional Flood Control Districts, or Transportation Departments.

(4) If the sources listed in paragraph (c)(3) of this section do not have or know of the information necessary to comply with the requirements in this part, the Regional Administrator may seek the services of a professional registered engineer.

(5) If a decision involves an area or location within extensive Federal or state holdings or a headwater area and FEMA's regulatory determinations under the National Flood Insurance Program are not available, the Regional Administrator shall seek information from the land administering agency before information and/or assistance is sought from the sources listed in paragraph (c)(3) of this section.

(3) If the identified sources do not have adequate information upon which to base the determination, the Agency shall carry out an on-site analysis performed by a representative of the FWS or other qualified individual for wetlands characteristics based on the definition of a wetland in § 9.4.

(4) If an action constitutes new construction and is in a wetland but not in a floodplain, the provisions of this part shall apply. If the action is not in a wetland, the Regional Administrator shall determine if the action has the potential to result in indirect impacts on wetlands. If so, all potential adverse impacts shall be minimized. For actions which are in a wetland and the floodplain, completion of the decision-making process is required. ( See § 9.6). In such a case, the wetland will be considered as one of the natural and beneficial values of the floodplain.

9. Amend § 9.8 by revising paragraphs (a) and (c)(1), the first sentence of Start Printed Page 57043 paragraph (c)(2), and paragraphs (c)(3) introductory text, (c)(3)(v), and (c)(4) and (5) to read as follows:

(a) Purpose. This section establishes the initial notice procedures to be followed when the Agency proposes any action in or affecting floodplains or wetlands.

(1) For an action for which an environmental impact statement is being prepared, the Notice of Intent to File an EIS constitutes the early public notice if it includes the information required under paragraph (c)(5) of this section.

(2) For each action having national significance for which notice is being provided, the Agency at a minimum shall provide notice by publication in the Federal Register and shall provide notice by mail to national organizations reasonably expected to be interested in the action. * * *

(3) The Agency shall determine whether it has provided appropriate notices, adequate comment periods, and whether to issue cumulative notices (paragraphs (c)(4), (6), and (7) of this section) based on factors which include, but are not limited to:

(v) Anticipated potential impact of the action.

(4) For each action having primarily local importance for which notice is being provided, notice shall be made in accordance with the criteria under paragraph (c)(3) of this section, and shall include, as appropriate:

(i) Notice through the internet or another comparable method.

(ii) Notice to Indian tribes when effects may occur on reservations.

(iii) Information required in the affected State's public notice procedures for comparable actions.

(iv) Publication in local newspapers.

(v) Notice through other local media including newsletters.

(vi) Notice to potential interested community organizations.

(vii) Direct mailing to owners and occupants of nearby or affected property.

(viii) Posting of notice on and off site in the area where the action is to be located.

(ix) Public hearing.

(5) The notice shall:

(i) Describe the action, its purposes, and a statement of the intent to carry out an action affecting or affected by a floodplain or wetland;

(ii) Based on the factors in paragraph (c)(3) of this section, include a map of the area and other identification of the floodplain and/or wetland areas which is of adequate scale and detail; alternatively, FEMA may state that such map is available for public inspection, including the location at which such map may be inspected and a telephone number to call for information or may provide a link to access the map online;

(iii) Based on the factors in paragraph (c)(3) of this section, describe the type, extent, and degree of hazard involved and the floodplain or wetland values present; and

(iv) Identify the responsible official or organization for implementing the proposed action, and from whom further information can be obtained.

10. Amend § 9.9 by:

a. Revising paragraphs (a)(1), (b)(2), and (c)(1) through (4);

b. Adding paragraph (c)(5);

c. Revising paragraphs (d), (e)(1)(i), (iii), and (iv), (e)(2) introductory text, (e)(3) introductory text, and (e)(4); and

d. Lifting the suspension of paragraph (e)(6) and removing the paragraph.

The revisions and additions read as follows:

(a) * * * *

(1) This section expands upon the directives set out in § 9.6 of this part in order to clarify and emphasize the requirements to avoid floodplains and wetlands unless there is no practicable alternative.

(2) Alternative actions which serve essentially the same purpose as the proposed action, but which have less potential to affect or be affected by the floodplain or wetlands. In developing the alternative actions, the Agency shall use, where possible, natural systems, ecosystem processes, and nature-based approaches; and

(1) Natural environment (including, but not limited to topography, habitat, hazards, when applicable);

(2) Social concerns (including, but not limited to aesthetics, historical and cultural values, land patterns, when applicable);

(3) Economic aspects (including, but not limited to costs of space, technology, construction, services, relocation, when applicable);

(4) Legal constraints (including, but not limited to deeds and leases, when applicable); and

(5) Agency authorities.

(1) The Agency shall not locate the proposed action in the floodplain as established by § 9.7(c) or in a wetland if a practicable alternative exists outside the floodplain or wetland.

(2) If no practicable alternative exists outside the floodplain or wetland, in order to carry out the action the floodplain or wetland must itself be a practicable location in light of the review required in this section.

(i) The action is still practicable at a floodplain or wetland site, considering the flood risk and the ensuing disruption of natural values;

(iii) The scope of the action can be limited to increase the practicability of previously rejected non-floodplain or wetland sites and alternative actions; and

(iv) Harm to or within the floodplain can be minimized using all practicable means.

(2) Take no action in a floodplain unless the importance of the floodplain site clearly outweighs the requirements to:

(3) Take no action in a wetland unless the importance of the wetland site clearly outweighs the requirements to:

(4) In carrying out this balancing process, give the factors in paragraphs (e)(2) and (3) of this section great weight.

11. Amend § 9.10 by revising paragraph (a), the second sentence of paragraph (b), and paragraphs (c) and (d) to read as follows:

(a) This section ensures that the effects of proposed Agency actions are identified.

(b) * * * Such identification of impacts shall be to the extent necessary to comply with the requirements of this part to avoid floodplain and wetland locations unless they are the only practicable alternatives to minimize harm to and within floodplains and wetlands.

(c) This identification shall consider whether the proposed action will result in an increase in the useful life of any structure or facility in question, maintain the investment at risk and exposure of lives to the flood hazard or forego an opportunity to restore the natural and beneficial values served by floodplains or wetlands. Start Printed Page 57044

(d) In the review of a proposed or alternative action, the Regional Administrator shall consider and evaluate: impacts associated with modification of wetlands and floodplains regardless of its location; additional impacts which may occur when certain types of actions may support subsequent action which have additional impacts of their own; adverse impacts of the proposed actions on lives and property and on natural and beneficial floodplain and wetland values; and the three categories of factors listed below:

(1) Flood hazard-related factors. These include, but are not limited to, the factors listed in § 9.7(b)(3);

(2) Natural values-related factors. These include, but are not limited to: water resource values, as in storing and conveying floodwaters, maintaining water quality, and groundwater recharge; living resource values, as in providing habitats and enhancing biodiversity for fish and wildlife and plant resources; cultural resource values, as in providing open space, natural beauty, recreation, scientific study, historical and archaeological resources, and education; and cultivated resource values, as in creating rich soils for agriculture, aquaculture, and forestry.

(3) Factors relevant to a proposed action's effects on the survival and quality of wetlands. These include, but are not limited to: Public health, safety, and welfare, including water supply, quality, recharge and discharge; pollution; flood and storm hazards; and sediment and erosion; maintenance of natural systems, including conservation and long term productivity of existing flora and fauna, species and habitat diversity and stability, hydrologic utility, fish, wildlife, timber, and food and fiber resources; and other uses of wetlands in the public interest, including recreational, scientific, and cultural uses.

12. Amend § 9.11 by:

a. Revising paragraphs (a) and (c)(1);

b. Revising the first sentence of paragraph (d) introductory text and revising paragraphs (d)(1) introductory text, (d)(2) through (4), (d)(5) introductory text, and (d)(9);

c. Lifting the suspension of paragraph (e)(4) and removing paragraph (e); and

d. Redesignating paragraph (f) as paragraph (e) and revising it.

The revisions read as follows:

(a) Purpose. This section expands upon the directives set out in § 9.6 of this part and sets out the mitigative actions required if the preliminary determination is made to carry out an action that affects or is in a floodplain or wetland.

(1) Potential harm to lives and the investment from flooding based on flood elevations as established by § 9.7(c);

(d) Minimization standards. The Agency shall apply, at a minimum, the following standards to its actions to comply with the requirements of paragraphs (b) and (c) of this section (except as provided in § 9.5(c), (d), and (g) regarding categories of partial or total exclusion). * * *

(1) There shall be no new construction or substantial improvement in a floodway and no new construction in a coastal high hazard area, except for:

(2) For a structure which is a functionally dependent use or which facilitates an open space use, the following applies: Any construction of a new or substantially improved structure in a coastal high hazard area must be elevated on adequately anchored pilings or columns, and securely anchored to such piles or columns so that the lowest portion of the structural members of the lowest floor (excluding the pilings or columns) is elevated to or above the floodplain as established by § 9.7(c). The structure shall be anchored so as to withstand velocity waters and hurricane wave wash.

(3) The following applies to elevation of structures:

(i) There shall be no new construction or substantial improvement of structures unless the lowest floor of the structures (including basement) is at or above the elevation of the floodplain as established by § 9.7(c).

(ii) If the subject structure is nonresidential, instead of elevating the structure, FEMA may approve the design of the structure and its attendant utility and sanitary facilities so that the structure is watertight below the flood elevation with walls substantially impermeable to the passage of water and with structural components having the capability of resisting hydrostatic and hydrodynamic loads and effects of buoyancy.

(iii) The provisions of paragraphs (d)(3)(i) and (ii) of this section do not apply to the extent that FEMA Resilience has granted an exception under § 60.6(b) of this chapter, or the community has granted a variance which the Regional Administrator determines is consistent with § 60.6(a) of this chapter. In a community which does not have a FEMA regulatory product in effect, FEMA may approve a variance from the standards of paragraphs (d)(3)(i) and (ii) of this section, after compliance with the standards of § 60.6(a).

(4) There shall be no encroachments, including but not limited to fill, new construction, substantial improvements of structures or facilities, or other development within a designated regulatory floodway that would result in any increase in flood elevation within the community during the occurrence of the 1 percent annual chance (base) flood discharge. Until a regulatory floodway is designated, no fill, new construction, substantial improvements, or other development shall be permitted within the 1 percent annual chance (base) floodplain unless it is demonstrated that the cumulative effect of the proposed development, when combined with all other existing and anticipated development, will not increase the water surface elevation of the 1 percent annual chance (base) flood more than the amount designated by the NFIP or the community, whichever is most restrictive.

(5) Even if an action is a functionally dependent use or facilitates open space uses (under paragraph (d)(1) or (2) of this section) and does not increase flood heights (under paragraph (d)(4) of this section), such action may only be taken in a floodway or coastal high hazard area if:

(9) In the replacement of building contents, materials and equipment, the Regional Administrator shall require as appropriate, flood proofing and/or elevation of the building and/or elimination of such future losses by relocation of those building contents, materials, and equipment outside or above the floodplain as established by § 9.7(c).

(e) Restore and preserve. (1) For any action taken by the Agency which affects the floodplain or wetland and which has resulted in, or will result in, harm to the floodplain or wetland, the Agency shall act to restore and preserve the natural and beneficial values served by floodplains and wetlands.

(2) Where floodplain or wetland values have been degraded by the proposed action, the Agency shall identify, evaluate, and implement measures to restore the values.

(3) If an action will result in harm to or within the floodplain or wetland, the Agency shall design or modify the action to preserve as much of the natural and beneficial floodplain and wetland values as is possible.

13. Amend § 9.12 by:

a. Redesignating paragraphs (d) introductory text and (d)(1) through (6) as paragraphs (d)(1) introductory text and (d)(1)(i) through (vi), respectively; and

c. Designate the undesignated text after newly redesignated paragraph (d)(1)(vi) as paragraph (d)(2) and revise it.

The revision reads as follows:

(2) When a damaged structure or facility is already being repaired by the State or local government at the time of the project application, the requirements of Steps 2 and 7 (§ 9.8 and this section) may be met by a single notice. Such notice shall contain all the information required by both sections.

14. Revise § 9.13 to read as follows:

(a) This section sets forth the procedures whereby the Agency will provide certain specified types of temporary housing at a private, commercial, or group site.

(b) Prior to providing the temporary housing described in paragraph (a) of this section, the Agency shall comply with the provisions of this section. For temporary housing not enumerated above, the full 8-step process ( see § 9.6) applies.

(c) The actions described in paragraph (a) of this section are subject to the following decision-making process:

(1) The temporary housing action shall be evaluated in accordance with the provisions of § 9.7 to determine if it is in or affects the 1 percent annual chance (base) floodplain or wetland.

(2) No temporary housing unit may be placed on a site in a floodway or coastal high hazard area.

(3) An individual or family shall not be housed in the 1 percent annual chance (base) floodplain or wetland unless the Regional Administrator has complied with the provisions of § 9.9 to determine that such site is the only practicable alternative. The following factors shall be substituted for the factors in § 9.9(c) and (e)(2) through (4):

(i) Speedy provision of temporary housing;

(ii) Potential flood risk to the temporary housing occupant;

(iii) Cost effectiveness;

(iv) Social and neighborhood patterns;

(v) Timely availability of other housing resources; and

(vi) Potential harm to the floodplain or wetland.

(4) For temporary housing units at group sites, Step 4 of the 8-step process shall be applied in accordance with § 9.10.

(5) An individual or family shall not be housed in a floodplain or wetland (except in existing resources) unless the Regional Administrator has complied with the provisions of § 9.11 to minimize harm to and within floodplains and wetlands. The following provisions shall be substituted for the provisions of § 9.11(d) for temporary housing units:

(i) No temporary housing unit may be placed unless it is elevated to the fullest extent practicable up to the base flood elevation and adequately anchored.

(ii) No temporary housing unit may be placed if such placement is inconsistent with the criteria of the NFIP ( 44 CFR parts 59 and 60 ) or any more restrictive Federal, State, or local floodplain management standard. Such standards may require elevation to the base flood elevation in the absence of a variance.

(iii) Temporary housing units shall be elevated on open works (walls, columns, piers, piles, etc.) rather than on fill where practicable.

(iv) To minimize the effect of floods on human health, safety and welfare, the Agency shall:

(A) Where appropriate, integrate all of its proposed actions in placing temporary housing units for temporary housing in floodplains into existing flood warning or preparedness plans and ensure that available flood warning time is reflected;

(B) Provide adequate access and egress to and from the proposed site of the temporary housing unit; and

(C) Give special consideration to the unique hazard potential in flash flood and rapid-rise areas.

(6) FEMA shall comply with Step 2 Early Public Notice (§ 9.8(c)) and Step 7 Final Public Notice (§ 9.12). In providing these notices, the emergency nature of temporary housing shall be taken into account.

(7) FEMA shall carry out the actions in accordance with Step 8, ensuring the requirements of this section and the decision-making process are fully integrated into the provision of temporary housing.

(d) The following applies to the permanent installation of a temporary housing unit as part of a sale or disposal of temporary housing:

(1) FEMA shall not permanently install temporary housing units in floodways or coastal high hazard areas. FEMA shall not permanently install a temporary housing unit in floodplains as established by 9.7(c) or wetlands unless there is full compliance with the 8-step process. Given the vulnerability of temporary housing units to flooding, a rejection of a non-floodplain location alternative and of the no-action alternative shall be based on:

(i) A compelling need of the family or individual to buy a temporary housing unit for permanent housing; and

(ii) A compelling requirement to permanently install the unit in a floodplain.

(2) FEMA shall not permanently install temporary housing units in the floodplain as established by § 9.7(c) unless they are or will be elevated at least to the elevation of the floodplain as established by § 9.7(c).

(3) The Regional Administrator shall notify FEMA Resilience of each instance where a floodplain location has been found to be the only practicable alternative for permanent installation of a temporary housing unit.

15. Amend § 9.14 by revising paragraphs (a), (b)(4), (5), and (6), (b)(7)(ii) and (iii), and (b)(9) to read as follows:

(a) This section sets forth the procedures whereby the Agency shall dispose of property.

(4) Identify the potential impacts and support of floodplain and wetland development associated with the disposal of the property in accordance with § 9.10;

(5) Identify the steps necessary to minimize, restore, preserve and enhance in accordance with § 9.11. For disposals, this analysis shall address all four of these components of mitigation where unimproved property is involved, but shall focus on minimization through elevation or floodproofing and restoration of natural values where improved property is involved;

(6) Reevaluate the proposal to dispose of the property in light of its exposure to the flood hazard and its natural values-related impacts, in accordance with § 9.9. This analysis shall focus on whether it is practicable in light of the findings from §§ 9.10 and 9.11 to dispose of the property, or whether it must be retained. If it is determined that it is practicable to dispose of the property, this analysis shall identify the practicable alternative that best achieves the Agency's mitigation responsibility.

(ii) Properties located inside the floodplain but outside of the floodway and the coastal high hazard area; and

(iii) Properties located in a floodway, regulatory floodway, or coastal high hazard area.

(9) The Agency shall ensure that the applicable mitigation requirements are fully implemented in accordance with § 9.11(c).

16. Amend § 9.16 by revising paragraphs (b) introductory text, (b)(2) through (5), and (c) to read as follows:

(b) This shall be accomplished primarily through amendment of all Agency instructions to applicants, and also through contact made by agency staff during the normal course of their activities, to fully inform prospective applicants of:

(2) The decision-making process to be used by the Agency in making the determination of whether to take an action in or affecting floodplains or wetlands as set out in § 9.6;

(3) The practicability analysis as set out in § 9.9;

(4) The mitigation responsibilities as set out in § 9.11;

(5) The public notice and involvement process as set out in §§ 9.8 and 9.12; and

(c) Guidance to applicants shall be provided, where possible, prior to the time of application in order to minimize potential delays in the Agency's processing of the application due to failure of applicants to follow the provisions in this part.

17. Amend § 9.17 by revising paragraphs (a), (b) introductory text, (b)(3) through (5), (c), and (d) to read as follows:

(a) Purpose. In accordance with Executive Orders 11988, as amended, and 11990, the Federal executive agencies must respond to a number of floodplain management and wetland protection responsibilities before carrying out any of their activities, including the provision of Federal financial and technical assistance. This section provides notice to applicants for Agency assistance of both the criteria that FEMA is required to follow, and the applicants' responsibilities under this part.

(b) Responsibilities of applicants. Based upon the guidance provided by the Agency under § 9.16, the guidance included in the U.S. Water Resources Council's Guidelines for Implementing Executive Order 11988 , Floodplain Management, and Executive Order 13690 , Establishing a Federal Flood Risk Management Standard and a Process for Further Soliciting and Considering Stakeholder Input, and based upon the provisions of the Orders and this part, applicants for Agency assistance shall recognize and reflect in their application:

(c) Provision of supporting information. Applicants for Agency assistance may be required to provide supporting information relative to the various responsibilities set out in paragraph (b) of this section as a prerequisite to the approval of their applications.

(d) Approval of applicants. Applications for Agency assistance shall be reviewed for compliance with the provisions in this part in addition to the Agency's other approval criteria.

18. Amend § 9.18 by revising paragraph (a)(1), the second sentence of paragraph (b)(1), and the first sentence of (b)(2) to read as follows:

(1) Implement the requirements of the Orders and this part. Under §§ 9.2 and 9.6 through 9.13 and 9.15 where a direction is given to the Agency, it is the responsibility of the Regional Administrator.

(1) * * * When a decision of a Regional Administrator relating to disaster assistance is appealed, FEMA Resilience may make determinations under this part on behalf of the Agency.

(2) Prepare and submit to the Office of Chief Counsel reports to the Office of Management and Budget in accordance with section 2(b) of Executive Order 11988 , as amended, and section 3 of Executive Order 11990 . * * *

19. Remove appendix A to part 9.

Deanne Criswell,

Administrator, Federal Emergency Management Agency.

1.   42 FR 6030 , Feb. 10, 1978. A PDF copy of the 1978 Guidelines can be found at this link: hud.gov/sites/documents/DOC_14216.PDF (last accessed Jan. 24, 2024).

2.  FEMA published an interim final rule on December 27, 1979 ( 44 FR 76510 ) and a final rule on September 9, 1980 ( 45 FR 59520 ). Note that this part also implements a related Executive Order 11990 , “Protection of Wetlands.” See 42 FR 26961 , May 25, 1977.

3.  Any action FEMA takes in a floodplain or wetland, including its provision of grants for disaster assistance, undergoes an analysis pursuant to Executive Orders 11988 and 11990 (unless the action is specifically exempted from the requirements of the Orders). The grant recipient, therefore, generally provides information to FEMA about the practicability of alternatives outside the floodplain and wetland and other information to assist in the analysis.

4.   Executive Order 13690 , “Establishing a Federal Flood Risk Management Standard (FFRMS) and a Process for Further Soliciting and Considering Stakeholder Input.” 80 FR 6425 , Feb. 4, 2015. In 2017, President Donald Trump revoked the amendments to Executive Order 11988 . See Executive Order 13807 , “Establishing Discipline and Accountability in the Environmental Review and Permitting Process for Infrastructure Project,” 82 FR 40463 , Aug. 24, 2017. In 2021, President Joseph Biden reinstated the amendments. See Executive Order 14030 , “Climate Related Financial Risk,” 86 FR 27967 , May 25, 2021.

5.   See “Guidelines for Implementing Executive Order 11998 , Floodplain Management, and Executive Order 13690 , Establishing a Federal Flood Risk Management Standard and a Process for Further Soliciting and Considering Stakeholder Input,” 80 FR 64008 (Oct. 22, 2015) (providing notice of the availability of the Revised Guidelines in the docket for the rulemaking at https://www.regulations.gov/​document/​FEMA-2015-0006-0358 (main content) and https://www.regulations.gov/​document/​FEMA-2015-0006-0372 (appendices)) also available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​implementing-guidelines-EO11988-13690_​10082015.pdf (last accessed Mar. 11, 2024).

6.   80 FR 64008 , Oct. 22, 2015.

7.   See FEMA Policy 104-22-003, “Partial Implementation of the Federal Flood Risk Management Standard for Public Assistance (Interim),” June 3, 2022, found at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​fp-104-22-0003-partial-implemetnation-ffrms-pa-interim.pdf (last accessed Jan. 24, 2024) and FEMA Policy 206-21-003-0001, “Partial Implementation of the Federal Flood Risk Management Standard for Hazard Mitigation Assistance Program,” Dec. 7, 2022 found at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​policy-fp-206-21-003-0001-implementation-ffrms-hma-program_​122022.pdf (last accessed Jan. 24, 2024).

8.   88 FR 67870 , Oct. 2, 2023; 88 FR 67697 , Oct. 2, 2023.

9.   42 U.S.C. 5121 et seq.

10.   42 U.S.C. 4001 et seq.

11.   6 U.S.C. 101 et seq; see also 6 U.S.C. 314(a)(12) , which specifically charges the Administrator with supervising various grant programs authorized under the HSA. Such grant programs have long been governed by floodplain management regulations at 44 CFR part 9 , see, e.g., 44 FR 76510 (Dec. 27, 1979), 45 FR 59520 (Sept. 9, 1980). See also, e.g., 2 CFR 200.300(a) (directing Federal awarding agencies to manage and administer Federal awards in a manner so as to ensure that Federal funding is expended and associated programs are implemented in full accordance with the U.S. Constitution, Federal Law, and public policy requirements including, but not limited to, those protecting public welfare and the environment; and requiring the Federal awarding agency to communicate to the non-Federal entity all relevant public policy requirements, and incorporate them either directly or by reference in the terms and conditions of the Federal award.).

12.   15 U.S.C. 2229 and 2229a .

13.   42 U.S.C. 7701 et seq.

14.   See, e.g., 6 U.S.C. 609 (granting FEMA approval authority over grant funds for construction awards under its Homeland Security Grant Program, State Homeland Security Grant Program, Urban Area Security Initiative, Operation Stonegarden, Tribal Homeland Security Grant Program, and Nonprofit Security Grant Program); 6 U.S.C. 1182(d)(1) (granting DHS the authority to determine the grant requirements for the Intercity Bus Security Grant Program); 6 U.S.C. 1163(c)(1) (granting FEMA the authority to determine the grant requirements for the Intercity Passenger Rail grant program); 46 U.S.C. 70101 (granting DHS approval authority over grant funds for construction awards under the Port Security Grant Program); 6 U.S.C. 1135(c)(1) (granting DHS the authority to determine the grant requirements for the Transit Security Grant Program); 33 U.S.C. 467f-2(c)(2)(A) (granting FEMA the authority to set the minimum eligibility requirements for the Rehabilitation of High Hazard Dam Program).

15.   See 42 U.S.C. 5164 ; 42 U.S.C. 4128(a) and (b) .

16.   42 U.S.C. 5165a(a)(1)-(2) .

17.  As a result of climate change, flood events are on the rise. Climate change is increasing flood risk through (1) more “extreme” rainfall events,” caused by a warmer atmosphere holding more water vapor and changes in regional precipitation patterns; and (2) sea-level rise. See Rob Bailey, Claudio Saffioti, and Sumer Drall, Sunk Costs: The Socioeconomic Impacts of Flooding 3 and 8, Marsh McLennan (2021).

18.  Federal Budget Exposure to Climate Risk. OMB Assessment found https://www.whitehouse.gov/​wp-content/​uploads/​2022/​04/​ap_​21_​climate_​risk_​fy2023.pdf (last accessed Jan. 24, 2024).

19.   Id.

20.   88 FR 67870 , Oct. 2, 2023.

21.   88 FR 67697 , Oct 2, 2023.

22.  Freeboard is a factor of safety usually expressed in feet above a flood level for purposes of floodplain management. See https://www.fema.gov/​glossary/​freeboard (last accessed June 11, 2024).

23.  FEMA used an average of the number of affected projects during the prior 10-year period to estimate the average annual impacts of the future 10-year period.

24.  To obtain the total costs as in Section 7.12, add each individual approach to the FEMA admin cost. For example, CISA + FEMA admin = total CISA cost.

25.  To obtain the total costs as in Section 7.12, add each individual approach to the FEMA admin cost. For example, CISA + FEMA admin = total CISA cost.

26.  These counts are based on the number of closed or obligated projects at the time of analysis. It can take several years for a project to close out or reach the obligation status after the disaster year.

27.  Category E projects are public buildings and contents. See Public Assistance Fact Sheet at https://www.fema.gov/​sites/​default/​files/​2020-07/​fema_​public-assistance-fact-sheet_​10-2019.pdf .

28.  FEMA used one foot for benefits as the 2022 report, “A Benefits Analysis of Increased Freeboard for Public and Nonresidential Buildings in Riverine and Coastal Floodplains,” only specifies monetary benefits for an additional one foot over current requirements. FEMA included this number in the quantified benefits because it is the only monetary benefit available for any freeboard level.

A Benefits Analysis of Increased Freeboard for Public and Nonresidential Buildings in Riverine and Coastal Floodplains. FEMA. Draft, July 2022, page 16. Available at: https://www.regulations.gov/​document/​FEMA-2023-0026-0003 .

29.  Costs for the FVA may be a better comparison because they represent 2 or 3 feet of freeboard, depending on criticality. However, the number of projects using FVA and CISA differ, making such a comparison difficult.

30.   See 42 FR 26951 , May 25, 1977 at Section 2(d); see also 80 FR 6425 , Feb. 4, 2015 at Section 5(b).

31.   See 42 U.S.C. 4001 and 4102 .

32.   See 42 U.S.C. 4332(2)(C) .

33.   See 42 U.S.C. 4331(b)(3) .

34.  Any action FEMA takes in a floodplain, including its provision of grants for disaster assistance, undergoes an analysis pursuant to FEMA's implementation of Executive Order 11988 (unless the action is specifically exempted from the requirements of the Order and the implementing regulations). The grant recipient, therefore, generally provides information to FEMA about the practicability of alternatives outside the floodplain and other information to assist in the analysis.

35.  This is also referred to as the “100-year floodplain” or the “base floodplain.”

36.  The WRC, established by statute ( 42 U.S.C. 1962a-1 ), is charged with maintaining a continuing study and preparing an assessment biennially, or at such less frequent intervals as the Council may determine, of the adequacy of supplies of water necessary to meet the water requirements in each water resource region in the United States and the national interest therein; and maintaining a continuing study of the relation of regional or river basin plans and programs to the requirements of larger regions of the Nation and of the adequacy of administrative and statutory means for the coordination of the water and related land resources policies and programs of the several Federal agencies. It is responsible for appraising the adequacy of existing and proposed policies and programs to meet such requirements and making recommendations to the President with respect to Federal policies and programs.

37.   42 FR 6030 , Feb. 10, 1978. A PDF copy of the 1978 Guidelines can be found at this link: hud.gov/sites/documents/DOC_14216.PDF (last accessed Jan. 24, 2024).

38.   42 U.S.C. 5121 et seq.

39.   42 U.S.C. 4001 et seq.

40.   6 U.S.C. 101 et seq; see also 6 U.S.C. 314(a)(12) , which specifically charges the Administrator with supervising various grant programs authorized under the HSA. Such grant programs have long been governed by floodplain management regulations at 44 CFR part 9 , see, e.g., 44 FR 76510 (Dec. 27, 1979), 45 FR 59520 (Sept. 9, 1980). See also, e.g., 2 CFR 200.300(a) (directing Federal awarding agencies to manage and administer Federal awards in a manner so as to ensure that Federal funding is expended and associated programs are implemented in full accordance with the U.S. Constitution, Federal Law, and public policy requirements including, but not limited to, those protecting public welfare and the environment; and requiring the Federal awarding agency to communicate to the non-Federal entity all relevant public policy requirements, and incorporate them either directly or by reference in the terms and conditions of the Federal award.).

41.   15 U.S.C. 2229 and 2229a .

42.   42 U.S.C. 7701 et seq.

43.   See, e.g., 6 U.S.C. 609 (granting FEMA approval authority over grant funds for construction awards under its Homeland Security Grant Program, State Homeland Security Grant Program, Urban Area Security Initiative, Operation Stonegarden, Tribal Homeland Security Grant Program, and Nonprofit Security Grant Program); 6 U.S.C. 1182(d)(1) (granting DHS the authority to determine the grant requirements for the Intercity Bus Security Grant Program); 6 U.S.C. 1163(c)(1) (granting FEMA the authority to determine the grant requirements for the Intercity Passenger Rail grant program); 46 U.S.C. 70101 (granting DHS approval authority over grant funds for construction awards under the Port Security Grant Program); 6 U.S.C. 1135(c)(1) (granting DHS the authority to determine the grant requirements for the Transit Security Grant Program); 33 U.S.C. 467f-2(c)(2)(A) (granting FEMA the authority to set the minimum eligibility requirements for the Rehabilitation of High Hazard Dam Program).

44.   42 U.S.C. 5121 et seq.

45.   42 U.S.C. 5121(b)(5) and (7) .

46.   42 U.S.C. 5164 .

47.   42 U.S.C. 5165a(a)(1)-(2) .

48.   42 U.S.C. 4001(c) . As part of the floodplain management program under the NFIP, FEMA establishes minimum floodplain management criteria, and communities that participate in the NFIP must adopt and enforce floodplain management regulations that incorporate the minimum criteria. 44 CFR 59.2(b) , 59.22(a)(3) , 60.1(d) . FEMA has determined that it is consistent with the purposes of the NFIA to allow communities to adopt more comprehensive floodplain management regulations that exceed the minimum requirements. 44 CFR 60.1(d) . Similarly, in its implementation of Executive Order 11988 , FEMA prohibits taking any action taken unless it is consistent with the NFIP minimum criteria or any more restrictive Federal, State or local floodplain management standards. 44 CFR 9.11(d)(6) .

49.   42 U.S.C. 4128(a) .

50.   42 U.S.C. 4104c and 4102 . Please note this rulemaking does not alter the minimum floodplain management criteria that communities adopt to participate in the NFIP. The NFIP is a program through which property owners in participating communities can purchase Federal flood insurance as a protection against flood losses. 42 U.S.C. 4011(a) . As a condition of eligibility, a community must adopt and enforce floodplain management regulations that incorporate NFIP minimum floodplain management criteria developed by the Administrator. 42 U.S.C. 4011(a) and (b) ; 42 U.S.C. 4102 ; 44 CFR 59.2(b) , 59.22(a)(3) , 60.1(d) . Further information regarding FEMA's minimum floodplain management standards for the NFIP can be found at 44 CFR part 59 et seq. Because this rule only applies to actions subject to the FFRMS, this rule does not change any FEMA standards applicable to community or individual participation in any aspect of the NFIP. In general, changes to 44 CFR part 59 et seq. would require a rulemaking to revise the appropriate sections of the CFR.

51.  FEMA published an interim final rule on December 27, 1979 ( 44 FR 76510 ) and a final rule on September 9, 1980 ( 45 FR 59520 ). Note this part also implements a related Executive Order 11990 , “Protection of Wetlands.” See 42 FR 26961 , May 25, 1977.

52.   44 CFR 9.4 defines the actions subject to the requirements, which include federal lands and facilities, providing federal funds for construction and improvements, and conducting activities or programs that affect land use.

53.  A complete list of FEMA programs to which Part 9 does not apply appears at 44 CFR 9.5 . The exemption for actions under the NFIP is located at 44 CFR 9.5(f) .

54.  For example, Part 9 requires FEMA to apply the 8-step process to a programmatic determination of categories of structures to be insured but does not require FEMA to apply an 8-step review to a determination of whether to insure each individual structure. See 44 CFR 9.5(g) .

55.   44 CFR 9.5(c) , (d) , (e) , and (g) .

56.   80 FR 6425 , Feb. 4, 2015. Section 5(c) of Executive Order 13690 specifically states that the order “is not intended to, and does not, create any right or benefit, substantive or procedural, enforceable at law or in equity by any party against the United States, its departments, agencies, or entities, its officers, employees, or agents, or any other person.”

57.   80 FR 6530 , Feb. 5, 2015.

58.  FEMA received approximately 556 separate submissions, which raised over 2700 separate issues and positions. Written comments were received at a series of eight in-person listening sessions across the country (135 submissions); verbal comments were shared during the public comment periods of these same listening sessions (74 commenters); comments were submitted through the FFRMS email address (20 submissions); comments were submitted through regulations.gov (326 submissions); and comments were submitted as part of a petition of support (1 submission).

59.   80 FR 64008 , Oct. 22, 2015.

60.   86 FR 27967 , May 25, 2021. See also Executive Order 13990 (“Protecting Public Health and the Environment and Restoring Science To Tackle the Climate Crisis”), 86 FR 7037 , Jan. 25, 2021 (revoking Executive Order 13807 ).

61.   See FEMA Policy 104-22-003, “Partial Implementation of the Federal Flood Risk Management Standard for Public Assistance (Interim),” June 3, 2022 found at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​fp-104-22-0003-partial-implemetnation-ffrms-pa-interim.pdf (last accessed Jan. 24, 2024) and FEMA Policy 206-21-003-0001, “Partial Implementation of the Federal Flood Risk Management Standard for Hazard Mitigation Assistance Program,” Dec. 7, 2022 found at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​policy-fp-206-21-003-0001-implementation-ffrms-hma-program_​122022.pdf (last accessed Jan. 24, 2024).

62.   88 FR 67870 , Oct. 2, 2023.

63.  Although the FFRMS describes various approaches for determining the higher vertical flood elevation and corresponding horizontal floodplain for Federally funded projects, it is not meant to be an “elevation” standard. The FFRMS is a resilience standard. The vertical flood elevation and corresponding horizontal floodplain determined using the approaches in the FFRMS establish the level to which a structure or facility must be resilient to. This may include using structural or non-structural methods to reduce or prevent damage; elevating a structure; or, where appropriate, designing it to adapt to, withstand, and rapidly recover from a flood event. See “Guidelines for Implementing Executive Order 11988 , Floodplain Management, and Executive Order 13690 , “Establishing a Federal Flood Risk Management Standard and a Process for Further Soliciting and Considering Stakeholder Input” (Oct. 8, 2015), found at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​implementing-guidelines-EO11988-13690_​10082015.pdf (last accessed Jan. 24, 2024).

64.   See Executive Order 13690 Section 2(i), 80 FR 6425 , 6426 (Feb. 4, 2015).

65.   See Revised Guidelines, pgs. 36-37.

66.   See Revised Guidelines at 53. The Revised Guidelines suggest agencies should apply a reasonableness standard to higher SLTT floodplain management standards. FEMA has historically deferred to higher local codes and standards from an SLTT government in 44 CFR 9.11(d)(6) and will continue the practice through this rulemaking, rather than applying a case-by-case reasonableness analysis and believes this is appropriate because of program-specific controls that ensure higher standards are reasonable. Specifically, in the PA program, if an SLTT government has adopted a code or standard that exceeds minimum standards set by FEMA, regulations at 44 CFR 206.226(d) require the code to be in place and adopted pre-disaster which guards against an SLTT government's adoption of unreasonably high codes and standards. With respect to mitigation projects, they are all required to be cost-effective as a minimum criteria of eligibility. See 42 U.S.C. 5170c(a) ; 42 U.S.C. 5133(b) ; 42 U.S.C. 4104c(c)(2)(A) . This project-by-project cost-effectiveness analysis should guard against any SLTT standards that are unreasonably high.

67.   See NPRM, 88 FR 67870 , 67900 and FEMA Proposed Policy: Federal Flood Risk Management Standard at pg. 5 (posted to the public docket at https://www.regulations.gov/​document/​FEMA-2023-0026-0005 ). See also https://www.fema.gov/​sites/​default/​files/​documents/​fema_​ffrms-floodplain-determination-job-aid.pdf (last accessed Jan. 24, 2024) and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0004 .

68.   Id at Section 1.6.

69.   See Revised Guidelines, Appendix H: Climate-Informed Science Approach and Resources, pg.5

70.   See Revised Guidelines, pg. 51 and Appendix H: Climate-Informed Science Approach and Resources, pg. 5.

71.  Available at https://www.whitehouse.gov/​wp-content/​uploads/​2023/​03/​Federal-Flood-Risk-Management-Standard-Climate-Informed-Science-Approach-CISA-State-of-the-Science-Report.pdf?​trk=​public_​post_​comment-text (last accessed Mar. 12, 2024).

72.  FFRMS CISA State of the Science Report, Coastal workflow starting on pg. 11 and Riverine workflow starting on pg. 38.

73.   Id. at pg. 5.

74.   See id.

75.   Id. at pgs. 21-22.

76.   Id. at pg. 23.

77.  The FFRMS CISA State of the Science Report identifies the latest interagency Federal guidance for regionally-based SLR projections as available and actionable by recommending that all agencies should use these data as part of a CISA approach. At pg. 22, the Report states “Federal agencies should apply this latest interagency Federal guidance for regionally-based SLR projections. Scenarios and time horizons should use a consistent national approach based on risk tolerance and criticality.” However, the Report also warns against using the simplified approach with SLR in areas subject to runup and overtopping on pg. 28 “Notably, areas subject to runup and overtopping can be very sensitive to changes in water level (including due to SLR) and the variability of the slope—so within a CISA implementation, these areas should be treated with appropriate analysis and not simple linear addition of flooding components.” Based on these guidelines, the FFRMS Job Aid establishes the use of simplified CISA in specific areas, namely in some coastal environments, specifically along low-lying coastal shorelines on the Atlantic and Gulf Coasts. See FFRMS Job Aid, pg. 10.

78.  Available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​ffrms-floodplain-determination-job-aid.pdf (last accessed Mar. 12, 2024).

79.  FFRMS CISA State of the Science Report, pg.5, Coastal workflow starting on pg. 11, and Riverine workflow starting on pg. 38.

80.  FFRMS Job Aid, pg. 10.

81.   Id.

82.  Available at https://www.fema.gov/​sites/​default/​files/​2020-04/​Available_​Flood_​Hazard_​Information_​Policy_​104-008-2.pdf (last accessed Mar. 12, 2024).

83.   See FFRMS Policy, pg. 5.

84.  FFRMS Job Aid, pgs. 8-9.

85.  FFRMS Job Aid, pgs. 8-9 and pgs.13-15.

86.   Id., pgs. 20-23.

87.   Id.

88.  FFRMS Job Aid, pg. 21.

89.  FFRMS Job Aid, pg. 8.

90.   Id., pgs. 8-9

91.   Id., pgs. 30-31.

92.   Id.

93.   See https://www.regulations.gov/​document/​FEMA-2023-0026-0007 and https://www.regulations.gov/​document/​FEMA-2023-0026-0004 .

94.   89 FR 25674 (Apr. 11, 2024).

95.  One commenter provided a duplicate comment posted to both the rulemaking and FFRMS policy comments.

96.  22 commenters expressed direct support for the rule while 19 other commenters expressed only specific recommendations to improve the rule.

97.  Note that FEMA first partially implemented the FFRMS by policy with respect to covered projects in existing floodplains in its Public Assistance and Hazard Mitigation Assistance programs. See FEMA Policy 104-22-003, “Partial Implementation of the Federal Flood Risk Management Standard for Public Assistance (Interim),” June 3, 2022 found at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​fp-104-22-0003-partial-implemetnation-ffrms-pa-interim.pdf (last accessed Jan. 24, 2024) and FEMA Policy 206-21-003-0001, “Partial Implementation of the Federal Flood Risk Management Standard for Hazard Mitigation Assistance Program,” Dec. 7, 2022 found at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​policy-fp-206-21-003-0001-implementation-ffrms-hma-program_​122022.pdf (last accessed Jan. 24, 2024). Some current FEMA actions may be subject to these partial implementation policies; however, those actions would not be subject to this final rule or policy.

98.   42 U.S.C. 4011(a) .

99.   42 U.S.C. 4011(a) and (b) ; 42 U.S.C. 4102 ; 44 CFR 59.2(b) , 59.22(a)(3) , 60.1(d) .

100.   See “Guidelines for Implementing Executive Order 11998 , Floodplain Management, and Executive Order 13690 , Establishing a Federal Flood Risk Management Standard and a Process for Further Soliciting and Considering Stakeholder Input,” 80 FR 64008 (Oct. 22, 2015) (providing notice of the availability of the Revised Guidelines in the docket for the rulemaking at https://www.regulations.gov/​document/​FEMA-2015-0006-0358 (main content) and https://www.regulations.gov/​document/​FEMA-2015-0006-0372 (appendices)) also available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​implementing-guidelines-EO11988-13690_​10082015.pdf (last accessed Mar. 11, 2024).

101.  Established by the 2013 Climate Action Plan, the Climate Task Force met with stakeholders from State, local, Tribal, and territorial governments; private businesses; trade associations; academic organizations; civil society; and other stakeholders to develop and provide recommendations in November 2014. President's State, Local, and Tribal Leaders Task Force on Climate Preparedness and Resilience, Recommendations to the President, (2014), available at https://obamawhitehouse.archives.gov/​sites/​default/​files/​docs/​task_​force_​report_​0.pdf at 7 (last accessed Jan. 24, 2024). FEMA, acting on behalf of the MitFLG and consistent with Executive Order 13690 , published a draft of the Revised Guidelines for notice and comment on February 5, 2015 at 80 FR 6530 . During the public comment period, over 25 meetings were held across the country with State, local, and Tribal officials and interested stakeholders to discuss the Revised Guidelines. There were also 9 public listening sessions across the country that were attended by over 700 participants from State, local, and Tribal governments, and other stakeholder organizations to discuss the Revised Guidelines. The final Revised Guidelines were published on October 22, 2015 at 80 FR 64008 . FEMA published a notice of proposed rulemaking to implement FFRMS initially in 2016 at 81 FR 57402 (Aug. 22, 2016) along with a notice of availability and request for comment on a FFRMS policy at 81 FR 56558 (Aug. 22, 2016) and a notice of availability regarding a draft report at 81 FR 64403 (Sept. 20, 2016).

102.  Available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​ffrms-floodplain-determination-job-aid.pdf (last accessed Mar. 12, 2024).

103.  TMAC 2023 Interim Report, available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​rm-tmac-2023-interim-report-30OCT2023.pdf (last accessed Mar. 28, 2024).

104.   42 U.S.C. 4101a .

105.   42 U.S.C. 4101b .

106.  Also known as Risk Rating 2.0, Equity in Action. See https://www.fema.gov/​flood-insurance/​risk-rating (last accessed Mar. 18, 2024).

107.   42 U.S.C. 5165a .

108.   42 U.S.C. 4331(b) .

109.   42 U.S.C. 4102 , 42 U.S.C. 4104c .

110.   42 U.S.C. 4332(2)(C) .

111.   42 U.S.C. 5121(b)(5) .

112.   42 U.S.C. 4011(a) .

113.   42 U.S.C. 4011(a) and (b) ; 42 U.S.C. 4102 ; 44 CFR 59.2(b) , 59.22(a)(3) , 60.1(d) .

114.   See “Guidelines for Implementing Executive Order 11998 , Floodplain Management, and Executive Order 13690 , Establishing a Federal Flood Risk Management Standard and a Process for Further Soliciting and Considering Stakeholder Input,” 80 FR 64008 (Oct. 22, 2015) (providing notice of the availability of the Revised Guidelines in the docket for the rulemaking at https://www.regulations.gov/​document/​FEMA-2015-0006-0358 (main content) and https://www.regulations.gov/​document/​FEMA-2015-0006-0372 (appendices)) also available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​implementing-guidelines-EO11988-13690_​10082015.pdf (last accessed Mar. 11, 2024).

115.   Sackett v. EPA, 598 U.S. 651 (2023).

116.  142 S. Ct. 2587 (2022).

117.   Id. at 2604.

118.   42 U.S.C. 5121 et seq.

119.   42 U.S.C. 4001 et seq.

120.   6 U.S.C. 101 et seq; see also 6 U.S.C. 314(a)(12) , which specifically charges the Administrator with supervising various grant programs authorized under the HSA. Such grant programs have long been governed by floodplain management regulations at 44 CFR part 9 , see, e.g., 44 FR 76510 (Dec. 27, 1979), 45 FR 59520 (Sept. 9, 1980). See also, e.g., 2 CFR 200.300(a) (directing Federal awarding agencies to manage and administer Federal awards in a manner so as to ensure that Federal funding is expended and associated programs are implemented in full accordance with the U.S. Constitution, Federal Law, and public policy requirements including, but not limited to, those protecting public welfare and the environment; and requiring the Federal awarding agency to communicate to the non-Federal entity all relevant public policy requirements, and incorporate them either directly or by reference in the terms and conditions of the Federal award.).

121.   15 U.S.C. 2229 and 2229a .

122.   42 U.S.C. 7701 et seq.

123.   See, e.g., 6 U.S.C. 609 (granting FEMA approval authority over grant funds for construction awards under its Homeland Security Grant Program, State Homeland Security Grant Program, Urban Area Security Initiative, Operation Stonegarden, Tribal Homeland Security Grant Program, and Nonprofit Security Grant Program); 6 U.S.C. 1182(d)(1) (granting DHS the authority to determine the grant requirements for the Intercity Bus Security Grant Program); 6 U.S.C. 1163(c)(1) (granting FEMA the authority to determine the grant requirements for the Intercity Passenger Rail grant program); 46 U.S.C. 70101 (granting DHS approval authority over grant funds for construction awards under the Port Security Grant Program); 6 U.S.C. 1135(c)(1) (granting DHS the authority to determine the grant requirements for the Transit Security Grant Program); 33 U.S.C. 467f-2(c)(2)(A) (granting FEMA the authority to set the minimum eligibility requirements for the Rehabilitation of High Hazard Dam Program).

124.   See 42 U.S.C. 5164 ; 42 U.S.C. 4128(a) and (b) .

125.   42 U.S.C. 5165a(a)(1)-(2) .

126.   See, e.g., Disaster Mitigation Act of 2000, Public Law 106-390 , 114 Stat. 1552 (Oct. 30, 2000); Post-Katrina Emergency Management Reform Act of 2006, Public Law 109-295 , 120 Stat. 1452 (Oct. 4, 2006); Sandy Recovery Improvement Act of 2013; Public Law 113-2 , 127 Stat. 47 (Jan. 29, 2013); Disaster Recovery Reform Act of 2018, Public Law 115-254 , 132 Stat. 3448 (Oct. 5, 2018).

127.   42 U.S.C. 4101a .

128.   42 U.S.C. 4101b .

129.  Revised Guidelines at pg. 13.

130.  Functionally dependent use means those actions which cannot perform their intended function unless they are located in or in close proximity to water. See 44 CFR 9.4 .

131.  Note that FEMA first partially implemented the FFRMS by policy with respect to covered projects in existing floodplains in its Public Assistance and Hazard Mitigation Assistance programs. See FEMA Policy 104-22-003, “Partial Implementation of the Federal Flood Risk Management Standard for Public Assistance (Interim),” June 3, 2022 found at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​fp-104-22-0003-partial-implemetnation-ffrms-pa-interim.pdf (last accessed Jan. 24, 2024) and FEMA Policy 206-21-003-0001, “Partial Implementation of the Federal Flood Risk Management Standard for Hazard Mitigation Assistance Program,” Dec. 7, 2022 found at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​policy-fp-206-21-003-0001-implementation-ffrms-hma-program_​122022.pdf (last accessed Jan. 24, 2024). Some current FEMA actions may be subject to these partial implementation policies; however, those actions would not be subject to this final rule or policy.

132.  The NFIP's floodplain management standards are generally found at 44 CFR 60.3 . There are variances and exceptions from the standards written into 60.3. Additionally, some communities have higher standards above the NFIP's floodplain management minimum requirements.

133.  A comprehensive list of FEMA programs to which Part 9 does not apply appears at 44 CFR 9.5 . The exemption for actions under the NFIP is located at 44 CFR 9.5(f) .

134.   See https://www.fema.gov/​emergency-managers/​national-preparedness/​equity (last accessed Jan. 24, 2024).

135.   See, e.g., Federal Highway Administration Hydraulic Engineering Circular No. 17, 2nd Ed: Highways in the River Environment—Floodplains, Extreme Events, Risk, and Resilience 2016, available at https://www.fhwa.dot.gov/​engineering/​hydraulics/​library_​arc.cfm?​pub_​number=​2&​id=​162 (last accessed Jan. 24, 2024), Federal Highway Administration Hydraulic Engineering Circular No. 25, 2nd Ed: Highways in the Coastal Environment October 2014, available at https://www.fhwa.dot.gov/​engineering/​hydraulics/​pubs/​nhi14006/​nhi14006.pdf (last accessed March 28, 2024), US Army Corps of Engineers Engineering and Construction Bulletin 2018-14: Guidance for Incorporating Climate Change Impacts to Inland Hydrology in Civil Works Studies, Designs, and Projects, available at https://wbdg.org/​ffc/​dod/​engineering-and-construction-bulletins-ecb/​usace-ecb-2018-14 (last accessed Jan. 24, 2024), and US Army Corps of Engineers Engineer Regulation No. 1100-2-8162: Incorporating Sea Level Change in Civil Works Programs, June 2019, available at https://www.publications.usace.army.mil/​USACE-Publications/​Engineer-Regulations/​udt_​43546_​param_​orderby/​Pub_​x0020_​Number/​udt_​43546_​param_​direction/​descending/​?udt_​43546_​param_​page=​3 (last accessed Jan. 24, 2024).

136.   https://www.fema.gov/​sites/​default/​files/​2020-05/​DRRA1235b_​Consensus_​BasedCodes_​Specifications_​and_​Standards_​for_​Public_​Assistance122019.pdf (last accessed Apr. 2, 2024).

137.   See FFRMS Policy, pg. 8, “Particularly in cases where elevation may not be feasible or appropriate for non-structure facilities, the FFRMS floodplain, determined according to the process described in section C of this policy, establishes the level to which a structure or facility must be resilient. Resilience measures include using structural or nonstructural methods to reduce or prevent damage; elevating a structure; or, where appropriate, designing it to adapt to, withstand and rapidly recover from a flood event.”

138.   See FFRMS Job Aid, pg. 14.

139.   42 U.S.C. 4011(a) .

140.   42 U.S.C. 4011(a) and (b) ; 42 U.S.C. 4102 ; 44 CFR 59.2(b) , 59.22(a)(3) , 60.1(d) .

141.   See “Guidelines for Implementing Executive Order 11998 , Floodplain Management, and Executive Order 13690 , Establishing a Federal Flood Risk Management Standard and a Process for Further Soliciting and Considering Stakeholder Input,” 80 FR 64008 (Oct. 22, 2015) (providing notice of the availability of the Revised Guidelines in the docket for the rulemaking at https://www.regulations.gov/​document/​FEMA-2015-0006-0358 (main content) and https://www.regulations.gov/​document/​FEMA-2015-0006-0372 (appendices)) also available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​implementing-guidelines-EO11988-13690_​10082015.pdf (last accessed Mar. 11, 2024).

142.   See “Federal Flood Risk Management Standard Climate-Informed Science Approach (CISA) State of the Science Report,” available at https://www.whitehouse.gov/​wp-content/​uploads/​2023/​03/​Federal-Flood-Risk-Management-Standard-Climate-Informed-Science-Approach-CISA-State-of-the-Science-Report.pdf?​trk=​public_​post_​comment-text (last accessed Jan. 24, 2024), https://www.fema.gov/​floodplain-management/​intergovernmental/​white-house-flood-resilience-interagency-working-group (last accessed Jan. 24, 2024), and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0007 .

143.  Available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​implementing-guidelines-EO11988-13690_​10082015.pdf (last accessed Jan. 24, 2024).

144.  Available at https://www.whitehouse.gov/​wp-content/​uploads/​2023/​03/​Federal-Flood-Risk-Management-Standard-Climate-Informed-Science-Approach-CISA-State-of-the-Science-Report.pdf?​trk=​public_​post_​comment-text (last accessed Jan. 24, 2024), https://www.fema.gov/​floodplain-management/​intergovernmental/​white-house-flood-resilience-interagency-working-group (last accessed Jan. 24, 2024), and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0007 .

145.  FFRMS CISA State of the Science Report, pg. 23.

146.   See https://www.fema.gov/​sites/​default/​files/​documents/​fema_​ffrms-floodplain-determination-job-aid.pdf (last accessed Jan. 24, 2024) and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0004 .

147.   See https://www.regulations.gov/​document/​FEMA-2023-0026-0004 .

148.   See https://www.fema.gov/​sites/​default/​files/​documents/​fema_​ffrms-floodplain-determination-job-aid.pdf (last accessed Jan. 24, 2024).

149.  Revised Guidelines, pgs. 16-17 and 50-52.

150.  FFRMS CISA State of the Science Report, pgs. 7-8.

151.   Id.

152.  FFRMS Job Aid, pgs. 7-11 generally.

153.   See “Federal Flood Risk Management Standard Climate-Informed Science Approach (CISA) State of the Science Report,” available at https://www.whitehouse.gov/​wp-content/​uploads/​2023/​03/​Federal-Flood-Risk-Management-Standard-Climate-Informed-Science-Approach-CISA-State-of-the-Science-Report.pdf?​trk=​public_​post_​comment-text (last accessed Jan. 24, 2024), https://www.fema.gov/​floodplain-management/​intergovernmental/​white-house-flood-resilience-interagency-working-group (last accessed Jan. 24, 2024), and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0007 .

154.  FFRMS CISA State of the Science Report, pgs. 22-23 and 28.

155.   See https://www.fema.gov/​sites/​default/​files/​documents/​fema_​ffrms-floodplain-determination-job-aid.pdf (last accessed Jan. 24, 2024) and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0004 .

156.  Available at https://www.fema.gov/​sites/​default/​files/​2020-04/​Available_​Flood_​Hazard_​Information_​Policy_​104-008-2.pdf (last accessed Mar. 12, 2024). The FFRMS proposed and final policies reference this existing FEMA policy in Section D.1.

157.  Available at https://www.whitehouse.gov/​wp-content/​uploads/​2023/​03/​Federal-Flood-Risk-Management-Standard-Climate-Informed-Science-Approach-CISA-State-of-the-Science-Report.pdf?​trk=​public_​post_​comment-text (last accessed Jan. 24, 2024), https://www.fema.gov/​floodplain-management/​intergovernmental/​white-house-flood-resilience-interagency-working-group (last accessed Jan. 24, 2024), and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0007 .

158.   See https://www.fema.gov/​sites/​default/​files/​documents/​fema_​ffrms-floodplain-determination-job-aid.pdf (last accessed Jan. 24, 2024) and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0004 .

159.   See https://www.regulations.gov/​document/​FEMA-2023-0026-0004 .

160.   See https://www.fema.gov/​sites/​default/​files/​documents/​fema_​ffrms-floodplain-determination-job-aid.pdf (last accessed Jan. 24, 2024).

161.   89 FR 25674 (Apr. 11, 2024).

162.  Section 4, Executive Order 13690 , 80 FR 6425 (Feb. 4, 2015).

163.   See Revised Guidelines at pgs. 16-17.

164.   See Revised Guidelines at pgs. 16-17.

165.  Available at https://www.whitehouse.gov/​wp-content/​uploads/​2023/​03/​Federal-Flood-Risk-Management-Standard-Climate-Informed-Science-Approach-CISA-State-of-the-Science-Report.pdf?​trk=​public_​post_​comment-text (last accessed Jan. 24, 2024), https://www.fema.gov/​floodplain-management/​intergovernmental/​white-house-flood-resilience-interagency-working-group (last accessed Jan. 24, 2024), and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0007 .

166.   See https://www.fema.gov/​sites/​default/​files/​documents/​fema_​ffrms-floodplain-determination-job-aid.pdf (last accessed Jan. 24, 2024) and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0004 .

167.   See FFRMS Job Aid, pg. 14.

168.  The FEMA BCA Toolkit recommends using a 50-year project useful lift for public buildings and a 25-year project useful life for nonresidential buildings.

169.   See https://www.fema.gov/​sites/​default/​files/​documents/​fema_​ffrms-floodplain-determination-job-aid.pdf (last accessed Jan. 24, 2024) and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0004 .

170.   See Revised Guidelines pg. 23 for information on flooding characteristics and Appendix H of the Revised Guidelines for information on the CISA, pgs. 20-22.

171.   See https://www.fema.gov/​emergency-managers/​national-preparedness/​equity (last accessed Jan. 24, 2024).

172.  Available at https://www.fema.gov/​sites/​default/​files/​2020-04/​Available_​Flood_​Hazard_​Information_​Policy_​104-008-2.pdf (last accessed Mar. 12, 2024).

173.  Section 4, Executive Order 13690 , 80 FR 6425 (Feb. 4, 2015).

174.   See Revised Guidelines, pg. 57.

175.  Available at https://www.fema.gov/​sites/​default/​files/​2020-04/​Available_​Flood_​Hazard_​Information_​Policy_​104-008-2.pdf (last accessed Mar. 12, 2024).

176.   See Revised Guidelines, pg. 57.

177.   See section C.3.a note 13, pg. 4.

178.  For example, FEMA Recovery Interim Policy 104-009-11 Version 2.1, “Consensus-Based Codes, Specifications and Standards for Public Assistance” (December 20, 2019) requires “application of the latest nationwide consensus-based codes, specifications and standards that incorporate hazard resistance for PA funded projects” including buildings, electric power, roads, bridges, potable water, and wastewater. Available at https://www.fema.gov/​sites/​default/​files/​2020-07/​fema_​DRRA-1235b-public-assistance-codes-standards-interim-policy.pdf (last accessed Jan. 24, 2024). HMA also specifically references ASCE 24 and ASCE 7 in the HMA Program and Policy Guide available at https://www.fema.gov/​grants/​mitigation/​hazard-mitigation-assistance-guidance (last accessed Jan. 24, 2024).

179.   See “Building Codes Strategy” March 2022 available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​building-codes-strategy.pdf (last accessed Jan. 24, 2024).

180.   See Revised Guidelines, pg. 57.

181.   See Revised Guidelines, pg. 57.

182.   See FFRMS Policy, pg. 8, Section G.1.d “FEMA guidance provides technical information on elevation methods for new construction and retrofitting existing structures with various types of foundations. Guidance is available in NFIP Technical Bulletins (1-11), FEMA P-758: Substantial Improvement/Substantial Damage Desk Reference, FEMA P-936: Floodproofing Non-Residential Buildings, FEMA P-348: Protecting Building Utility Systems from Flood Damage, FEMA P-467-2: Floodplain Management Bulletin on Historic Structures, among other FEMA publications.”

183.  Hazard Mitigation Assistance Program and Policy Guide, pg. 85 available at https://www.fema.gov/​grants/​mitigation/​guide (last accessed Mar. 20, 2024).

184.  FFRMS policy, pg.8.

185.   See FEMA Policy 104-008-2: Guidance on the Use of Available Flood Hazard Information, available at https://www.fema.gov/​sites/​default/​files/​2020-04/​Available_​Flood_​Hazard_​Information_​Policy_​104-008-2.pdf (last accessed Mar. 20, 2024).

186.  Available at https://www.fema.gov/​sites/​default/​files/​2020-04/​Available_​Flood_​Hazard_​Information_​Policy_​104-008-2.pdf (last accessed Jan. 24, 2024).

187.  FFRMS CISA State of the Science Report, pgs. 22-23.

188.   89 FR 25674 (Apr. 11, 2024).

189.   See “Federal Flood Risk Management Standard Climate-Informed Science Approach (CISA) State of the Science Report,” available at https://www.whitehouse.gov/​wp-content/​uploads/​2023/​03/​Federal-Flood-Risk-Management-Standard-Climate-Informed-Science-Approach-CISA-State-of-the-Science-Report.pdf?​trk=​public_​post_​comment-text (last accessed Jan. 24, 2024), https://www.fema.gov/​floodplain-management/​intergovernmental/​white-house-flood-resilience-interagency-working-group (last accessed Jan. 24, 2024), and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0007 .

190.   See Revised Guidelines, pg. 67.

191.   89 FR 25674 (Apr. 11, 2024).

192.   See Revised Guidelines, pg. 57.

193.   See FFRMS Job Aid, pg. 14.

194.   See Revised Guidelines, pgs. 16-17, 50-52.

195.   See FFRMS CISA State of the Science Report, pgs. 7-8.

196.   See https://www.fema.gov/​sites/​default/​files/​documents/​fema_​ffrms-floodplain-determination-job-aid.pdf (last accessed Jan. 24, 2024) and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0004 .

197.  Available at https://www.whitehouse.gov/​wp-content/​uploads/​2023/​03/​Federal-Flood-Risk-Management-Standard-Climate-Informed-Science-Approach-CISA-State-of-the-Science-Report.pdf?​trk=​public_​post_​comment-text (last accessed Jan. 24, 2024), https://www.fema.gov/​floodplain-management/​intergovernmental/​white-house-flood-resilience-interagency-working-group (last accessed Jan. 24, 2024), and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0007 .

198.   See https://www.regulations.gov/​document/​FEMA-2023-0026-0004 .

199.   See https://www.fema.gov/​sites/​default/​files/​documents/​fema_​ffrms-floodplain-determination-job-aid.pdf (last accessed Jan. 24, 2024).

200.  FFRMS Job Aid, pgs. 20-21. NOAA viewer available at https://coast.noaa.gov/​slr/​ (last accessed Mar. 28, 2024).

201.   See Jesse M. Kennan, “A climate intelligence arms race in financial markets,” Science 365 (6459), pp. 1240-1243, abstract available at https://www.science.org/​doi/​10.1126/​science.aay8442 (last accessed Mar. 21, 2024).

202.  The FFRMS CISA State of the Science Report identifies the latest interagency Federal guidance for regionally-based SLR projections as available and actionable by recommending that all agencies should use these data as part of a CISA approach. At pg. 22, the Report states “Federal agencies should apply this latest interagency Federal guidance for regionally-based SLR projections. Scenarios and time horizons should use a consistent national approach based on risk tolerance and criticality.” However, the Report also warns against using the simplified approach with SLR in areas subject to runup and overtopping on pg. 28 “Notably, areas subject to runup and overtopping can be very sensitive to changes in water level (including due to SLR) and the variability of the slope—so within a CISA implementation, these areas should be treated with appropriate analysis and not simple linear addition of flooding components.” Based on these guidelines, the FFRMS Job Aid establishes the use of simplified CISA in specific areas, namely in some coastal environments, specifically along low-lying coastal shorelines on the Atlantic and Gulf Coasts. See FFRMS Job Aid, pg. 10.

203.   See FFRMS CISA State of the Science Report at i.

204.  Available at https://www.fema.gov/​sites/​default/​files/​2020-04/​Available_​Flood_​Hazard_​Information_​Policy_​104-008-2.pdf (last accessed Jan. 24, 2024).

205.  Available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​implementing-guidelines-EO11988-13690_​10082015.pdf (last accessed Jan. 24, 2024).

206.   See https://www.whitehouse.gov/​wp-content/​uploads/​2023/​03/​Federal-Flood-Risk-Management-Standard-Climate-Informed-Science-Approach-CISA-State-of-the-Science-Report.pdf?​trk=​public_​post_​comment-text (last accessed Dec. 14, 20 last accessed Jan. 24, 202423) and also posted to the public docket with this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0007 .

207.   80 FR 6425 (Feb. 4, 2015).

208.   See https://www.fema.gov/​fact-sheet/​future-flood-risk-data-ffrd (last accessed Mar. 26, 2024).

209.   See https://www.regulations.gov/​document/​FEMA-2023-0026-0013 .

210.   See TMAC 2021 Annual Report, Chapter 3 Future Conditions available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​2021-technical-mapping-advisory-annual-report.pdf (last accessed Apr. 1, 2024).

211.  FEMA Policy 104-0008-2: Guidance on the use of available flood hazard information, available at https://www.fema.gov/​sites/​default/​files/​2020-04/​Available_​Flood_​Hazard_​Information_​Policy_​104-008-2.pdf (last accessed Mar. 27, 2024).

212.   89 FR 25674 (Apr. 11, 2024).

213.  Available at https://www.fema.gov/​sites/​default/​files/​2020-04/​Available_​Flood_​Hazard_​Information_​Policy_​104-008-2.pdf (last accessed Jan. 24, 2024).

214.   See “Implementation of Guidance for Federal Departments and Agencies on Indigenous Knowledge,” Nov. 30, 2022, found at https://www.whitehouse.gov/​ceq/​news-updates/​2022/​12/​01/​white-house-releases-first-of-a-kind-indigenous-knowledge-guidance-for-federal-agencies/​ (last accessed Jan. 24, 2024).

215.   See FFRMS Job Aid, pg. 14.

216.  As a result of climate change, flood events are on the rise. Climate change is increasing flood risk through (1) more “extreme” rainfall events,” caused by a warmer atmosphere holding more water vapor and changes in regional precipitation patterns; and (2) sea-level rise. See Rob Bailey, Claudio Saffioti, and Sumer Drall, Sunk Costs: The Socioeconomic Impacts of Flooding 3 and 8, Marsh McLennan (2021).

217.  Federal Budget Exposure to Climate Risk. OMB Assessment found https://www.whitehouse.gov/​wp-content/​uploads/​2022/​04/​ap_​21_​climate_​risk_​fy2023.pdf (last accessed Jan. 24, 2024).

218.  Note that FEMA first partially implemented the FFRMS by policy with respect to covered projects in existing floodplains in its Public Assistance and Hazard Mitigation Assistance programs. See FEMA Policy 104-22-003, “Partial Implementation of the Federal Flood Risk Management Standard for Public Assistance (Interim),” June 3, 2022 found at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​fp-104-22-0003-partial-implementation-ffrms-pa-interim.pdf (last accessed Jan. 24, 2024) and FEMA Policy 206-21-003-0001, “Partial Implementation of the Federal Flood Risk Management Standard for Hazard Mitigation Assistance Program,” Dec. 7, 2022 found at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​policy-fp-206-21-003-0001-implementation-ffrms-hma-program_​122022.pdf (last accessed Jan. 24, 2024). Some current FEMA actions may be subject to these partial implementation policies; however, those actions would not be subject to this final rule or policy.

219.  FEMA's appeals and arbitrations process for PA can be found at 44 CFR 206.206 and HMGP's appeals process can be found at 44 CFR 206.440 .

220.   See https://www.fema.gov/​emergency-managers/​national-preparedness/​equity (last accessed Jan. 24, 2024).

221.  Information on FEMA disaster and other declarations, see https://www.fema.gov/​disaster/​declarations (last accessed Mar. 27, 2024). For FEMA disaster and other declarations specific to the commenter, see https://www.fema.gov/​disaster/​declarations?​field_​dv2_​declaration_​date_​value%5Bmin%5D=​2019&​field_​dv2_​declaration_​date_​value%5Bmax%5D=​2024&​field_​dv2_​declaration_​type_​value=​All&​field_​dv2_​incident_​type_​target_​id_​selective=​All&​field_​dv2_​state_​territory_​tribal_​value%5B%5D=​MT (last accessed Mar. 27, 2024).

222.  For example, see FEMA, Press Release, Biden-Harris Administration Announces Nearly $2 Billion in Available Funding to Increase Climate Resilience Nationwide, https://www.fema.gov/​press-release/​20231012/​biden-harris-administration-announces-nearly-2-billion-available-funding (last accessed Mar. 27, 2024) (“As part of the Administration's Justice40 initiative, the BRIC and FMA programs aim to deliver 40 percent of their overall benefits to disadvantaged communities that are marginalized, overburdened by pollution, and underserved . . . FEMA is providing up to 90 percent federal cost share for FMA in disadvantaged communities, relative to a standard cost share of 75 percent. Designated Community Disaster Resilience Zones (CDRZs) are eligible for up to 90 percent federal cost share for BRIC, relative to a standard cost share of 75 percent . . . FEMA continues to not require a Benefit-Cost Analysis as a condition to apply for an Economically Disadvantaged Rural Community, federally recognized tribal government, or a subapplicant with a hazard mitigation project within or primarily benefiting a Community Disaster Resilience Zone. FEMA will review the hazard mitigation project subapplications that are eligible for selection and may assist such communities with developing a BCA.”).

223.  Note that FEMA first partially implemented the FFRMS by policy with respect to covered projects in existing floodplains in its Public Assistance and Hazard Mitigation Assistance programs. See FEMA Policy 104-22-003, “Partial Implementation of the Federal Flood Risk Management Standard for Public Assistance (Interim),” June 3, 2022 found at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​fp-104-22-0003-partial-implemetnation-ffrms-pa-interim.pdf (last accessed Jan. 24, 2024) and FEMA Policy 206-21-003-0001, “Partial Implementation of the Federal Flood Risk Management Standard for Hazard Mitigation Assistance Program,” Dec. 7, 2022 found at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​policy-fp-206-21-003-0001-implementation-ffrms-hma-program_​122022.pdf (last accessed Jan. 24, 2024). Some current FEMA actions may be subject to these partial implementation policies; however, those actions would not be subject to this final rule or policy.

224.   See Environmental Planning and Historic Preservation Responsibilities and Program Requirements, available at https://www.fema.gov/​sites/​default/​files/​2020-07/​fema_​ehp_​requirements_​2018.pdf (last accessed Mar. 27, 2024).

225.  “Climate-Related Financial Risk,” 86 FR 27967 (May 20, 2021).

226.  See 44 CFR 9.16 , 9.17 .

227.   See, e.g., 2 CFR 200.339 and 200.342 ; see also 44 CFR 206.206 (appeals and arbitration process for PA), 44 CFR 206.115 (appeals process for IA), 44 CFR 206.440 (HMGP and HMGP Post-Fire's appeals process); and “Hazard Mitigation Assistance Program and Policy Guide,” pg. 211-216, 229-234, 240-241, and 247 available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​hma_​guide_​08232023_​v1.pdf (last accessed April 2, 2024) (appeals process for HMGP, HMGP Post-Fire, BRIC, and FMA), “Public Assistance Program and Policy Guide, pgs. 39-41 available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​pappg-v4-updated-links_​policy_​6-1-2020.pdf (last accessed Mar. 12, 2024).

228.   80 FR 6425 (Feb. 4, 2015).

229.   See https://www.regulations.gov/​document/​FEMA-2023-0026-0013 .

230.   See Section F of the FFRMS Policy, “Where possible, the Agency shall use natural systems, ecosystem processes, and nature-based solutions.”

231.   See https://www.regulations.gov/​document/​FEMA-2023-0026-0005 .

232.  Established by the 2013 Climate Action Plan, the Climate Task Force met with stakeholders from State, local, Tribal, and territorial governments; private businesses; trade associations; academic organizations; civil society; and other stakeholders to develop and provide recommendations in November 2014. President's State, Local, and Tribal Leaders Task Force on Climate Preparedness and Resilience, Recommendations to the President, (2014), available at https://obamawhitehouse.archives.gov/​sites/​default/​files/​docs/​task_​force_​report_​0.pdf at 7 (last accessed Jan. 24, 2024). FEMA, acting on behalf of the MitFLG and consistent with Executive Order 13690 , published a draft of the Revised Guidelines for notice and comment on February 5, 2015 at 80 FR 6530 . During the public comment period, over 25 meetings were held across the country with State, local, and Tribal officials and interested stakeholders to discuss the Revised Guidelines. There were also 9 public listening sessions across the country that were attended by over 700 participants from State, local, and Tribal governments, and other stakeholder organizations to discuss the Revised Guidelines. The final Revised Guidelines were published on October 22, 2015 at 80 FR 64008 . FEMA published a notice of proposed rulemaking to implement FFRMS initially in 2016 at 81 FR 57402 (Aug. 22, 2016) along with a notice of availability and request for comment on a FFRMS policy at 81 FR 56558 (Aug. 22, 2016) and a notice of availability regarding a draft report at 81 FR 64403 (Sept. 20, 2016).

233.  Established by the 2013 Climate Action Plan, the Climate Task Force met with stakeholders from State, local, Tribal, and territorial governments; private businesses; trade associations; academic organizations; civil society; and other stakeholders to develop and provide recommendations in November 2014. President's State, Local, and Tribal Leaders Task Force on Climate Preparedness and Resilience, Recommendations to the President, (2014), available at https://obamawhitehouse.archives.gov/​sites/​default/​files/​docs/​task_​force_​report_​0.pdf at 7 (last accessed Jan. 24, 2024). FEMA, acting on behalf of the MitFLG and consistent with Executive Order 13690 , published a draft of the Revised Guidelines for notice and comment on February 5, 2015 at 80 FR 6530 . During the public comment period, over 25 meetings were held across the country with State, local, and Tribal officials and interested stakeholders to discuss the Revised Guidelines. There were also 9 public listening sessions across the country that were attended by over 700 participants from State, local, and Tribal governments, and other stakeholder organizations to discuss the Revised Guidelines. The final Revised Guidelines were published on October 22, 2015 at 80 FR 64008 . FEMA published a notice of proposed rulemaking to implement FFRMS initially in 2016 at 81 FR 57402 (Aug. 22, 2016) along with a notice of availability and request for comment on a supplementary policy at 81 FR 56558 (Aug. 22, 2016) and a notice of availability regarding a draft report at 81 FR 64403 (Sept. 20, 2016).

234.   See https://www.fema.gov/​emergency-managers/​national-preparedness/​equity (last accessed Jan. 24, 2024).

235.  Revised Guidelines, pg. 20.

236.  For example, FEMA found that for a project with a 75% FEMA/25% applicant cost share, the cost to an applicant to elevate a structure above the BFE to meet FEMA's FFRMS requirements using the FVA+2 (1.91 percent of construction cost) represented less than 0.5% of the total project cost, or an average of an additional $4,775 in applicant cost share on an original total project cost of $1,000,000. See A Benefit Analysis of Increased Freeboard for Public and Nonresidential Buildings in Riverine and Coastal Floodplains, posted to the public docket of this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0003 .

238.  Public meetings were held at a range of locations across the country at varied times to maximize participation. Meetings were held in Fairfax, VA; Seattle, WA; Dallas, TX; New York, NY; Ames, IA; Biloxi, MS; Sacramento, CA; and Hampton Roads, VA. See generally Guidelines for Implementing Executive Order 11988 , Floodplain Management non-rulemaking docket available at https://www.regulations.gov/​docket/​FEMA-2015-0006/​document for the public meeting notices and transcripts from the meetings.

239.  Established by the 2013 Climate Action Plan, the Climate Task Force met with stakeholders from State, local, Tribal, and territorial governments; private businesses; trade associations; academic organizations; civil society; and other stakeholders to develop and provide recommendations in November 2014. President's State, Local, and Tribal Leaders Task Force on Climate Preparedness and Resilience, Recommendations to the President, (2014), available at https://obamawhitehouse.archives.gov/​sites/​default/​files/​docs/​task_​force_​report_​0.pdf at 7 (last accessed Jan. 24, 2024). FEMA, acting on behalf of the MitFLG and consistent with Executive Order 13690 , published a draft of the Revised Guidelines for notice and comment on February 5, 2015 at 80 FR 6530 . The final Revised Guidelines were published on October 22, 2015 at 80 FR 64008 . FEMA published a notice of proposed rulemaking to implement FFRMS initially in 2016 at 81 FR 57402 (Aug. 22, 2016) along with a notice of availability and request for comment on a supplementary policy at 81 FR 56558 (Aug. 22, 2016) and a notice of availability regarding a draft report at 81 FR 64403 (Sept. 20, 2016).

240.   See https://www.fema.gov/​emergency-managers/​national-preparedness/​equity (last accessed Jan. 24, 2024).

241.   See “Instructions on Implementation of the Environmental Planning and Historic Preservation Responsibilities and Program Requirements,” pgs. 4 and 15, available at https://www.fema.gov/​sites/​default/​files/​2020-07/​fema_​ehp_​instructions_​implementation_​2018.pdf (last accessed Apr. 22, 2024).

242.   See FFRMS policy, pg. 8.

243.  Available at https://www.regulations.gov/​document/​FEMA-2023-0026-0004 and https://www.fema.gov/​sites/​default/​files/​documents/​fema_​ffrms-floodplain-determination-job-aid.pdf (last accessed Jan. 24, 2024).

244.   Sackett v. EPA, 598 U.S. 651 (2023).

245.   Sackett v. EPA, 598 U.S. 651 (2023).

246.   See 44 CFR 9.9(e)(3) .

247.  FEMA's website has information and materials available in languages other than English, including Spanish, French, German, Arabic, Hausa, Vietnamese, Portuguese, Chinese, Japanese, Hindi, Myanmar (Burmese), Korean, Nepali, Somali, Swahili, Tagalog, Tongan, Creole, Fijian, and Russian. See https://www.fema.gov/​disaster/​recover/​languages (last accessed Mar. 28, 2024).

248.  FEMA Policy FP-256-23-001, available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​policy-language-access.pdf (last accessed Mar. 27. 2024).

249.  FEMA's Language Access Policy requires the agency to have processes in place to regularly identify and assess the language assistance needs of the public and requires written translation of vital documents in languages other than English based on assessments of need and capacity. See Principles A. and C. of the policy available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​policy-language-access.pdf (last accessed Mar. 27. 2024).

250.   See e.g. “FEMA Public Notice: 4618-DR-PA-Pennsylvania Individual Assistance, Public Assistance and HMGP” available at https://www.fema.gov/​disaster/​4618/​publicnotice (last accessed June 11, 2024); “DR-4673-FL EHP Public Notice 001” available at https://www.fema.gov/​disaster-federal-register-notice/​dr-4673-fl-ehp-public-notice-001 (last accessed June 11, 2024).

251.  FEMA Section 504 Implementation Plan, available at https://www.fema.gov/​sites/​default/​files/​2020-06/​fema_​section-504-implementation-plan.pdf (last accessed Mar. 27, 2024).

252.   See FEMA, OpenFEMA Data Sets, https://www.fema.gov/​about/​openfema/​data-sets (last accessed Mar. 25, 2024).

253.   See https://www.fema.gov/​emergency-managers/​national-preparedness/​equity (last accessed Jan. 24, 2024).

254.   Sackett v. EPA, 598 U.S. 651 (2023).

255.   See FFRMS policy, pg. 8.

256.   44 CFR 60.3(c)(10) .

257.   44 CFR 9.11(d)(4) .

258.   See TMAC 2023 Interim Report, available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​rm-tmac-2023-interim-report-30OCT2023.pdf (last accessed Mar. 28, 2024).

259.   See 24 CFR 55.12(c)(8)(i) and (ii) as of March 28, 2024.

260.   89 FR 30850 (Apr. 23, 2024).

261.   See CRS Coordinator's Field Manual 2017 and 2021 Addendum, available at https://www.fema.gov/​floodplain-management/​community-rating-system (last accessed Apr. 4, 2024).

262.  Available at https://www.whitehouse.gov/​wp-content/​uploads/​2023/​03/​Federal-Flood-Risk-Management-Standard-Climate-Informed-Science-Approach-CISA-State-of-the-Science-Report.pdf?​trk=​public_​post_​comment-text (last accessed Jan. 24, 2024), https://www.fema.gov/​floodplain-management/​intergovernmental/​white-house-flood-resilience-interagency-working-group (last accessed Jan. 24, 2024), and posted to the public docket for this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0007 .

263.   See https://www.fema.gov/​flood-insurance/​rules-legislation/​congressional-reauthorization/​legislative-proposals (last accessed Jan. 24, 2024).

264.   See e.g. “Hazard Mitigation Assistance Guidance,” pgs. 59-60 available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​hma_​guide_​08232023_​v1.pdf (last accessed April 2, 2024), “Public Assistance Program and Policy Guide, pg. 151 available at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​pappg-v4-updated-links_​policy_​6-1-2020.pdf (last accessed Mar. 12, 2024).

265.   See https://www.regulations.gov/​document/​FEMA-2023-0026-0013 . Specifically, see section 7.11.5 “Elevation Requirement Impacts on THUs.”

266.  Available at https://obamawhitehouse.archives.gov/​sites/​default/​files/​final_​principles_​and_​requirements_​march_​2013.pdf (last accessed Jan. 24, 2024) and https://obamawhitehouse.archives.gov/​sites/​default/​files/​docs/​prg_​interagency_​guidelines_​12_​2014.pdf (last accessed Jan. 24, 2024).

267.   See “Principles and Requirements for Federal Investments in Water Resources at pg. 1, (Mar. 2013) available at https://obamawhitehouse.archives.gov/​sites/​default/​files/​final_​principles_​and_​requirements_​march_​2013.pdf (last accessed Apr. 29, 2024) (“It is intended that these Principles and the supporting Requirements and Guidelines be applied to a broad range of Federal investments that by purposes, either directly or indirectly, affect water quality or water quantity”); see also and “Interagency Guidelines,” available at https://obamawhitehouse.archives.gov/​sites/​default/​files/​docs/​prg_​interagency_​guidelines_​12_​2014.pdf (last accessed Apr. 29, 2024).

268.  OMB Circular A-4, Regulatory Analysis, September 17, 2003, pages 33-34. Available at: https://www.reginfo.gov/​public/​jsp/​Utilities/​a-4.pdf (last accessed Apr. 29, 2024).

269.  Construction Cost Index History. Engineering News Record (ENR). Available at: https://www.enr.com/​economics/​historical_​indices/​construction_​cost_​index_​history (last accessed: Mar. 18, 2024).

270.  FFRMS CISA State of the Science Report, pg. 22, available at https://www.whitehouse.gov/​wp-content/​uploads/​2023/​03/​Federal-Flood-Risk-Management-Standard-Climate-Informed-Science-Approach-CISA-State-of-the-Science-Report.pdf?​trk=​public_​post_​comment-text (last accessed April 4, 2024). The report recommends that agencies use the latest interagency Federal guidance for regionally-based SLR projections. The underlying SLR science reported used for the report is based on the IPCC AR6 which uses shared socioeconomic pathways (SSPs) rather than the older Representative Concentration Pathways (RCPs). The five SLR scenarios described in Sweet et al. (2022), page 10, are based on global mean sea level (GMSL) target values at 2100. These sea level scenarios are related to but distinct from the emissions pathway scenarios in the IPCC AR6. The intermediate SLR scenario corresponds to a GMSL target value in 2100 of 1m and the intermediate-high SLR corresponds to GMSL target value in 2100 of 1.5M.

271.  FFRMS Job Aid, pg. 21.

272.  OMB Circular A-4, Regulatory Analysis, September 17, 2003, pages 33-34. Available at: https://www.reginfo.gov/​public/​jsp/​Utilities/​a-4.pdf (last accessed Apr. 29, 2024).

273.  OMB Circular A-4, Regulatory Analysis, September 17, 2003, page 10. Available at: https://www.reginfo.gov/​public/​jsp/​Utilities/​a-4.pdf (last accessed Apr. 29, 2024).

274.  OMB Circular A-4, Regulatory Analysis, September 17, 2003, pages 9-10. Available at: https://www.reginfo.gov/​public/​jsp/​Utilities/​a-4.pdf (last accessed Apr. 29, 2024).

275.  FEMA assumed the reference to DOE-TVA is to the Tennessee Valley Authority although FEMA notes that TVA is not a component of the Department of Energy.

276.  For example, USACE has a suite of resources on its website related to its implementation of CISA in its Civil Works Programs which detail how project delivery teams must consider the effects of sea level change when formulating, selecting, and evaluating project alternatives, and how to characterize potential project vulnerabilities to the effects of climate change on inland hydroclimatology. See https://www.iwr.usace.army.mil/​Missions/​Flood-Risk-Management/​Flood-Risk-Management-Program/​About-the-Program/​Policy-and-Guidance/​Federal-Flood-Risk-Management-Standard/​ . However, this information did not include relevant data that FEMA could use in its economic analysis related to the costs of implementation for facilities.

277.  FEMA-2023-0026-0018.

278.  The Third National Climate Assessment. https://nca2014.globalchange.gov , (last accessed Apr. 29, 2024).

279.  FEMA, A Benefits Analysis of Increased Freeboard for Public and Nonresidential Buildings in Riverine and Coastal Floodplains, July 2002, available at: https://www.regulations.gov/​document/​FEMA-2023-0026-0003 .

280.  National Institute of Building Sciences. Multi-Hazard Mitigation Council. “Natural Hazard Mitigation Saves.” 2019. https://www.nibs.org/​files/​pdfs/​NIBS_​MMC_​MitigationSaves_​2019.pdf (last accessed Apr. 29, 2024). See, for example, Table 5: BCRs for various heights above BFE for new coastal V-zone buildings and Table 2-2: Summary BCR results for sampled counties susceptible to riverine flooding.

281.  A Benefits Analysis of Increased Freeboard for Public and Nonresidential Buildings in Riverine and Coastal Floodplains. FEMA. Draft, July 2022, pg. 16, available at: https://www.regulations.gov/​document/​FEMA-2023-0026-0003 .

282.  A Benefits Analysis of Increased Freeboard for Public and Nonresidential Buildings in Riverine and Coastal Floodplains. FEMA. Draft, July 2022, pg. 16, available at: https://www.regulations.gov/​document/​FEMA-2023-0026-0003 .

283.  FEMA, 2016 Evaluation of the Benefits of Freeboard for Public and Nonresidential Buildings in Coastal Areas. Available at: https://www.regulations.gov/​document/​FEMA-2015-0006-0379 .

284.  BCA Reference Guide, Appendix D. Project Useful Life Summary (June 2009). Available at: https://www.fema.gov/​sites/​default/​files/​2020-04/​fema_​bca_​reference-guide.pdf (last accessed May 15, 2024).

285.  If FEMA limited the analysis to only 10 years of impacts, it would consider all of the costs and transfers but only a small portion of the benefits from additional protection from flood events because the life of the structure is more than 10 years. After year 10, the final rule would continue to impact FEMA projects funding new construction, substantial improvements or repairs to fix substantial damage. To estimate the future number of impacted structures, FEMA used the average number of projects that would have been affected by this rule had it been in place over the past 10-year period, assuming the next 10 years would look largely like the past 10 years. FEMA chose to limit the analysis to 10 years of affected structures because estimating the number of affected projects and their associated benefits further into the future—that is, further from historical disaster data would become less accurate as conditions change and the expected frequency and severity of major disasters increases. Accordingly, FEMA's analysis focuses on the 50-year impacts of the rule on projects that take place in the initial 10-year period, for a total period of analysis spanning 60 years.

286.  The final rule and policy contain content that is interrelated but not identical. For purposes of this analysis, FEMA considers both documents as a single proposal.

287.  The one percent annual chance elevation refers to the elevation to which floodwater is anticipated to rise during the 1 percent annual chance flood (also known as the base or 100-year flood). Under Executive Order 11988 , non-critical actions must be elevated or floodproofed to at least the one percent annual chance elevation (or base flood elevation). Critical actions must be elevated or floodproofed to at least the 0.2 percent annual chance flood (or 500-year) elevation.

288.  A critical action is any activity for which even a slight chance of flooding would be too great. A non-critical action is any activity not considered a critical action.

289.  For all projects in coastal areas, if the 0.2 percent annual chance flood elevations do not account for the effects of wave action, the appropriate FVA must be used to determine the FFRMS floodplain.

290.  While application of the 0.2PFA may provide a more consistent reduction of flood risk as it is probability based, the relationship to the FVA varies depending on topography ( i.e., in some instances the 0.2PFA may result in a lower flood elevation than the FVA). Application of only the 0.2PFA without a comparison to the FVA may result in building to a higher resilience standard than is necessary.

291.  The Special Flood Hazard Area is the area designated on FEMA regulatory mapping products depicting a 1 percent annual chance floodplain.

292.  National Oceanic and Atmospheric Administration. U.S. Department of Commerce. “Climate change impacts.” https://www.noaa.gov/​education/​resource-collections/​climate/​climate-change-impacts . Last accessed February 15, 2022.

293.  U.S. Global Change Research Program (2014). Climate Change Impacts in the United States: The Third National Climate Assessment. Available at: https://repository.library.noaa.gov/​view/​noaa/​19485 . Page 20. Last accessed: April 16, 2024.

294.  Ibid [page 21].

295.  Ibid [page 21].

296.  Global Change Research Program (2014). Climate Change Impacts in the United States: The Third National Climate Assessment. Available at: https://repository.library.noaa.gov/​view/​noaa/​19485 . Page 20. Last accessed: April 16, 2024.

297.  Environmental Protection Agency (EPA). Supplementary Material for the Regulatory Impact Analysis for the Supplemental Proposed Rulemaking. “Standards of Performance for New, Reconstructed, and Modified Sources and Emissions Guidelines for Existing Sources: Oil and Natural Gas Sector Climate Review.” Page 36. https://www.epa.gov/​system/​files/​documents/​2022-11/​epa_​scghg_​report_​draft_​0.pdf . Last accessed: September 14, 2023.

298.  The EPA uses the Framework for Assessing Changes To Sea-level (FACTS) and Building Blocks for Relevant Ice and Climate Knowledge (BRICK) sea-level rise models for their projections.

299.   Climate.gov . “U.S. billion-dollar weather and climate disasters.” https://www.ncei.noaa.gov/​access/​billions/​summary-stats/​US/​1980-2022 . Last accessed October 31, 2023. Flood related damages are from flooding, severe storms, and tropical cyclones. Data is CPI adjusted. Severe storms can include wind-related damages, but the source does not separate data out by type of damage.

300.  FEMA used an average of the number of affected projects during the prior 10-year period to estimate the average annual impacts of the future 10-year period.

301.  The 50-year period is based on the 2022 Report, which assumed 50-year useful life for public buildings. Therefore, FEMA estimated such benefits over a 50-year period. Please see section 7.14.2 of the RIA for more information.

302.  If FEMA limited the analysis to only 10 years of impacts, it would consider all of the costs and transfers but only a small portion of the benefits from additional protection from flood events because the life of the structure is more than 10 years. After year 10, the final rule would continue to impact FEMA projects funding new construction, substantial improvements or repairs to fix substantial damage, but FEMA chose to limit the analysis to 10 years of affected structures because it used 10 years of historical data, and due to changing conditions, projecting impacts past 10 years would become less accurate due to an expected increase in the frequency and severity of major disasters. Accordingly, FEMA's analysis focuses on the 50-year impacts of the rule on projects that take place in the initial 10-year period, for a total period of analysis spanning 60 years.

303.  From 2013-2022, for PA, FEMA funded a total of 199,993 projects for $172.6 billion (CPI adjusted to 2022 dollars). Of that total number of projects, FEMA funded $22.8 billion (CPI adjusted to 2022 dollars) for all PA Category E projects, which is about 13.2 percent ($22.8 billion ÷ $172.6 billion) of the total FEMA PA funding. For PA Category E projects within the floodplain, FEMA funded $1.2 billion (CPI adjusted to 2022 dollars) which is about 0.7 percent ($1.2 billion ÷ $172.6 billion) of all FEMA PA funding or 2,437 projects which is about 1.2 percent (2,437 projects ÷ 199,993 projects) of all FEMA PA projects.

From 2013-2022, for HMA, FEMA funded a total of 8,761 projects. There are no data fields that show whether a project is located in a floodplain. Therefore, FEMA used the assumption that all HMA projects were located in the floodplain. This may lead to an overestimate in the costs associated with HMA projects.

From 2013-2022, for IA, FEMA funded a total of 13,576 THU and 184 PHC projects. FEMA assumed that 11.1 percent of IA PHC and THU projects would be located in the floodplain, based on PA project data. Accordingly, FEMA estimated a 20 (184 PHC projects × 11.1 percent) PHC projects and 1,507 (13,576 THU projects × 11.1 percent) THU projects in the current floodplain in years 1-10 of the analysis.

304.  These counts are based on the number of closed or obligated projects at the time of analysis. It can take several years for a project to close out or reach the obligation status after the disaster year.

305.  FEMA estimated a range of possible costs since it was not able to accurately estimate the number of new construction projects that would elect to elevate versus those that would elect to floodproof, so estimates are provided for both the cost of elevating all new construction projects and the costs of floodproofing all new construction projects.

306.  FEMA Public Assistance. https://www.fema.gov/​fact-sheet/​fema-public-assistance-0 . Accessed April 23, 2024.

307.  For FEMA's primary estimate, FEMA used 59 inches of SLR, due to it being the closest SLR option to FEMA's +5-ft assumption for CISA. CISA is the preferred approach for FFRMS if the data are available. Since 5 ft is equivalent to 60 inches (5 × 12 inches per foot), 59-inch SLR is the closest SLR option that FEMA has available to use for this portion of the analysis.

308.  PA Category A-Debris Removal and Category B-Emergency Protective Measures do not fund building or repair of structures and are not subject to the FFRMS.

309.  FEMA. “FEMA B-797 Hazard Mitigation Field Book: Roadways.” 2010. Available at https://www.fema.gov/​sites/​default/​files/​2020-07/​b797_​hazmit_​handbook.pdf .

310.   See 44 CFR 60.3 .

See also Floodproofing. FEMA. Available at: https://www.fema.gov/​glossary/​floodproofing . Last accessed: January 11, 2023.

311.  Projects outside of the 1 percent annual chance floodplain, but below the required level will need to be elevated to the required level. These projects require elevations of different levels, depending on the structure's current elevation. FEMA assumes that half of the projects will need to be elevated 1-ft and the other half or projects will need to be elevated 2-ft. This assumption was made because FEMA is unsure of the actual number of projects that will need to be elevated by 1-ft or 2-ft and so assumed that it will be an even proportion for each height. IA projects is all considered non-critical actions and will not require a 3-ft level.

312.  For analysis purposes, FEMA calculated the expanded floodplain using the mid-point (and rounded down) to +5-ft CISA which would expand the floodplain by 26 percent. FEMA opted for the mid-point for CISA because this is the best approach with available data. Please see further explanation in the appropriate CISA sections: 7.4.3, 7.5.3, and 7.6.3.

313.  FEMA's project level data for IA, PA, and HMA delineate whether projects are in the Special Flood Hazard Area (1 percent annual chance floodplain) but do not show whether they are in the 0.2 percent chance floodplain. For critical actions, FEMA was unable to determine the baseline number of critical actions that are located in the 0.2 percent chance floodplain. Regardless of which floodplain the project is in, a critical action must be elevated at or above the 0.2 percent annual chance flood level.

314.  Partial Implementation of the Federal Flood Risk Management Standard for Public Assistance (Interim). FEMA Policy 104-22-0003. Available at: https://www.fema.gov/​sites/​default/​files/​documents/​fema_​fp-104-22-0003-partial-implemetnation-ffrms-pa-interim.pdf . Last accessed: July 20, 2022.

315.  Under 44 CFR 9.4 , Floodplain means the “lowland and relatively flat areas adjoining inland and coastal waters including, at a minimum, that area subject to a one percent or greater chance of flooding in any given year. Wherever in this regulation the term floodplain is used, if a critical action is involved, floodplain shall mean the area subject to inundation from a flood having a 0.2 percent chance of occurring in any given year (500-year floodplain). Floodplain does not include areas subject only to mudflow until FIA adopts maps identifying M Zones.”

316.  Under 44 CFR 59.1 , Substantial Damage means “damage of any origin sustained by a structure whereby the cost of restoring the structure to its before damaged condition would equal or exceed 50 percent of the market value of the structure before the damage occurred.”

317.  Under 44 CFR 9.4 , Substantial Improvement means “any repair, reconstruction or other improvement of a structure or facility, which has been damaged in excess of, or the cost of which equals or exceeds, 50% of the market value of the structure or replacement cost of the facility (including all public facilities as defined in the Disaster Relief Act of 1974) (a) before the repair or improvement is started, or (b) if the structure or facility has been damaged and is proposed to be restored, before the damage occurred. If a facility is an essential link in a larger system, the percentage of damage will be based on the relative cost of repairing the damaged facility to the replacement cost of the portion of the system which is operationally dependent on the facility. The term substantial improvement does not include any alteration of a structure or facility listed on the National Register of Historic Places or a State Inventory of Historic Places.”

318.  Under 44 CFR 9.4 , New Construction means “the construction of a new structure (including the placement of a mobile home) or facility or the replacement of a structure or facility which has been totally destroyed.”

319.  Partial Implementation of the Federal Flood Risk Management Standard for Hazard Mitigation Assistance Programs (Interim). FEMA Policy FP-206-21-0003. Available at: https://www.fema.gov/​sites/​default/​files/​documents/​fema_​policy-fp-206-21-0003-partial-mplementation-ffrms-hma-programs-interim.pdf . Last accessed: July 20, 2022.

320.  FEMA implemented an update to the HMA interim policy on December 2022. This updated interim policy provides updated elevation requirements for critical and non-critical actions involving structures as defined in 44 CFR part 9.4 located in a designated floodplain. The updated interim policy also provides updated requirements for elevating and floodproofing structures funded under HMA programs. The RIA does not address the changes in the updated HMA interim policy.

321.  The 1 percent annual chance floodplain is currently also defined as the Special Flood Hazard Area under the NFIP.

322.  Partial Implementation of the Federal Flood Risk Management Standard for Hazard Mitigation Assistance Programs. FEMA Policy 206-21-003-0001. Available at: https://www.fema.gov/​sites/​default/​files/​documents/​fema_​policy-fp-206-21-003-0001-implementation-ffrms-hma-program_​122022.pdf . Last accessed: December 30, 2022.

323.  FEMA limited its dollar-valuation to the projects impacted in the first 10 years after the rule's effective date. FEMA has considered the resulting costs, benefits, and transfer payments of the final rule on those projects over a 50-year period, for a total of 60 years. The costs and transfers occur in the first 10 years of the 60-year period because that is when the initial investment to elevate or floodproof them to meet the FFRMS requirements takes place. This is an upfront cost that occurs when the project is constructed. However, the benefits of the final rule are realized over the 50-year useful life of the affected structures.

324.  FEMA has created a range for the administrative costs: between if all projects used the FFSST (low estimate) and if all used the Job Aid (high estimate). FEMA acknowledges that there may be situations where a combination of the FFSST and Job Aid may be used. However, FEMA was unable to estimate how many would use the FFSST and how many would use the Job Aid since the FFSST is currently being improved. In reality, the administrative costs will likely fall somewhere within the low and high estimates.

325.  A Benefits Analysis of Increased Freeboard for Public and Nonresidential Buildings in Riverine and Coastal Floodplains. FEMA. Draft, July 2022. Available at: https://www.regulations.gov/​document/​FEMA-2023-0026-0003 . Last accessed: March 22, 2024.

326.  Representative Concentration Pathways (RCP) are projected future emissions and concentration trajectories for climate change models that account for the increase in greenhouse gas, aerosol, and chemically active gas emissions. According to the Environmental Protection Agency, they define RCP as the following. RCP 4.5: This scenario assumes a stabilization in GHG emissions shortly after 2100. RCP 8.5: This scenario is characterized by increasing GHG emissions over time, and factors in the highest GHG concentration levels of all the scenarios by 2100.

Changes Over Time. EPA. Available at: https://www.epa.gov/​enviroatlas/​changes-over-time . Last accessed: December 1, 2023.

327.  FEMA developed the BCA Toolkit to perform an analysis of cost-effectiveness of mitigation projects. The BCA Toolkit uses Office of Management and Budget cost-effectiveness guidelines and FEMA-approved methodologies and tools to complete a benefit-cost analysis. The tool can be found here: https://www.fema.gov/​grants/​tools/​benefit-cost-analysis#toolkit .

328.  2016 Evaluation of the Benefits of Freeboard for Public and Nonresidential Buildings in Coastal Areas. https://www.regulations.gov/​document/​FEMA-2015-0006-0379 . Page 4.

329.  Category E projects are public buildings and contents. See “Public Assistance Program and Policy Guide” Page 51, at https://www.fema.gov/​sites/​default/​files/​documents/​fema_​pappg-v4-updated-links_​policy_​6-1-2020.pdf .

330.  Costs for the FVA may be a better comparison because they represent 2 or 3 feet of freeboard, depending on criticality. However, the number of projects using FVA and CISA differ, making such a comparison difficult.

331.  To obtain the total costs as in Section 7.12, add each individual approach to the FEMA admin cost. For example, CISA + FEMA admin = total CISA cost.

332.  To obtain the total costs as in Section 7.12, add each individual approach to the FEMA admin cost. For example, CISA + FEMA admin = total CISA cost.

333.  Because it is more expensive to elevate substantial repair projects than to floodproof them, FEMA assumes that all substantial repair projects will choose to floodproof.

334.  FEMA has calculated the primary estimates by calculating the average of the minimum and the maximum estimates for respective each percent. For example, for the primary 3 percent benefits, FEMA calculated the average for 3 percent discount minimum and 3 percent discount maximum.

335.  In addition to the FEMA-administered grant programs discussed in this analysis (IA, PA, HMA, and programs administered by GPD), FEMA also provides flood insurance through the NFIP. FEMA does not apply 44 CFR part 9 to non-grant site specific actions under the NFIP.

336.  This report is available at regulations.gov under docket ID FEMA-2023-0026.

337.  The cost of elevating an existing structure is significantly higher than the cost of retrofitting the structure to be floodproofed, so FEMA assumed that substantial improvement projects would elect to floodproof rather than elevate.

338.  The population of PA Category E projects includes all “Public Buildings” grants from 2013-2022 that received substantial improvement floodproofing or new construction funding. Because of the large population, FEMA used Slovin's formula and a 90 percent confidence interval to determine the sample size. Slovin's formula: n = N/(1+N*e ‸ 2). Therefore, 1,154/(1 + 1,154 × 0.1 ‸ 2) = 92 (rounded).

339.  FEMA was unable to obtain 10-years of historical data from 2013-2022 for HMA due to changes within the program's database. Therefore, FEMA used the best available data for years 2010 through 2019 instead.

340.  The other project type related to flood mitigation is acquisition. Generally, acquisition projects are for open space purposes and restore the natural and beneficial functions of the floodplain. Property acquisitions that result in relocated structures would be subject to FFRMS elevation and floodproofing requirements if the structure is relocated within the FFRMS floodplain. HMA data does not break out relocation costs from acquisition costs, so FEMA is unable to estimate additional relocation expenses for acquisition projects.

341.  In FEMA's dataset, HMA recipients only included project titles and not the name of the grantee. This prevented FEMA from determining if a grant recipient was a small entity. Since PA and HMA provide funding to similar entities (States, Tribal governments, local governments, and certain non-profit organizations) for disaster related activity, FEMA used the percentages of small entity grant recipients found in PA Category E as a proxy for HMA small entities.

342.  Because of the large population, FEMA used Slovin's formula and a 90 percent confidence interval to determine the sample size. Slovin's formula: n = N/(1+N*e‸2). Therefore, 1,036/(1 + 1,036 × 0.1‸2) = 91 (rounded).

343.  Because of the large population, FEMA used Slovin's formula and a 90 percent confidence interval to determine the sample size. Slovin's formula: n = N/(1+N*e‸2). Therefore, 120/(1 + 120 × 0.1‸2) = 55 (rounded).

344.  Because of the large population, FEMA used Slovin's formula and a 90 percent confidence interval to determine the sample size. Slovin's formula: n = N/(1+N*e‸2). Therefore, 208/(1 + 208 × 0.1‸2) = 68 (rounded).

345.  Because of the large population, FEMA used Slovin's formula and a 90 percent confidence interval to determine the sample size. Slovin's formula: n = N/(1+N*e‸2). Therefore, 314/(1 + 314 × 0.1‸2) = 76 (rounded).

346.  Because of the large population, FEMA used Slovin's formula and a 90 percent confidence interval to determine the sample size. Slovin's formula: n = N/(1+N*e‸2). Therefore, 84/(1 + 84 × 0.1‸2) = 46 (rounded).

347.  According to historical HMA data, there have been an average of 63 elevation projects and only 4 floodproofing projects per year.

348.  FEMA, “2008 Supplement to the 2006 Evaluation of the National Flood Insurance Program's Building Standards” Table 3, available at https://www.fema.gov/​sites/​default/​files/​2020-07/​fema_​nfip_​2008_​freeboard_​report_​0.pdf (last accessed Apr. 29, 2024).

349.  FEMA expects that increased costs to applicants will be minimal. For example, FEMA found that for a project with a 75% FEMA/25% applicant cost share, the cost to an applicant to elevate a structure above the BFE to meet FEMA's FFRMS requirements using the FVA+2 (1.91 percent of construction cost) represented less than 0.5% of the total project cost, or an average of an additional $4,775 in applicant cost share on an original total project cost of $1,000,000. See A Benefit Analysis of Increased Freeboard for Public and Nonresidential Buildings in Riverine and Coastal Floodplains, posted to the public docket of this rulemaking at https://www.regulations.gov/​document/​FEMA-2023-0026-0003 .

350.  The White House, “President Obama's Climate Action Plan, 2nd Anniversary Progress Report—Continuing to cut carbon, pollution, protect American communities, and lead internationally.” June 2015 found at https://obamawhitehouse.archives.gov/​sites/​default/​files/​docs/​cap_​progress_​report_​final_​w_​cover.pdf (last accessed Jan. 24, 2024).

BILLING CODE 9111-66-P

BILLING CODE 9111-66-C

[ FR Doc. 2024-15169 Filed 7-10-24; 8:45 am]

  • Executive Orders

Reader Aids

Information.

  • About This Site
  • Accessibility
  • No Fear Act
  • Continuity Information

IMAGES

  1. A Case Study on Distribution Management

    case study in distribution management

  2. Sales and Distribution Management Case Study

    case study in distribution management

  3. Wal-Mart Supply Chain Management Case Study Distribution Management By

    case study in distribution management

  4. (PDF) Warehouse Management System and Business Performance: Case Study

    case study in distribution management

  5. PPT

    case study in distribution management

  6. Distribution strategies with case study

    case study in distribution management

VIDEO

  1. 02 Marketing Channels in the Supply Chain DISTRIBUTION MANAGEMENT

  2. answer for case study of sales and distribution management

  3. Sales and Distribution Management Assignment Quiz Week -4 (2024)

  4. Sales and Distribution Management week -1 Assignment 2024🔥

  5. Goalkeeper Case Study

  6. Castrol

COMMENTS

  1. Case Study: Wal-Mart's Distribution and Logistics System

    Case Study: Wal-Mart's Distribution and Logistics System. As the world's largest retailer with net sales of almost $419 billion for the fiscal year 2011, Wal-Mart is considered a "best-in-class" company for its supply chain management practices. These practices are a key competitive advantage that have enabled Wal-Mart to achieve ...

  2. Case Study and Distribution

    Case Study: Smelling the Coffee with JCB's Teletruk. Logistics Business Magazine. JUNE 7, 2019. The company produces and distributes some 6 million litres of milk per week from its processing facility in Acton, West London and operates additional retail distribution sites in Leeds, Manchester, Derby, Coventry, Cardiff, Birmingham and Plympton in Devon. . The company's Acton site operates ...

  3. Distribution Channels: Articles, Research, & Case Studies on

    Too much corporate emphasis on payroll management may motivate managers to operate their stores with insufficient labor capacity that, in turn, degrades financial performance. Emphasis on payroll management can also degrade employee morale. Closed for comment; 0 Comments.

  4. Distribution: Articles, Research, & Case Studies on Distribution- HBS

    Many companies build their businesses on open source software, code that would cost firms $8.8 trillion to create from scratch if it weren't freely available. Research by Frank Nagle and colleagues puts a value on an economic necessity that will require investment to meet demand. 12 Dec 2023. Research & Ideas.

  5. Distribution Management: Definition, Advantages & Strategies

    Distribution management is the process used to oversee the movement of goods from supplier to manufacturer to wholesaler or retailer and finally to the end consumer. Numerous activities and processes are involved, including raw good vendor management, packaging, warehousing, inventory, supply chain, logistics and sometimes even blockchain.

  6. PDF Warehousing and Logistics Case Study

    Warehousing and Logistics Case Study. tices Among States During COVID-19 In the 21st century, public organizations have increasingly shifted to an on-demand just-in-time model of pro. urement and supply chain management. This model has been useful for shrinking bud-gets by cutting out the overhead costs associated with operating a warehousing ...

  7. Distribution Inventory Management Case Studies

    Miller Welding Supply. Maintaining Miller Welding Supply's legacy distribution management system took three employees five to six hours per day. Learn how SalesPad by Cavallo cut that overhead to improve the company's speed and flexibility. View Case Study.

  8. Case study: Dell—Distribution and supply chain innovation

    In a year's time, Dell's venture had $6 million in annual sales. In 1985, Dell changed his strategy to begin offering built-to-order computers. That year, the company generated $70 million in sales. Five years later, revenues had climbed to $500 million, and by the end of 2000, Dell's revenues had topped an astounding $25 billion.

  9. Case Study, Distribution and Logistics

    SCM Research. JUNE 29, 2020. Norrman & Jansson's (2004) casestudy on Ericsson's supply chain risk management (SCRM) practices is definitely part of the canon of SCM literature. International Journal of Physical Distribution & Logistics Management. After 15 years, it was time for an update.

  10. (PDF) Outbound Logistics and Distribution Management

    This chapter outlines the core definitions and objectives for outbound logistics and distribution management (Sect. 14.1) before providing an extensive case study for this specific topic (Sect. 14.2).

  11. A 'Case Study' on Distribution Channels

    Remember that one of the most important factors to consider when evaluating Distribution Channels would be the cost to serve. It can lead to some excellent alternative Distribution Strategies. Editor's Note: This post was originally published on September 08, 2021, under the title "A 'Case Study' on Distribution Channels and Thinking ...

  12. (PDF) Case Studies in Channels of Distribution

    Abstract. Case studies were employed as research tools, for undergraduate and MBA students for 25+ years. The International Management course was taught in two classes at an undergraduate Business ...

  13. (PDF) Case Studies in Channels of Distribution

    E-Leader Croatia 2011 Case Studies in Channels of Distribution Donald K. Hsu, PhD Associate Professor Division of Business Administration Dominican College Orangeburg, New York, USA Abstract Case studies were employed as research tools, for undergraduate and MBA students for 25+ years. The International Management course was taught in two ...

  14. A Distribution Case Study: Optimizing Center Activities

    In this distribution case study, we examine the implementation of technology to optimize activities within a distribution center and increase visibility and productivity while reducing inventory. This case study is a review of distribution center optimization. ... Provides inventory management at two facilities - one internal (150,000+ sq. ft ...

  15. Case Studies from Logistics industries

    Case Study - Fashion industry logistics: Gant. Capitalise on the retail expertise and capabilities of Noatum Logistics, including our robust warehouse management technologies and local capacity. The benefits of greater inventory visibility and control would cascade into other supply chain functions including transportation, warehousing ...

  16. Demand management in downstream wholesale and retail distribution: a

    This study lends insight into the use of demand management techniques to improve efficiency in downstream wholesale and retail distribution, thereby enhancing sustainability and profitability of business. To serve mainly as a case study and an illustration of the approach, the scope of the study is limited to six stores in the distribution ...

  17. Sales and Distribution Management Short Case Studies

    Sales and Distribution Management ICMR Case Collection provides teachers, corporate trainers, and management professionals with a variety of teaching and reference material. The collection consists of case studies and research reports on a wide range of companies and industries - both Indian and international. The collection contains several kinds of case studies like Business Environment ...

  18. Nestlé India: Adopting a Regional Approach in its Distribution Strategy

    The case is structured to achieve the following teaching objectives: Understand the importance of an efficient distribution and logistics management system in reducing costs and creating value for customers. Get insights into the distribution operations and the distribution channels utilized by a leading FMCG company.

  19. Logistics‐driven packaging innovation: a case study at IKEA

    International Journal of Retail & Distribution Management Logist ics-driven packaging innovat ion: a case st udy at IKEA Daniel Hellström Fredrik Nilsson Article information: To cite this document: Daniel Hellström Fredrik Nilsson, (2011),"Logistics-driven packaging innovation: a case study at IKEA", International Journal of Retail & Distribution Management, Vol. 39 Iss 9 pp. 638 - 657 ...

  20. Case Study: 7/11 Distribution Management

    CASE STUDY: 7/11 DISTRIBUTION MANAGEMENT - Free download as PDF File (.pdf), Text File (.txt) or read online for free. This document provides background information on 7-Eleven Philippines, including its establishment, operations, target markets, and promotional activities. Specifically, it discusses 7-Eleven Philippines' history and license from its parent company in the US, its employees and ...

  21. A Case Study on Distribution Management

    Business Query Resolution Approach - A Case. Study on Distribution Management(Page 1 of 3) Client Situation. Client Query. • The company is manufacturing a range of drugs. The company wants to understand the current distribution. channel structure and tips to understand how to leverage the current distribution channel prevalent in the ...

  22. Microsoft: A Case Study in Strategy Transformation

    HBR On Strategy curates the best case studies and conversations with the world's top business and management experts, to help you unlock new ways of doing business. New episodes every week.

  23. Ongoing Strategizing in Practice: The Case of the Metropolitan Economic

    Academy of Management Annual Meeting Proceedings includes abstracts of all papers and symposia presented at the annual conference, plus 6-page abridged versions of the "Best Papers" accepted for inclusion in the program (approximately 10%). Papers published in the Proceedings are abridged because presenting papers at their full length could preclude subsequent journal publication.

  24. Generative AI as an Enabler of Business Model Innovation: A Multiple

    Generative AI is transforming industries and business functions at a rapid pace. This paper contributes to the understanding of the transformative role that Generative AI plays in driving business model innovation (BMI). Through a comprehensive multiple-case study approach, this study delves into the drivers, barriers, and opportunities that Generative AI provides in context to the three ...

  25. What Can an All-in-One Event Management Platform Do?

    According to Forrester, the market for all-in-one event management platforms is considered "mature." The report's top identified current market dynamics in the event tech industry include macroeconomic factors and buyers' budgetary pressures, the rise of AI as a disruptor, and the growing importance of fully integrating event platforms ...

  26. BRE announces winners of BREEAM Awards 2024

    Gillian Charlesworth, CEO of BRE, said: "We are thrilled to recognise some of the greatest sustainability achievements in the built environment at this year's BREEAM Awards. "Embracing science-based sustainability methodologies like BREEAM can deliver significant impacts for businesses, investors and for society as a whole.

  27. Implantable cardiac monitor and leadless pacemaker in the management of

    Case presentation. An 83-year-old man with a history of syncope was the focus of this case study. An implantable cardiac monitor (ICM) recorded occasional high-degree atrioventricular block in the patient. Subsequently, the Micra AV was implanted via the left femoral vein, and its settings were adjusted in accordance with data obtained from the ...

  28. 3 Lessons from The Washington Post's Leadership Turmoil

    The leadership questions surrounding new Washington Post CEO Will Lewis serve as a case study in the challenges of bringing in an outsider to lead an organization, highlighting the importance of ...

  29. Land

    Using Xi'an as a case study, this research applies the above methods to explain the distribution of travel distance differences caused by spatiotemporal heterogeneity at the station level, providing an analytical framework for similar issues in other urban subway networks.

  30. Federal Register :: Updates to Floodplain Management and Protection of

    Start Preamble Start Printed Page 56929 AGENCY: Federal Emergency Management Agency, Department of Homeland Security. ACTION: Final rule. SUMMARY: On October 2, 2023, the Federal Emergency Management Agency (FEMA) published a notice of proposed rulemaking (NPRM) and supplementary policy that proposed to implement the Federal Flood Risk Management Standard (FFRMS) and update the agency's 8-step ...